Professional Documents
Culture Documents
Daily Events
None
GT-1 Activities
Time hrs
Maximum vibration at GT-1 was noted as 3.8mm/s on generator bearing-2 (39V-
0:07 5A) load 341 MW, ,Mvars 115, lube oil temperature 49.1°C, and Frequency
50.30Hz.
Note GT-1 evap cooler problem persisting. PTW extended for one week.
GT-1 at base load AFDP=9.17 ,CF= 6.71, FS=1.67, Carbon brushes temperature
Note remained 42,41,40°C during the night.
GT-2 Activities
Time hrs
Maximum vibration at GT-2 was noted as 10.0 mm/s on generator bearing-2 (39V-
8:13 5B) load 389 MW, Mvars 83 .lube oil temperature 48.9°C and Frequency 50.16 Hz.
STG Activities
Time hrs
17:39
ST lube oil TCV abnormally closed during operation, got normal after resetting
breaker. Informed I&C.
HRSG Activities
Time hrs
12:12 HRSG-2, SCR-1 fan started for vibration measurement at 10% speed.
12:22
SCR-1, fan speed gradually increased to 50%, current 22amp, vibration D.E
2.9mm/sec and gas flow 6029m3/hour.
12:36
SCR-2, fan speed gradually increased to 50%, current 22.08amp, vibration D.E
1.9mm/sec.
12:41 SCR-2 fan stopped
Electrical Activities
Time hrs
BOP Activities
Time hrs
Fire fighting system de-isolated after completion of maintenace work but again
20:50 leakage observed from hydrant#12 .Maintenace team tighted the hydrant bolt and
sytem normalized.
22:09 Fire fighting system pressurizing completed.
Defects
Auxiliary Load
Total Auxiliary
KV MW Amp KV MW Amp (MWh)
Aux Bus Bar-GT1 11.20 3.99 298.00 Aux Bus Bar-STG-1 11.48 4.60 371.00
464.59
Aux Bus Bar-GT2 11.45 3.0 233 Aux Bus Bar-STG-2 6.42 8.17 523
Gas Consumption
HBS Meter (MMSCfd) 150.7 H2 Consumption (m3) 28.15 10.35 4.16
DM Water
0.00 DM Water Consumption (m3) 736.00
Production (m3)