SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008) Rev 3 30-Jun-08

SAIC NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO INSPECTION CHECKLIST
Exhaust Fan Installation Inspection SAIC-K-4002 15-Dec-09 HVAC
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Fans shall be air-foiled, backward-inclined, backward curved, or forward- SAES-K-001


A1
curved. Para 4.8.9.1
SAES-K-001
A2 Variable speed fan shall be provided in variable air volume systems
Para 4.8.9.1

All exhaust fans shall have back draft dampers which shall close when SAES-K-001
A3
fan is off. Para 4.8.9.2

SAES-K-001
A4 All fans shall be isolated from their ducts by flexible connections.
Para 4.8.14.3

Equipment (fan assembly) clearance shall be provided with a minimum


SAES-K-001
A5 of 1 m clearance on each side of equipment with openable panel or
Para 5.1.4
controls, unless equipment manufacturer requires greater clearances.

Exhaust shall be directly to the outside with a point of discharge of at


SAES-K-001
A6 least 1.5 m away from any openable window or door, and a minimum of
Para 4.4.10.3
1m above and 3 m away from any air intake.

Exhaust fan used for ventilating the Battery Room shall have their
SAES-K-002
A7 exhaust point (air outlet) located in the ceiling or its upper edge flush with
Para 6.4
ceiling if it is located in a wall.

Fans and their Motors shall be accessible for servicing and maintenance SAES-K-100
A8
(UMC Para 503.1) Section 1

REMARKS:

REFERENCE DOCUMENTS:
1-SAES-K-001 -- Heating, Ventilating and Air Conditioning (HVAC), 25 November, 2006
2-SAES-K-002 -- Air Conditioning System for Essential Operating Facilities 31 May , 2004
3- Uniform Mechanical Code (UMC), 1997

4-SAES-K-100 -- Saudi Aramco Mechanical (HVAC) Code, 31 May , 2004

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

Page 1 of 2
*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Page 2 of 2