Professional Documents
Culture Documents
275
S.NO/
BOQ NO DESCRIPTION NO.S L B D QTY
Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of
21 sides and bottom and backfilling with approved material as per approved drawing or as directed by the Engineer-in-
Charge.
7 Aks Volume D/S L/S Wing & Return Wall Of Cr 1 149.35+131.5/2 3.60 505.53
8 Tail channel Qty 200.00 (44.7+35.7)/2 3.00 24120.00
TOTAL 32118.83
Excavation in ordinary rock without blasting for foundations of canal cross drainage and other
22 appurtenant structures and placing the excavated stuff neatly in specified dump area or disposing off
the same as directed, as per approved drawing or as directed by the Engineer-in-Charge.
3 Hdr Volume Of D/S Wing & Return Wall Escape 2 476.19+142.19/2 7.00 4328.66
Hdr Volume Of U/S Wing & Return Wall
4 Escape 2 75.19+120.8/2 7.10 1391.53
1 Hdr Volume For Cr Abutment Hoist 2 24.5+32.06/2 4.32 244.34
2 Hdr Volume For Cr Road Bridge Above (Cbl) 2 52.5+63.84/2 4.32 502.59
3 Hdr Volume For Cr Below Cbl Hoist 2 3.50 10.20 4.18 298.45
Hdr Volume Cr Abutnent Below Cbl Road
4 Bridge 2 5.25 12.70 4.18 557.40
6 Middle Pier 2Nd &3Rd 2 12.25 4.90 3.44 412.97
7 End Piers 1St & 4Th Road Bridge 2 7.00 4.60 3.44 221.54
8 End Piers 1St &4Th Hoist Platform 2 3.50 4.20 3.44 101.14
9 End Piers 1St &4Th Cut Water Portion 2 1.85 4.90 3.44 62.37
Cr Hdr Volume Of U/S R/S Wing Wall Below
10 Cbl & Return 1 31.83+15.26/2 7.90 1.50 279.01
Hdr Volume Of U/S R/S Wing Wall Above Cbl &
11 Return 1 186.00+144.44/2 7.90 4.32 713.75
Hdr Volume Of D/S R/S Wing Wall & Return
12 Below Cbl 1 14.98+32.91/2 8.60 2.38 490.10
Hdr Volume Of D/S R/S Wing Wall & Return
13 Above Cbl 1 205.93+449.35/2 8.60 4.32 767.40
Hdr Volume D/S L/S Wing & Return Wall Of Cr
14 Above Cbl 1 205.93+149.35/2 4.32 767.40
Hdr Volume Of D/S L/S Wing & Return Of Cr
15 Below Cbl 1 14.98+32.91/2 8.60 2.38 491.03
Tail channel Qty 200.00 (20.7+35.7)/2 5.00 28200.00
TOTAL 42333.95
1/14
S.NO/
BOQ NO DESCRIPTION NO.S L B D QTY
Providing & constructing Sand filling below foundations including cost of materials, machinery, labour,
S3 - 13 watering, ramming etc., complete with initial lead upto 50m and all lifts as per specifications and
approved drawing or as directed by the Engineer-in -charge.
18 Sand filling for u/s r/s wing wall & return of CR 1 29.91+16.13/2 6.90 0.30 47.65
TOTAL 516.79
Providing and laying insitu vibrated M-15 (28 days cube compressive strength not less than 15 n/sq mm)
grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for sub
23 structure/ super structure works including cost of all materials cost of all materials, machinery, labour,
formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete for plain concrete works as per approved drawing or as directed by the Engineer-
in-Charge.
1 Slrb Abutment pcc 1x2 13.00 5.40 0.15 21.06
2 Hoist abutment pcc 1x2 10.50 3.65 0.15 11.50
3 Escape pier hoist platform portion 1 3.50 3.80 0.15 1.99
4 Road bridge portion 1 5.25 4.60 0.15 3.62
5 Cut water portion 2 1.75 4.90 0.15 2.57
((15.58+16.64)+
6 For d/s r/s wing wall 1 (7.35+11.48))/2 7.60 0.15 29.09
((15.58+16.64)+
7 For d/s l/s wing wall 1 (7.35+11.48))/2 7.60 0.15 29.09
8 U/S wings& returns rhs pcc 1x1 31.15+19.4/2 6.90 0.15 26.16
9 U/S wings lhs pcc 1x1 17.60 6.75 0.15 17.82
10 Escape u/s apron 1 14.50 (24.13+6.69)/2 0.60 134.06
11 Escape u/s apron in 0.3 meter portion 1 0.30 (6.69+6.33)/2 (.6+.75)/2 1.32
12 U/s cut off wall 1 0.60 (23.4+24.13)/2 1.06 15.11
13 U/s cut water portion in vents 2 1.00 4.50 1.59 14.28
14 Apron at hoist 2 3.50 4.50 2.33 73.39
15 Apron at slrb in 2.07m portion 2 2.07 4.50 (2.33+1.3)/2 33.81
16 Apron at slrb in 3.18m portion 2 3.18 4.50 1.30 37.21
17 D/s cut water prtion in vents 2 1.00 4.50 1.30 11.70
18 D/s apron beside cut water portion 1 1.32 (8.07+8.53)/2 1.30 14.24
19 D/s apron in middle 5m portion 1 5.00 (8.53+12.46)/2 1.05 55.10
20 D/s apron in last 5m portion 1 5.00 (12.46+16.4)/2 0.95 68.54
21 D/s cut off wall 1 0.60 20.70 2.43 30.18
22 D/s drop wall 1 4.43 (20.7+12.9)/2 0.44 32.75
23 Apron in groves portion 4 1.00 0.50 2.33 4.66
24 Slrb abutment pcc 1x2 13.00 5.40 0.15 21.06
25 Hoist abutment pcc 1x2 10.50 3.65 0.15 11.50
26 End pier 1st &4th road bridge 2 5.25 4.60 0.15 7.25
27 End piers 1st & 4th hoist platform 2 3.50 4.20 0.15 4.41
28 End piers 1st & 4th cut water portion 4 1.75 4.90 0.15 5.14
2/14
S.NO/
BOQ NO DESCRIPTION NO.S L B D QTY
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement
concrete using 20 mm down size approved, clean, hard, graded aggregates for Piers & Pier Foundations including cost of all
S3-9 materials, labour, machinery, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts as per approved drawings or as directed by the Engineer-
in -charge.
3/14
S.NO/
BOQ NO DESCRIPTION NO.S L B D QTY
Providing and laying insitu vibrated M-25 (28 days cube compressive strength not less than 25 N / sq mm)
grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for
25 columns and beams including cost of all materials, machinery, labour, formwork, centering,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.
complete for as per approved drawing or as directed by the Engineer-in-Charge.
Providing and laying insitu vibrated M-25 ( 28 days cube compressive strength not less than 25 N / sq mm ) grade
cement concrete using 20 mm down size approved, clean, hard, graded aggregates for deck slab & kerb including cost of
all materials,machinery, labour, formwork, scaffolding,leaning, batching,mixing, placing in position, levelling, vibrating,
S6-2
finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 380 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--65:35, FA : 0.46 cum) If water is to be brought
from other place add only lead charges @ 500 ltr /cum.
4/14
S.NO/
BOQ NO DESCRIPTION NO.S L B D QTY
Providing and laying insitu vibrated M-30 ( 28 days cube compressive strength not less than 30 N / sq mm )
grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for
S3-12 Wearing Coat including cost of all materials, machinery, labour, formwork, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts as per specifications and approved drawing or as directed by the Engineer-in
-charge.
1 slrb slab wearing coat 1x2 4.25 6.50 0.08 4.14
2 Slrb slab wearing coat 1x5 4.25 6.50 0.08 10.36
TOTAL 14.50
Providing and laying insitu vibrated M-30 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade
cement concrete using 20 mm down size approved, clean, hard, graded aggregates for Piers & Pier Foundations including
S6-1
cost of all materials, labour, machinery, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling,
vibrating, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
Providing and laying insitu M-35 (28 days cube compressive strength not less than 30 N / sqmm) grade
cement concrete using 20 mm down size approved, clean, hard, graded aggregates for wearing coat
27 including cost of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in
position in alternate panels, levelling, compacting, finishing, curing, packing joints with asphalt mortar
etc., complete as per approved drawing or as directed by the Engineer-in-Charge
28 Supply of expansion joint filler board conforming to IS: 1838 for buildings, columns, beams and slabs
20 mm Thick as per approved drawing or as directed by the Engineer-in-Charge.
5/14
S.NO/
BOQ NO DESCRIPTION NO.S L B D QTY
35 Supply and providing of 310 mm wide PVC water stopper including cost of all materials and labour
charges etc complete as per approved drawing or as directed by the Engineer-in-Charge.
1 slrb abutment & hoist abutment 1x2 6.55 13.10
2 Slrb abutment & hoist abutment 1x2 6.55 13.10
TOTAL 26.20
Providing Semi- pervious/ pervious casing hearting embankment using soil collected from heaps in
embankment area as a part of disposal of excavated soil from canal including cost of all materials,
7 machinery labour, all operations such as excavation, sorting out, transportation, spreading in layers of
25 cm before compaction , breaking clods, sectioning, watering and compacting each layer to density
control of not less than 98 percent or stipulated by the sheep foot roller/ Vibratory roller 8 to 10 tone
power roller etc. complete as per approved drawing or as directed by the Engineer-in-Charge.
1 Under aproach slab gravel filling 1x2 3.50 5.25 0.23 8.27
2 Under aproach slab gravel filling 1x2 3.50 5.25 0.23 8.27
3 Road bridge aproaches of c.r 1x2 5.25 19+8.5/2 9.22 1331.14
4 Road bridge aproaches of c.r 1X2 5.25 2+0.5/2 1.00 13.13
5 Road bridge aproaches of escape 2 5.25 19+8.5/2 9.22 1331.14
6 Road bridge aproaches of escape 2 5.25 2+0.5/2 1.50 19.69
s TOTAL 2711.63
Supply and providing of Drainage spouts including cost of all materials and labour charges etc complete
30 as per approved drawing or as directed by the Engineer-in-Charge.
6/14
DETAILED MEASUREMENT
BOQ Providing, fabricating and placing in position reinforcement steel bars for RCC works including cleaning, straightening, cutting,
No.29 bending, hooking, lapping, welding wherever required, tying with 1.25 mm dia soft annealed steel wire, including cost of all
materials, machinery, labour etc., complete with initial lead upto 50 and all lifts as per approved drawing or as directed by the
Engineer-in-Charge.
UNIT TOTAL
S.NO DESCRIPTION DIA SPACING NO.S LENGTH
WEIGTH WEIGTH
54.275@ ESCAPE CUM CR
Escape Abutment hoist steel
1 Abutment hoist raft bottum main bars lhs 25mm 135mm 1x2x27 6.85 3.85 1424.12
2 Raft bottum mate main bars rhs 16mm 125mm 1x2x29 6.85 1.58 627.73
3 Raft bottum mat distributers 16mm 125mm 1x2x83 5.20 1.58 1311.40
4 Raft top mat distributers 16mm 125mm 1x2x83 5.20 1.58 1311.40
5 Raft top mate main bars 16mm 110mm 1x2x33 11.70 1.58 1220.08
9 Abutment hoist inner side verticle main bars 16mm 100mm 1x2x36 12.85 1.58 1461.82
10 Hoist inner side verticle disributors 16mm 100mm 1x2x110 4.45 1.58 1546.82
11 Hoist outer side varticle main bars up to 110.350 25mm 125mm 1x2x29 8.00 3.85 1786.40
12 Hoist outer side varticle main bars 110.350 to 115.354 25mm 250mm 1x2x15 5.20 3.85 600.60
13 Hoist outer side verticle disributors 16mm 100mm 1x2x116 4.40 1.58 1612.86
14 Hoist side verticle bars 16mm 100mm 1x2x31x2 11.90 1.58 2331.45
15 Hoist side disributors 16mm 100mm 1x110x2x2 2.15 1.58 1494.68
16 Abutment hiost plate form outer verticle main bars 16mm 150mm 1x25x2 9.00 1.58 711.00
17 Abutment hiost plate form inner verticle main bars 16mm 150mm 1x25x2 8.80 1.58 695.20
18 Abutment hoist plate form inner side distributors 16mm 150mm 1x47x2 9.74 1.58 1446.58
19 Abutment hoist plate form outer side distributors 16mm 150mm 1x42x2 7.10 1.58 942.31
20 Abutment hoist sides verticle bars 16mm 150mm 1x7x2x2 7.10 1.58 314.10
21 Abutment hoist sides verticle distributors 16mm 150mm 1x45x2x2 0.92 1.58 261.65
Escape Abutment slrb bridge steel
1 Abutment slrb raft bottum main bars lhs 25mm 125mm 1x2x43 6.45 3.85 2135.60
2 Abutment slrb raft bottum main bars rhs 16mm 125mm 1x43x2 9.75 1.58 1324.83
3 Slrb raft bottum mat distributors 16mm 125mm 1x103x2 6.75 1.58 2196.99
4 Slrb raft top mat main bars 16mm 110mm 1x49x2 15.00 1.58 426.60
5 Slrb raft top mat distributors 16mm 125mm 1x103x2 6.75 1.58 2196.99
6 Slrb inner side verticle main bars 20mm 200mm 1x2x28 12.73 2.47 1760.81
7 Slrb inner side verticle disributors 20mm 200mm 1x2x55 5.15 2.47 1399.26
8 Slrb outer side vertical main bars up to 110.350 25mm 125mm 1x2x43 8.00 3.85 2648.80
9 Slrb outer side varticle main bars 110.350 to 114.579 25mm 250mm 1x2x22 4.73 3.85 764.84
10 Slrb outer side verticle disributors 20mm 200mm 1x2x55 6.25 2.47 1698.13
11 Slrb side verticle main bars 20mm 200mm 1x15x2 12.73 2.47 943.29
12 Slrb side distributors 20mm 200mm 1x55x2 2.15 2.47 584.16
Escape Pier steel
1 pier foundation raft bottum &top main bars 16mm 125mm 1x2x97 5.10 1.58 1563.25
2 pier raft top & bottum distributors 12mm 250mm 1x2x20 12.45 0.89 443.22
3 pier varticle main bars up to 114.700 25mm 150mm 1x131 11.80 3.85 5951.33
4 water cutter verticle bars up to fsl 25mm 150mm 1x38 8.80 3.85 1287.44
5 pier distributors up to fsl 10mm 300m 1x28 28.10 0.62 487.82
6 pier hoist & slrb side verticle main bars 25mm 150mm 1x2x14 3.50 3.85 377.30
7 pier hoist & slrb side verticle distributor bars 10mm 300mm 1x8 23.50 0.62 116.56
8 pier hoist plate form verticles bars 25mm 300m 1x42 8.80 3.85 1422.96
9 pier hoist plate form distributors 10mm 300mm 1x24 10.38 0.62 154.45
10 piers hoist plate form sides verticle main bars 25mm 300m 1x8x2 8.80 3.85 542.08
11 piers hoist plate form sides verticle distributor bars 10mm 300mm 1x24x2 0.92 0.62 27.38
Escape D/S wings & returns steel
7/14
UNIT TOTAL
S.NO DESCRIPTION DIA SPACING NO.S LENGTH
WEIGTH WEIGTH
1 D/s wings & returns raft bottum mat main bars lhs 20mm 150mm 1x217x2 4.20 2.47 4502.32
2 Raft bottum mat main bars rhs 12mm 125mm 1x159x2 5.63 0.89 1591.99
3 Raft bottum mat distributors 12mm 125mm 1x60x2 27.39 0.89 2876.50
4 Raft top mat main bars 20mm 120mm 1x243x2 8.20 2.47 9843.44
5 Raft top mat distributors 12mm 125mm 1x59x2 27.39 0.89 2876.50
6 Wings & returns inner side verticle main bars 12mm 125mm 1x232x2 11.10 0.89 4583.86
7 Wings & returns inner side verticle distributors 12mm 125mm 1x79x2 29.40 0.89 4134.23
8 Wings & returns outer side verticle main bars 25mm 125mm 1x215x2 11.50 3.85 19038.25
9 Wings & returns outer side verticle distributors 12mm 125mm 1x2x79 27.50 0.89 3867.05
10 Side verticle bars 12mm 125mm 1x12x2x2 11.10 0.89 474.19
11 Side distributors 12mm 125mm 1x79x2x2 0.80 0.89 224.99
Escape U/S R/S wings& returns steel
1 U/s r/s wings&returns raft bottam mat main bars lhs 20mm 150mm 1x208x1 4.30 2.47 2209.17
2 U/s r/s wings&returns raft bottam mat main bars rhs 12mm 125mm 1x1x154 5.00 0.89 685.30
3 U/s r/s wings&returns raft bottam distributors 12mm 125mm 1x54 26.10 0.89 1254.37
4 U/s r/s wings&returns raft top mat main bars 20mm 150mm 1x168 7.60 2.47 3153.70
5 U/s r/s wings&returns raft top mat distributors 12mm 125mm 1x54 26.10 0.89 1254.37
6 U/s r/s wings&returns inner side verticle main bars 12mm 125mm 1x221 10.30 0.89 2025.91
7 U/s r/s wings&returns inner side distributors 12mm 125mm 1x72 28.40 0.89 1819.87
8 U/s r/s wings&returns outer side verticle main bars 25mm 125mm 1x208x1 10.30 3.85 8089.62
9 U/s r/s wings&returns outer side distributors 12mm 125mm 1x74 26.70 0.89 1758.46
10 Side verticle bars 12mm 125mm 1x10x2 10.30 0.89 183.34
11 Side distributors 12mm 125mm 1x74x2 1.30 0.89 171.24
Escape U/S L/S wings& returns steel
1 U/s lhs wing wall raft bottam mat main bars lhs 20mm 150mm 1x117 4.30 2.47 1242.66
2 U/s lhs wing wall raft bottam mat main bars rhs 12mm 125mm 1x140 5.00 0.89 623.00
3 Raft bottum mat distributors 12mm 125mm 1x54 18.50 0.89 889.11
4 Raft top mat main bars 20mm 150mm 1x115 7.50 2.47 2130.38
5 Raft top mat distributors 12mm 125mm 1x54 18.50 0.89 889.11
6 Inner side verticle main bars sloped portion 12mm 125mm 1x84 4.80 0.89 358.85
7 Inner side verticle distributors sloped portion 12mm 125mm 1x72 5.25 0.89 336.42
8 Outer side varticle main bars bars sloped portion 25mm 125mm 1x84 4.80 3.85 1552.32
9 Outer side varticle destributors sloped portion 12mm 125mm 1x72 5.25 0.89 336.42
10 Inner side verticle main bars strighte portion 12mm 125mm 1x57 10.10 0.89 512.37
11 Inner side verticle distributors strighte portion 12mm 125mm 1x72 7.50 0.89 480.60
12 Outer side varticle main bars strighte portion 25mm 125mm 1x57 10.20 3.85 2238.39
13 Outer side varticle distributor strighte portion 12mm 125mm 1x72 7.50 0.89 480.60
14 Side verticle bars 12mm 125mm 1x8 10.10 0.89 71.91
15 Side distributors 12mm 125mm 1x72 0.65 0.89 41.65
16 D/s drope wall rings 12mm 200mm 1x105 3.40 0.89 317.73
17 D/s drope wall main bars 12mm 200mm 1x16 17.20 0.89 244.93
Escape SLRB bridge steel
1 Slrb abutment bed block 2 legged rings 12mm 150mm 1x35x2 3.80 0.89 236.74
2 Bed block main bars 16mm 1x10x2 5.15 1.58 162.74
3 Dirt wall 2legged rings 12mm 150mm 1x35x2 2.50 0.89 155.75
4 Dirt wall main bars 12mm 125mm 1x2x9 5.15 0.89 82.50
5 Pier bed block master ring 12mm 150mm 1x35 4.60 0.89 143.29
6 Pier bed block distributor ring 12mm 150mm 1x35 2.60 0.89 80.99
7 Pier bed block main bars 12mm 1x16 5.15 0.89 73.34
8 Aproch slab bottum & top main bars 12mm 150mm 1x35x2x2 3.40 0.89 423.64
9 Aproch slab top & bottum distributors 12mm 150mm 1x23x2x2 5.15 0.89 421.68
10 Slrb slab bottum main bars 20mm 200mm 1x28x2 6.80 2.47 940.58
11 Slrb slab bottum distributors 12mm 200mm 1x34x2 5.15 0.89 311.68
8/14
UNIT TOTAL
S.NO DESCRIPTION DIA SPACING NO.S LENGTH
WEIGTH WEIGTH
12 Slrb slab top main bars 12mm 300mm 1x19x2 6.80 0.89 229.98
13 Slrb slab top distributors 12mm 300mm 1x23x2 5.15 0.89 210.84
14 Crush barriar stirrups 10mm 200mm 1x66x2 2.10 0.62 171.86
15 Parepet walls stirrups 10mm 200mm 1x66x2 3.30 0.62 270.07
16 Cranck bars 10mm 200mm 1x66x2 1.30 0.62 106.39
17 Outer side distributors 10mm 200mm 1x7x2 13.00 0.62 112.84
18 Inner side distributors 10mm 200mm 1x8x2 13.00 0.62 64.48
CR Abutment hoist raft steel
1 Hoist raft bottum main bars lhs 25mm 135mm 1x27x2 6.85 3.85 1424.12
2 Bottum mat main bars rhs 16mm 125mm 1x29x2 5.00 1.58 458.20
3 Bottum mat Distributors 16mm 125mm 1x82x2 5.00 1.58 1295.60
4 Top mat distributors 16mm 125mm 1x82x2 5.00 1.58 1295.60
5 Top mat main bars 16mm 110mm 1x33x2 11.70 1.58 1220.08
6 Inner side verticle main bars 16mm 100mm 1x36x2 11.25 1.58 1279.80
7 Inner side Distributors 16mm 100mm 1x110x2 4.45 1.58 1546.82
8 Outer side verticle bars up to 110.350 25mm 125mm 1x29x2 8.50 3.85 1898.05
9 Outer side verticle bars up to 115.354 25mm 250mm 1x15x2 5.10 3.85 589.05
10 Outer side Distributors 16mm 100mm 1x117x2 4.50 1.58 1663.74
11 Side verticle bars 16mm 100mm 1x31x2x2 11.30 1.58 2213.90
12 Side distributors 16mm 100mm 1x110x2x2 3.00 1.58 2085.60
13 Abutment hoist verticle main bars 114 .700 to 121.500 16mm 150mm 1x61x2 8.80 1.58 1696.29
14 Abutment hoist distributor bars 114 .700 to 121.500 16mm 150mm 1x47x2 9.74 1.58 1446.58
15 Abutment hoist plate form side verticles 16mm 150mm 1x7x2x2 8.30 1.58 367.19
16 Abutment hoist plate form side destributors 16mm 150mm 1x46x2x2 1.70 1.58 494.22
CR Abutment road bridge raft steel
1 Slrb bridge abutment raft bottum main bars lhs 25mm 125mm 1x44x2 6.45 3.85 2185.26
2 Abtment raft bottum main bars rhs 16mm 125mm 1x44x2 9.75 1.58 1355.64
3 Bottum mat distributors 16mm 125mm 1x103x2 6.75 1.58 2196.99
4 Top mat main bars 16mm 110mm 1x49x2 15.00 1.58 2322.60
5 Top mat distributors 16mm 125mm 1x103x2 6.75 1.58 2196.99
6 Inner side verticle main bars 20mm 200mm 1x27x2 12.10 2.47 1613.90
7 Iinner side distributors 20mm 200mm 1x54x2 7.20 2.47 1920.67
8 Outer side verticlemain bars up to 110.35 25mm 125mm 1x43x2 6.20 3.85 2052.82
9 Outer side verticle main bars up to 114.549 25mm 250mm 1x22x2 4.93 3.85 797.18
10 Outer side distributors 20mm 200mm 1x55x2 7.20 2.47 2134.08
11 Side verticle main bars 20mm 200mm 1x16x2 12.10 2.47 956.38
12 Side distributors 20mm 200mm 1x55x2 3.00 2.47 815.10
CR Pier raft steel
1 Pier raft bottum & top main bars 16mm 125mm 1x96x2x4 5.12 1.58 6212.81
2 Pier raft bottum & top distibutors 16mm 250mm 1x19x2x4 12.45 1.58 2989.99
3 Pier varticle main bars up to FSL 25mm 150mm 1x131x4 10.80 3.85 21787.92
4 Pier water cutter varticle bars up to FSL 25mm 150mm 1x38x4 8.80 3.85 5149.76
5 Pier distributors up to FSL 10mm 300mm 1x27x4 25.56 0.62 1711.50
6 Pier verticle bars FSL TO 114.7 25mm 150mm 1x159x4 2.20 3.85 5386.92
7 Pier distributor bars FSL TO 114.7 10mm 300mm 1x9x4 22.30 0.62 497.74
8 Pier hoist verticle main bars 114 .7 to 121.5 25mm 300 mm 1x30x4 8.80 3.85 4065.60
9 Pier hoist distributor bars 114 .7 to 121.5 10mm 300mm 1x24x4 10.30 0.62 613.06
10 Pier verticle bars sides FSL TO 114.7 25mm 150mm 1x14x2x4 2.70 3.85 1164.24
11 Pier verticle distributor bars sides FSL TO 114.7 10mm 300mm 1x8x2x4 2.40 0.62 95.23
12 Pier hoist side verticles 25mm 300mm 1x4x2x4 8.30 3.85 1022.56
13 Pier hoist side distributors 10mm 300mm 1x24x4x2 1.40 0.62 166.66
CR Road bridge slab steel
9/14
UNIT TOTAL
S.NO DESCRIPTION DIA SPACING NO.S LENGTH
WEIGTH WEIGTH
1 SLRB bridge slab bottum main bars 20mm 200mm 1x27x5 6.80 2.47 2267.46
2 SLRB bridge slab bottum distributors bars 12mm 200mm 1x33x5 5.57 0.89 817.95
3 SLRB bridge slab top main bars 12mm 300mm 1x23x5 6.80 0.89 574.94
4 SLRB bridge slab top distributor bars 12mm 300mm 1x22x5 5.60 0.89 548.24
5 Crush barriors stirrups 10mm 200mm 1x165x2 2.10 0.62 169.26
6 Parapet walls rings 10mm 200mm 1x165x2 3.30 0.62 675.18
7 Parapet walls cranck bars 10mm 200mm 1x165x2 1.10 0.62 225.06
8 Crash barriors inner main bars 10mm 200mm 1x7x2x5 32.50 0.62 1410.50
9 Crush barriors outer main bars 10mm 200mm 1x7x2x5 32.50 0.62 1410.50
10 C.R abutment bed bolck 2- legged stirrups 12mm 150mm 1x35x2 3.70 0.89 230.51
11 C R abutment bed block main bars 16mm 1x10x2 5.15 1.58 162.74
12 C.R abutment dirt wall 2- legged stirrups 12mm 150mm 1x35x2 2.35 0.89 146.41
13 C R abutment dirt wall main bars 12mm 150mm 1x9x2 5.15 0.89 82.50
14 Pier bed block 4- legged 1st stirrups 12mm 150mm 1x35x4 4.84 0.89 603.06
15 Pier bed block 2nd stirrups 12mm 150mm 1x35x4 2.60 0.89 323.96
16 Pier bed block main bars 16mm 1x16x4 5.15 1.58 520.77
17 Aprouch slab bottum &top main bars 12mm 150mm 1x35x2x2 3.40 0.89 423.64
18 Aprouch slab top & bottum distributors 12mm 150mm 1x23x2x2 5.15 0.89 421.68
CR D/S wings & returns raft steel
1 D/s wings& returns raft bottum mat main bars lhs 20mm 150mm 1x206x2 4.60 2.47 4681.14
2 Raft bottum mat main bars rhs 12mm 125mm 1x137x2 5.63 0.89 1371.71
3 Wings & returns bottum mat distributors 12mm 125mm 1x60x2 27.20 0.89 2904.96
4 D/s wings& returns raft top mat main bars 20mm 125mm 1x192x2 8.20 2.47 7777.54
5 Raft top mat distributors 12mm 125mm 1x60x2 27.20 0.89 2904.96
6 D/S wings & returns inner side varticle bars 12mm 125mm 1x215x2 10.50 0.89 4018.35
7 D/S wings & returns inner side disributor bars 12mm 125mm 1x80x2 27.00 0.89 3844.80
8 D/S wings & returns outer side varticle bars 25mm 125mm 1x197x2 11.40 3.85 17292.66
9 D/S wings & returns outer side distributor bars 12mm 125mm 1x80x2 25.30 0.89 3602.72
10 Side verticle bars 12mm 125mm 1x8x2 10.50 0.89 149.52
11 Side distributors bars 12mm 125mm 1x80x2 0.80 0.89 113.92
CR U/S R/S wings & returns raft steel
1 U/s rhs wings & returns raft bottum main bars lhs 20mm 150mm 1x198 4.40 2.47 2151.86
2 U/s rhs wings & returns raft bottum main bars rhs 12mm 125mm 1x127 5.00 0.89 565.15
3 U/s rhs wings & returns raft bottum mat distributors 12mm 125mm 1x54 24.20 0.89 1163.05
4 Raft top mat main bars 20mm 150mm 1x154 7.50 2.47 2852.85
5 Raft top mat distributors 12mm 125mm 1x54 24.20 0.89 1163.05
6 Inner side verticle main bars 12mm 125mm 1x206 10.50 0.89 1925.07
7 Inner side distributor bars 12mm 125mm 1x72 26.75 0.89 1714.14
8 Outer side varticle main bars 25mm 125mm 1x188 10.50 3.85 7599.90
9 Outer side distributors bars 12mm 125mm 1x72 25.75 0.89 1627.14
10 Side verticle bars 12mm 125mm 1x8x2 10.50 0.89 149.52
11 Side distributor bars 12mm 125mm 1x72x2 0.75 0.89 96.12
12 D/s drope wall stirrups 12mm 150mm 1x205 3.60 0.89 656.82
13 D/s drope wall distributors 12mm 150mm 1x26 29.50 0.89 682.63
Total (Kg) 319529.00
10/14
ESCAPE KM 54.275 ABSTRUCT
S.NO/ BOQ. NO DESCRIPTION OF ITEM UNIT QUANTITY
21 AKS CUM 5755.08
22 HDR CUM 8224.46
S3-13 SAND FILLING CUM 227.67
23 CC M15 40 MSA CUM 669.25
S3-9 M20 20 MSA CUM 2271.66
S6-2 M25 20 MSA CUM 43.03
25 M25 20 MSA CUM 27.3
26 M30 20 MSA CUM 5.51
S3-12 M30 20 MSA WEARING COAT CUM 4.14
S3-10 M20 20 MSA WEARING COAT CUM 85.31
27 M35 20 MSA WEARING COAT CUM 3.15
28 MASTIC PADS SQM 7.48
33 WEEP HOLES NO.S 126
35 WATER STOPER RMT 13.1
30 DRAINAGE SPOTS NO.S 8
KRAFT PAPER SQM 21
7 BACK FILLING CUM 8634.77
32 APROACH SLABS UNDER GRAVEL FILLING CUM 8.27
29 STEEL KGS 145116.94