Standard Calibration Procedure

Doc. No. Call/SCP/025 Rev. 00 May 01, 2015


Electric Oven / Furnace

STANDARD CALIBRATION PROCEDURE

ELECTRIC OVEN / FURNACE

Prepared by

Muhammad Ajlan Signature Date : 01.05.2015

Reviewed by

Muhammad Sarwar Signature Date : 01.05.2015

Approved by

Qaswar Mehmood Signature Date : 01.05.2015

Controlled Copy No. Uncontrolled Copy

Issued to :

Page 1 of 4
Standard Calibration Procedure
Doc. No. Call/SCP/025 Rev. 00 May 01, 2015
Electric Oven / Furnace

This document is the property of Qstar Engineering, and is issued only for persons or entity as
written on this document. It is not to be retransmitted, printed or copied without prior written
permission of company.

Table of Contents

Sr. No. Title Page No(s).


1.0 Scope 03
2.0 Standard Equipment 03
3.0 Preliminary Operations 03
4.0 Calibration Procedure 03
5.0 Related Documents 03

Page 2 of 4
Standard Calibration Procedure
Doc. No. Call/SCP/025 Rev. 00 May 01, 2015
Electric Oven / Furnace

1.0 Scope

This procedure provides guidelines for calibration of Electric Oven / Furnace.

2.0 Standard Equipment

2.1 Process Calibrator & Sensor with a valid certificate of calibration traceable to
international standard in accordance with an industrial code or a regulation shall be used
as a standard for calibration.
2.2 The reference standard shall be kept under controlled environmental conditions e.g. dust
free environment and Lab. temperature 22°C ± 3°C. Lab Humidity 60%RH ± 20%RH.

3.0 Preliminary Operations

3.1 The details of Electric Oven / Furnace received for calibration shall be entered in the
Calibration Job Form (Form: Call/001).
3.2 The Electric Oven / Furnace shall be inspected and marked () in relevant block of
equipment’s primary inspection section of Calibration Data Sheet (Form: Call/013).

4.0 Calibration Procedure

4.1 The Electric Oven / Furnace to be calibrated shall be maintained at same place of
standard (Process Calibrator) for 03 hours minimum.
4.2 Insert the Sensor of Process Calibrator into Electric Oven / Furnace and connect the
output of Sensor with Processor Calibrator.
4.3 Select the Electric Oven / Furnace under test for the desired range and give the sufficient
time for stable reading.
4.4 The Electric Oven / Furnace shall be checked at approximately 20%, 40%, 60% and
80% of full range.
4.5 The relevant section of Calibration Data Sheet (Form: Call/013) shall be marked.
4.6 The readings of Electric Oven / Furnace shall be recorded in measured value column
against the standard readings in set value column of Calibration Data Sheet (Form:
Call/013).

Page 3 of 4
Standard Calibration Procedure
Doc. No. Call/SCP/025 Rev. 00 May 01, 2015
Electric Oven / Furnace

4.7 After completion of calibration the Electric Oven / Furnace and the equipment should be
secured.
4.8 Calibration Certificate (Form: Call/002) shall be issued for calibrated Electric Oven /
Furnace as per Calibration Data Sheet Record (Form: Call/013).
4.9 A Calibration Sticker (Form: Call/003) containing following information shall be affixed
on the calibrated Thermocouple.
a) Item code
b) Calibrated on
c) Next calibration date

5.0 Related Documents

All the latest formats are documented in Master List of Document / Record and placed in CQF
file for reference.
All the latest Standard Calibration Procedures (SCP) are controlled and issued to concerned
Calibration Engineers.