Techno-Commercial Proposal for

15 KLD Sewage Treatment Plant


S Y Malvankar Resorts Pvt Ltd

D BHARATSHAKTI INFRA
“Durvankur” , Trishul Society, Saswad . Tahsil Purandar. Pune 412301
Contact no. 7218736939 / 7588580494 /9921790515 dbharatshakti@gmail.com

Revision Date Comment Prepared Checked Approved


R0 26.01.2019 Based upon discussion DP PK DBSI
SYMRPL
SYMRPL/DBI/20190126/008/R0 26th January 2019

To
S Y Malvankar Resorts Pvt Ltd
Devbag, Tahsil Malvan
District Sindhudurg

Kind Attn : Mr. Rajeev Damari

Dear Sir,

Subject : Techno-Commercial Offer for 15 KLD STP

Greetings!

We thank you for giving us an opportunity to submit the proposal for reuse of wastewater
Comprising of MBBR based sewage treatment plant.

We hope our offer is in detail & meet’s your expectation and look forward to your guidance
in moving forward to mutually work in this project. Should you require any further details,
please feel free to contact us. Thanking you and assuring you of our best services always,
we remain.

However if you require any clarification/confirmation in respect to our offer please feel free
to contact us.

Thanking you and assuring you best of our services at all times.

Yours faithfully,

For D BHARATSHAKTI INFRA


Pallavi D Phadatare

Page 2
SYMRPL

Table of Contents

1 DESIGN CONSIDERATION .......................................................................................................... 4


1.1 Design Capacity ...................................................................................................................... 4
1.2 Sewage Quality ....................................................................................................................... 4
1.2.1 Treatment Design Selection ............................................................................................... 4
1.2.2 Treated sewage parameters at STP outlet: ................................................................. 4
2 PROCESS DESCRIPTION .............................................................................................................. 5
3 PROCESS FLOW DIAGRAM & WATER BALANCE (TENTATIVE) ...................................... 7
4 TECHNICAL SPECIFICATION ...................................................................................................... 8
4.1 Mechanical Specifications .................................................................................................... 8
4.2 INSTRUMENTATION SCHEDULE ..................................................................................... 11
4.3 Battery Limits ........................................................................................................................ 12
4.4 Client Obligations ................................................................................................................. 12
5 POWER & CHEMICAL SCHEDULE ............................................................................................ 13
5.1 Power Schedule ..................................................................................................................... 13
5.2 Chemical Schedule ............................................................................................................... 13
6 LIST OF CIVIL WORKS (Customer Scope).......................................................................... 14
7 PRICE, COMMERCIAL TERMS & CONDITIONS ................................................................... 15

Page 3
SYMRPL

1 DESIGN CONSIDERATION

1.1Design Capacity

 Feed for STP –15 m3/day


 Working period - 24 Hours
 Peak Factor 2.5
 Operation : Manual

1.2 Sewage Quality

1.2.1 Treatment Design Selection

Parameter Value Units


Flow 50 m3/day
Chemical Oxygen Demand (COD) 350 mg/lit
Biological Oxygen Demand (BOD) 300 mg/lit
Total suspended solids 250 mg/lit
Oil & Grease 20-30 mg/lit
pH 7-8 -

1 Any adverse variation in the feed sewage quality will affect the plant performance in
terms of quality and quantity of treated water.
2 We have considered the temperature of the sewage as 25°C for Plant design.

1.2.2 Treated sewage parameters at STP outlet:

Parameter Value Units


Chemical Oxygen Demand (COD) <100 mg/lit
Biological Oxygen Demand (BOD) <30 mg/lit
Total suspended solids <10 mg/lit
Oil & Grease <5 mg/lit

Page 4
SYMRPL

2 PROCESS DESCRIPTION

 Bar Screen
 Oil & grease Trap
 Sewage Collection tank cum Equalization tank
 MBBR System
 Tube Settler
 Hypo Dosing System
 Chlorine contact tank
 PSF/ ACF

Process Details:

A) Screening

Bar screen will remove foreign materials, such as plastic, rag, napkin and any other
solid/floating matter along with the incoming sewage.

B) Oil & Grease Trap

In this tank, Oil & Grease Trap will separate the free floating oil & grease from the
Sewage.

C) Equalization Tank/Collection sump

The sewage is collected in the Equalization tank by Gravity. From this tank the
sewage will be pumped to the Aeration Tank. The air blowers will be provided for
mixing & homogenization of the Sewage in the tank.

D) Aeration Tank

The equalized sewage will be transferred to the Aeration


Tank (MBBR). In MBBR (Moving Bed Bio-reactor) the
Sewage Water flows down keeping in contact with media
which is PP, designed for high Surface loading rate and
BOD removal for sewage plants. The air in form of fine
bubbles coming from the bottom of tank comes in contact
with Water & MBBR media. The tank is provided with fine
bubble diffusers for the biological oxidation of sewage.
Here, recirculation of
Sludge is done only in
the start-up phase to
bring the process under steady state. As soon as
steady state reaches no need for recirculation as

Page 5
SYMRPL
the layers of inactive sludge (which comes off naturally due to moving nature of
media) itself provide the desired MLSS to be maintained.

E) Tube Settler

The sewage comprising of the biological floc from MBBR will pass through a Tube
Settler where the solid mass will settle down at the bottom. The Tube Settler media
will facilitate the settling of suspended
particles. The clarified supernatant will be
collected in the filter feed tank by gravity
means. A part of underflow sludge will be
recycled back with the Sludge Recirculation
Pump to the MBBR to maintain the population of micro-organisms, required during
plant startup. The excess amount of Underflow sludge will be transferred to the
sludge drying beds.

F) Chlorine Contact Tank

Clear water from the Clarifier will be dosed with Sodium Hypo for disinfection &
stored in the Chlorine Contact Tank for tertiary treatment. Clear water from this
compartment is passed through a pressure sand filter and stored in final treated
water tank

G) Filters (PSF & ACF)

Pressure Sand Filter (PSF) consists essentially of a


pressure vessel. It is externally fitted with necessary
pipe work, valves, and pressure gauges. The bed
consists of sand, pebble gravel etc. Waste water
flows downwards
through the filter bed
and the suspended
solids are retained on
the media. It is required to
remove suspended
solids and turbidity from
clarified water.
Activated Carbon Filter (ACF) is used to knock off VOC
(Volatile Organic Compounds) normally associated in
almost all sewage treatment plant. ACF also helps in giving
polished look to treated water.
The filters will be backwashed after every 22 hours of
service or when the pressure drop across the filter exceeds 0.8 Kgs /cm2.
Waste Water generated from Filter backwash shall be recycled back to Equalization tank.

Page 6
3 PROCESS FLOW DIAGRAM & WATER BALANCE (TENTATIVE)

Water Balance for 15 KLD STP


Filtration Biological Treatment Chlorination PSF ACF
Feed Flow 15 m3/day Feed Flow 16 m3/day Feed Flow 15.0 m3/day Feed Flow 15.1 m3/day Feed Flow 14.6 m3/day
Feed Flow 1.0 m3/hr Feed Flow 1.08 m3/hr Feed Flow 1.0 m3/hr Feed Flow 1.01 m3/hr Feed Flow 0.97 m3/hr
Operational 15 hrs Operational 15 hrs Operational 15 hrs Operational 15 hrs Operational 15 hrs
Filter B/W 1.10 m3/day Sludge 1.1 m3/day Chemical 0.1 m3/day B/W 0.55 m3/day B/W 0.55 m3/day
Sludge Filtrate 1.1 m3/day Treated waste 14.0 m3/day

Screen, O&G, Collection


DMF DMFMBBR + Tube Settler RO Treated Water Tank
Chlorination Tank PSF ACF
tank

Waste Sludge B/W waste B/W waste


1.0 m3/day 1.1 m3/day 0.6 m3/day 0.6 m3/day
0.07 m3/hr 0.08 m3/hr 0.04 m3/hr 0.04 m3/hr
To Sludge Drying Bed and EQT To EQT To EQT
SYMRPL

4 TECHNICAL SPECIFICATION

4.1 Mechanical Specifications

Sr. EQUIPMENT PECIFICATIONS 15 KLD


No
1. Bar Screen
Quantity 1 No
Material of construction SS304
Operation Manual
Opening Space 8 mm
Make DBI

2. Raw Sewage Transfer Pumps


Quantity 2 Nos.(1W+1S)
Capacity 1 m3/h
Head 10-12 mwc
Material of construction SS316
Type Horizontal, Self-Priming
Make Kirloskar/ Equiv.

3. Air Blower for EQT, AT


Quantity 2 Nos.(1W+1S)
Type Twin Lobe
Capacity 140.00 m3/h
Head 4.00 mwc
Material of construction CI
Make Kay / Everest / Equi.

4. Air Diffusers
For Aeration Tank
Type Fine bubble diffusers
Material of Construction EPDM
Quantity 1 Lot
Make Southern Cogen/Equiv.

5. MBBR Bio-media
Surface area 400 m2/m3

Page 8
SYMRPL
Material of Construction Polypropylene
Quantity (m3) 1 Lot
MOC PP UV Stabilized

6. Tube Settler
Quantity in. 1 No
Hydraulic Loading Rate in m3/m2/hr 2.5

Tube Media PVC


1 Lot
Tube Settler MOC RCC, Media Support in MSEP
Media Make Cooldeck/MMAqua/Equiv.

7. Filter Feed Pump


Quantity in 2 Nos.(1W+1S)
Capacity 1-2 m3/h
Head 25-30 mwc
Material of construction CI
Type Horizontal Centrifugal
Make Kirloskar / Equiv.

8. Sludge Trabsfer Pumps


Quantity 2 Nos.(1W+1S)
Capacity 1 m3/h
Head 10 mwc
Material of construction CI
Type Self-Priming / Non clog
Make Kirloskar / Equiv.

9. Pressure Sand Filter


Quantity in 1 No
Design Flow 1-2 m3/h
Working Pressure 25-30 mwc
Design Pressure 5.5 Bar
Type Vertical Down flow
Size 450mm Dia x 1500 mm Ht
Accessories Collection and distribution system,
Multiport valve with sand, pebbles
and gravels

Page 9
SYMRPL
Make Aventura/Pentair/WaveCyber / Eqvt.

10. Activated Carbon Filter


Quantity in 1 No
Design Flow 1-2 m3/h
Working Pressure 25 mwc
Working Pressure 25-30 mwc
Design Pressure 5.5 Bar
Size 450mm Dia x 1500 mm Ht
Accessories Collection and distribution system,
Multiport valve with Carbon, pebbles
and gravels
Make Aventura/Pentair/WaveCyber / Eqvt.

11. Chlorine Dosing System


Dosing Pump
Quantity 2 Nos.(1W+1S)
Capacity 0-6 lph
Head 30 mwc
Material of construction PP
Type Metering
Make Prominent/Asia LMI/e-dose Equi.
Dosing Tank
Quantity 1 No
Capacity 100 Liters
Material of construction HDPE/LDPE

12. Piping & Valves


Valves (Manual) 1 Lot
Material of construction uPVC/PP
Make Astral/Prince/Pune Polymer Equi.
PIPING 1 Lot
Note: Piping/cable tray common or separate support will be at approx. 4 m
C/c distance

13. Electrical
MCC cum control panel 1 No
Type Non-Compartmental –SFU Feeder

Page 10
SYMRPL
type
Make of Switch Gears & Internals Siemens/ L&T/ GE/Equivalent
Cable 1 Lot
Make DBI

4.2 INSTRUMENTATION SCHEDULE

SL. LOCATION QTY. PROCESS TYPE OF MAKE


No. MEDIUM INST.
DETAILS
A. Pressure Gauge
1. Sewage transfer 2 No Sewage Bourdon Waree/WIKA/General/Baumer/Eq
pump
2. Filter feed pump 2 No Filtered water Bourdon Waree/WIKA/General/Baumer/Eq
3. Air Blower Dis 2 No Air Bourdon Waree/WIKA/General/Baumer/Eq
4. Sludge Pump 1 No Sewage Bourdon Waree/WIKA/General/Baumer/Eq
5. PSF outlet 1 No Filtered water Bourdon Waree/ANI/General/Baumer/Eq
6. ACF outlet 1 No Filtered water Bourdon Waree/ANI/General/Baumer/Eq

Page 11
SYMRPL

4.3 Battery Limits

S. Description / Unit Battery limit


No.
1. Raw Sewage At the Bar Screen inlet
2. Individual equipment drain / Backwash / To the nearest drain trench /collection
Flushing waste from respective unit up to 1 m.
3. Treated sewage At ACF outlet up to 2 m distance
4. Sludge At Filter Press outlet
5. Screening/Oil & grease At Screen/O&G trap outlet

4.4 Client Obligations

S.No Description Requirement


1. Power Supply 3 phase 415 V, 50 Hz to MCC feeder
2. Waste Water 15 m3/day
3. Service water At desired points at suitable pressure
4. Storage Facility & area As per requirement

Page 12
SYMRPL

5 POWER & CHEMICAL SCHEDULE

5.1Power Schedule

Sr. Drive Description Connected Qty No. of. No. of


No Power Working Standby
Power Nos
(MKw)

1 Raw Sewage Transfer 0.37 2 1 1


Pump

2 Sludge Pump 0.37 2 1 1

3 Air Blower 0.5 2 1 1

5 Filter Feed Pump 0.75 2 1 1

7 Hypo Dosing Pump 0.18 2 1 1

5.2Chemical Schedule

Sr.No Chemcial Dosing rate Strength Plant Capacity Consumption


ppm % KLD Kg/day

1 Sodium hypo 5 10% 15 1


Chloride

Note: Power & Chemical consumption mentioned in table is tentative & is subjected to
revision during detailed engineering or as per commissioning requirements.

Page 13
SYMRPL

6 LIST OF CIVIL WORKS (Customer Scope)


Sr. Civil Unit MOC Nos. Dimensions (m)
No
LxWxH

1 Bar Screen RCC 1 0.15 x 0.9 x 0.35

2 Oil & Grease RCC 1 1 x 1 x 1.5


Removal

3 Equalization Tank RCC 1 2.5 x 2.5 x 2.5 M

4 MBBR Tank RCC 1 1.8 x 2.2 x 3.0 M


(Partitioned)

5 Settling Tank RCC 1 1.2 x 0.5 x 2.7

6 Treated Water Tank RCC 1 1.8 x 0.35 x 1.3

7 Drain/channel/Buildi Suitable 1 lot Suitable


ng / platform/
staircase/Hand
railing/ Compound
as applicable

Note-The Area & volume specification mentioned above is tentative & subjected to be
revised after fine tuning during detailed engineering or as per commissioning requirements.

Page 14
SYMRPL

7 PRICE, COMMERCIAL TERMS & CONDITIONS

Price
Our price for Design, Engineering, Manufacture, Assembly, Testing and Supply of Equipment
/ Materials with all accessories as per technical specification details specified in this proposal
shall be

Sl. No Description Water Treatment Plant


1. Design & Engineering, Supply, Erection, Rs 5.04 Lakh
Commissioning15 of 100 KLD STP

Rs. Five Lakh Four Thousand Only

Commercial Terms & Conditions

Price Basis
The above price is FOR site inclusive of packing & forwarding, inland freight and Insurance

Taxes
Taxes Extra (18% GST)

Supply Payment terms


40 % as advance
60 % within 15 days on receipt of material at site

Delivery Period
DBSI will be in position to successfully handover the plant within 4-8 weeks, only if following
criteria & supporting activity is met.

1. Receipt of techno-commercial cleared PO with advance payment.


2. Approval of BEP, PID and Layout within one week of submission by DBSI.
3. Readiness of site for commissioning on intimation from DBSI

Erection 1 – 1.5 weeks


Testing & Commissioning 1-2 weeks

Validity
Our offer is valid for a period of 30 days from the date hereof.

Warranty
All components of the equipment except the consumables are backed with 12 months
Warranty of trouble free performance from the date of commissioning or 18 months from
the date of major supply whichever is earlier.