Standard Calibration Procedure

Doc. No. Call/SCP/014 Rev. 00 May 01, 2015


Pressure Gauge

STANDARD CALIBRATION PROCEDURE

PRESSURE GAUGE

Prepared by

Muhammad Ajlan Signature Date : 01.05.2015

Reviewed by

Muhammad Sarwar Signature Date : 01.05.2015

Approved by

Qaswar Mahmood Signature Date : 01.05.2015

Controlled Copy No. Uncontrolled Copy

Issued to :

Page 1 of 4
Standard Calibration Procedure
Doc. No. Call/SCP/014 Rev. 00 May 01, 2015
Pressure Gauge

This document is the property of Qstar Engineering, and is issued only for persons or entity as
written on this document. It is not to be retransmitted, printed or copied without prior written
permission of company.

Table of Contents

Sr. No. Title Page No(s).


1.0 Scope 03
2.0 Standard Equipment 03
3.0 Preliminary Operations 03
4.0 Calibration Procedure 03
5.0 Related Documents 03

Page 2 of 4
Standard Calibration Procedure
Doc. No. Call/SCP/014 Rev. 00 May 01, 2015
Pressure Gauge

1.0 Scope

This procedure provides guidelines for calibration of Pressure Gauge.

2.0 Standard Equipment

2.1 Dead Weight Tester with a valid certificate of calibration traceable to international
standard in accordance with an industrial code or a regulation shall be used as a
standard for calibration.
2.2 The reference standard shall be kept under controlled environmental conditions e.g. dust
free environment and Lab. temperature 22°C ± 3°C. Lab Humidity 60%RH ± 20%RH.

3.0 Preliminary Operations

3.1 The details of Pressure Gauge received for calibration shall be entered in the Calibration
Job Form (Form: Call/001).
3.2 It Shall shell be ensured that the Pressure Port of Pressure Gauge is not blocked.
3.3 The Pressure Gauge shall be inspected and marked () in relevant block of equipment's
primary inspection section of Calibration Data Sheet (Form: Call/013).

4.0 Calibration Procedure

4.1 The Pressure Gauge to be calibrated shall be maintained at same place of standard
(Dead Weight Tester) for 06 hours minimum.
4.2 Pressure Gauge shall be exercised 2 to 3 times to full range.
4.3 Pressure Gauge shall be taped lightly while recording the readings to minimize friction
error.
4.4 The Pressure Gauge shall be checked at approximately 20%, 40%, 60% and 80% of full
range.
4.5 The relevant section of Calibration Data Sheet (Form: Call/013) shall be marked.
4.6 The readings of Pressure Gauge shall be recorded in measured value column against
the standard readings in set value column of Calibration Data Sheet (Form: Call/013).
4.7 The Pressure Gauge shall be cleaned and lubricated if required.
4.8 Calibration Certificate (Form: Call/002) shall be issued for calibrated Pressure Gauge as
per Calibration Data Sheet Record (Form: Call/013).
Page 3 of 4
Standard Calibration Procedure
Doc. No. Call/SCP/014 Rev. 00 May 01, 2015
Pressure Gauge

4.9 A Calibration Sticker (Form: Call/003) containing following information shall be affixed
on the calibrated Pressure Gauge.
a) Item code
b) Calibrated on
c) Next calibration date

5.0 Related Documents

All the latest formats are documented in Master List of Document / Record and placed in CQF
file for reference.
All the latest Standard Calibration Procedures (SCP) are controlled and issued to concerned
Calibration Engineers.