Professional Documents
Culture Documents
ENGINEERING DEPARTMENT
CONFIDENTIALITY: All the SOPs should be treated confidential and shall not be shown to unauthorized persons.
CSH Pharmaceuticals (Pvt.) Ltd. Lahore
SOP NO. ENG/GEN-001/01
1. OBJECTIVE
This procedure outlines the method for administration of equipment predictive/preventive
maintenance program.
2. REASON
2.1. To describe the minimum GMP requirements for a site maintenance schedule.
2.2. To ensure that lubricants, seals, gaskets, filters or other product contact Items used in
manufacturing areas are not sources of significant product contamination.
2.3 To ensure that equipment used for the control and release of product is suitably maintained.
2.4 To describe an authorized procedure for maintenance of plant and equipment according to
master preventive maintenance schedule.
3. SCOPE
This procedure applies to all plant equipment in CSH Pharmaceutical (Pvt.) Ltd. Lahore
4. ENVIRONMENTAL, HEALTH AND SAFETY PROTECTION
There are no significant hazards or special instructions relating to the process/activities
described in this SOP.
6.7.3 No Impact:
Equipment, machine or systems which neither has direct impact or indirect
impact on product quality, e.g. Lifts, ladders and trolley etc.
6.8 Preventive Maintenance Plan Review
Engineering management must reviews the Preventive Maintenance plan periodically to
confirm that contents are still effecting the frequency must be based on an assessment of
the risk to product quality and must not be greater than 3 years. Such reviews must be
documented.
Note:-
All planned activities must be conducted within 30 days of scheduled date month. If
delayed Engineering Manager will discuss the matter in monthly quality forum meeting.
6.9 If we change the part of machine / equipment or install a new one change control
document will be raised as described below:
6.10
Change
Spare parts and Components for plant and facilities fall into four categories
control
Prepared By: Checked By: Page 5 of 10
Date Date
CSH Pharmaceuticals (Pvt.) Ltd. Lahore
SOP NO. ENG/GEN-001/01
Identical Spare parts having the same specification, same manufacturer, and the
NA
same part number or manufacturers identification as the original
Equivalent Spare parts complying with the same specification and performing the
same function as the original but not necessarily from the same NA
manufacturer.
Replacemen Spare parts that have a different specification but perform the same
Required
t function as the original part.
Redesign Spare parts having a different specification and different functionality
Required
to the original
New If any new equipment installed / facilities change
Required
Equipment
7. VERSION HISTORY:
This SOP, Supersedes the SOP No. ENG-015/02 with following changes:
SOP allotted new Number and category, ENG/GEN-001/01
Change Control description is added in procedure.
Maintenance Schedule – Utility Equipments is added in procedure.
Changed Appendix No. of Job Description Card
Note is included in procedure.
Responsibility of Quality Assurance is defined in procedure .
8. REFERENCES
Guidance for the preparation of Standard Operating Procedures, U.S EPA Current
Version
9. LIST OF APPENDICES:
Appendix-1 Preventive Maintenance Schedule—Electrical
Appendix-2 Preventive Maintenance Schedule—Production Machines
Appendix-3 Preventive Maintenance Schedule—HVAC
Appendix-4 Preventive Maintenance Schedule—Utility Equipments
Appendix-5 Preventive Maintenance Schedule—Civil
MONTH / WEEK
SR AREA / OCT NOV DEC REMARK
JAN FEB MAR APR MAY JUN JULY AUG SEP
No EQUIPMENTS S
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
750KVA, power
Generator
150KVA, power
Generator
2 LT Panels
Portable
Equipments
3
Insect cutter
Air Curtain
Earth pit testing
Production
Machine
5 Utility Area
6 Technical Area
Equipments
Emergency
Lights
CSH Pharmaceuticals (Pvt.) Ltd. Lahore
SOP NO. ENG/GEN-001/01
Prepared By: __________________ Approved by Quality Assurance ____________________ Approved By Engineering Manger: ____________________
CC TV Cameras
2 Power supply
Backup (UPS)
Telephone
Exchange and
3 Extension Lines
Door inter
locking /Access
Card system
Security Lights
Prepared By: __________________ Approved by Quality Assurance ____________________ Approved By Engineering Manger: ____________________
Page 8 of 10
CSH Pharmaceuticals (Pvt.) Ltd. Lahore
SOP NO. ENG/GEN-001/01
20 Granulator Machine
Page 9 of 10
CSH Pharmaceuticals (Pvt.) Ltd. Lahore
SOP NO. ENG/GEN-001/01
SR JAN FEB MAR APR MAY JUN JULY AUG SEP OCT NOV DEC
AREA / EQUIPMENTS
No 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1 Production Area
2 Ware house
Administration Block
3 Utility Areas
5 Workshops
6 Outside Production
Area
Prepared By: __________________ Approved by Quality Assurance ____________________ Approved By Engineering Manger: ____________________
Page 10 of 10