New Construction Commissioning Process Activities, Deliverables, and Responsibilities

Chapter 1

Step Activity Deliverable Normally Provided By For Use By


1. Project commissioning Contract and work orders, Owner Owner
initiation roles and responsibilities
2. Owner’s Project OPR document Owner with assistance from Owner, design and
Requirements design and Commissioning Commissioning
Teams Teams
3. Basis of Design BoD document Design Team Owner, design and
Commissioning
Teams
4. Commissioning Plan Cx Plan CxP with input from Owner, Cx and Construction
Design Team, and contractor Teams, authority
Chapter 3

having jurisdiction
(AHJ)
5. Contractor Cx Project specifications Design Team and CxP Contractors and
requirements suppliers
6. Design review Design review report CxP Owner, Design Team
Chapter 4

7. Submittal review Submittal review report CxP Design Team,


contractors, suppliers
8. Cx designated systems Installation, inspection, Contractors, manufacturers, Contractors and
inspections, functional and functional test reports, CxP, and team suppliers
performance testing performance test reports
9. Issues and resolution log Issues and resolution logs CxP and team Owner, Design and
Chapter 5

Commissioning
Teams, contractors
10. Develop Systems Manual Systems Manual Contractors with review by CxP Contractors, Owner,
operators
11. Training Training plan and reports Contractors and manufacturers Operators
Appendix A

with review by CxP


12. Preliminary Cx report Preliminary Cx report CxP Owner, contractors,
AHJ
13. Postoccupancy operation Additional information, CxP and building operations Owner, operators
testing, and updates to personnel
reports
Appendix B

14. Commissioning reports Preliminary and final CxP Owner, operators,


Cx reports AHJ
Appendix B
Appendix B