You are on page 1of 3

Weekly report

Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date: 09/16 SEP 18
To: Renders Engineering Consultant
: Eng. Atef

CCS ACTIVITY DESCRIPTION


ACT
NO.
Casting concrete for the first basement columns had been done 100%
01
Dishuttering for the first basement had been done 100%
02
Third stage of waterproofing for retaining wall had been done 85%
03
Struts had been removed 100 %
04
Steel work for the retaining wall in the first basement floor had been started 10%
05
form work for the ground floor slab had been started 5%
06

07

08

This report must be submitted no later than 9:00 a.m. Sheet 1 of 3


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date: 09/16 SEP 18
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 2 of 3


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 00


Date: 09/16 SEP 18
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 3 of 3

You might also like