Professional Documents
Culture Documents
FOR
CONTROL VALVE
Prepared by
Reviewed by
Approved by
Issued to:
This document is the property of INAT and is issued only for persons or entity as written on this
manual. It is not to be retransmitted, printed or copied without prior written permission of company
Issue 01, OCT. 2014 Page 1 of 4
P.O. Box: 30060, Al-Khobar 31952, Tel: 00966 3 8933250, Fax: 00966 3 8643351,
Email: calibration@inatt.com, info@inatt.com, www.inatt.com
International Agent Group
Calibration, NDT, Trading, Inspection, Testing, QMS
Consultancy, IT Solutions and Contracting
Standard Calibration Procedure for Doc. No.:
Rev. 00 OCT. 2014
CONTROL VALVE INAT/MECH/LCP-009
Table of Contents
P.O. Box: 30060, Al-Khobar 31952, Tel: 00966 3 8933250, Fax: 00966 3 8643351,
Email: calibration@inatt.com, info@inatt.com, www.inatt.com
International Agent Group
Calibration, NDT, Trading, Inspection, Testing, QMS
Consultancy, IT Solutions and Contracting
Standard Calibration Procedure for Doc. No.:
Rev. 00 OCT. 2014
CONTROL VALVE INAT/MECH/LCP-009
1.0 Scope
2.1 Pneumatic calibrator and Process calibrator with a valid certificate of calibration
traceable to international standard in accordance with an industrial code or a regulation
shall be used as a standard for calibration.
2.2 The reference standard shall be used under ambient environmental conditions 22°C
±2°C and 60% ±20% RH.
3.1 The details of Control valve received for calibration shall be visually inspected for any
damage and entered in the Calibration Job Form (. (Applicable in Calibration Laboratory)
3.2 It shall be ensured that the Pressure supply of 20 PSI is applied to the positioner of the
Control valve and direction of operation of the positioner must be checked.
3.3 Standard Pneumatic signal of 3 to 15 PSI must be applied to the positioner of the Control
valve and scale must be noted for corresponding linear displacement values.
3.4 The control valve bench setting must be adjusted as per Name Plate marking.
3.5 The Control valve shall be inspected and marked () in relevant block of equipment's
primary inspection section of Calibration Data Sheet .
4.1 The Pneumatic calibrator and Process calibrator shall be maintained at same place of
Control valve to be calibrated to stabilize the temperature.
4.3 Control valve shall be taped lightly while recording the readings to minimize friction error.
4.4 The Control valve shall be checked at approximately 0%, 250%, 50%, 75% & 100% of
full range.
4.6 The readings of Control valve shall be recorded in observed value column against the
standard readings in set value column of Calibration Data Sheet.
P.O. Box: 30060, Al-Khobar 31952, Tel: 00966 3 8933250, Fax: 00966 3 8643351,
Email: calibration@inatt.com, info@inatt.com, www.inatt.com
International Agent Group
Calibration, NDT, Trading, Inspection, Testing, QMS
Consultancy, IT Solutions and Contracting
Standard Calibration Procedure for Doc. No.:
Rev. 00 OCT. 2014
CONTROL VALVE INAT/MECH/LCP-009
4.8 Calibration Certificate shall be issued for calibrated Control valve as per Calibration
Data Sheet Record.
4.9 A Calibration Sticker containing following information shall be affixed on the calibrated
Control valve.
a) Item code
b) Calibrated on
c) Next calibration date
All the latest formats are documented in Master List of Document / Record and placed in CQF
file for reference.
All the latest Standard Calibration Procedures (SCP) are controlled and issued to concerned
Calibration Engineers.
P.O. Box: 30060, Al-Khobar 31952, Tel: 00966 3 8933250, Fax: 00966 3 8643351,
Email: calibration@inatt.com, info@inatt.com, www.inatt.com