The weekly report from Alfa Contractor provides progress updates for the period of July 19-25 on a construction project consisting of 2 basement floors, a ground floor, and 4 upper floors plus a gym. Various interior and exterior construction activities are 70-100% complete, including marble installation, epoxy painting, false ceilings, aluminum work, stair railings, kitchen cabinets and lighting fixtures. The report was submitted to Renders Engineering Consultant as report number 41.
The weekly report from Alfa Contractor provides progress updates for the period of July 19-25 on a construction project consisting of 2 basement floors, a ground floor, and 4 upper floors plus a gym. Various interior and exterior construction activities are 70-100% complete, including marble installation, epoxy painting, false ceilings, aluminum work, stair railings, kitchen cabinets and lighting fixtures. The report was submitted to Renders Engineering Consultant as report number 41.
The weekly report from Alfa Contractor provides progress updates for the period of July 19-25 on a construction project consisting of 2 basement floors, a ground floor, and 4 upper floors plus a gym. Various interior and exterior construction activities are 70-100% complete, including marble installation, epoxy painting, false ceilings, aluminum work, stair railings, kitchen cabinets and lighting fixtures. The report was submitted to Renders Engineering Consultant as report number 41.
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
CCS ACTIVITY DESCRIPTION
ACT NO. External interlock work had been done 70% 01 Marble for entrance wall had been done 100% 03 Marble for entrance floor had been done 98% 04 epoxy paint in the second basement floor had been done 100% 08 epoxy paint in the first basement floor had been done 80% 09 False ceiling works in the second floor had been done 100% 10 False ceiling works in the third floor had been done 100 % 11 False ceiling works in the fourth floor had been done 100% 12 False ceiling works in the gym floor had been done 100% 13 Aluminum work for first floor had been done 95% 14 Aluminum work for second floor had been done 95% 15 Aluminum work for third floor had been done 95% 16 Aluminum work for fourth floor had been done 95% 17 Aluminum work for gym floor had been done 95% 18 Stair case handrail had been done 70% 19 Balcony handrail had been done 100% 20 Kitchen cabinet for fourth floor had been done 100% 21 Light fitting in the control room,Lv room had been done 90% 22 Light fitting in the boundary had been done 100% 23 Lv room works had been done 100% 24 Wiring accessories in the first basement had been done 100% 25 Wiring accessories in the second basement had been done 100% 26 Light fitting in the second basement had been done 100% 27 Control room works had been done 80% 28
This report must be submitted no later than 9:00 a.m. Sheet 1 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
Gate barrier installation had been done 80%
29 Fire breaching inlet unstallation had been done 100% 30 Final fix for sprinkler in the ground floor had been done 100% 31 Grills and diffusers in the fourth floor had been done 100% 32
This report must be submitted no later than 9:00 a.m. Sheet 2 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 3 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 4 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 5 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 6 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 7 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 8 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 9 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 10 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 11 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 12 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 13 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 14 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 15 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 16 of 17
Weekly report Project: 2B + G + 4Floors + Gym
Contractor: Alfa Contractor Report No : 41
Date 19 July – 25July 19 To: Renders Engineering Consultant : Eng. Atef
This report must be submitted no later than 9:00 a.m. Sheet 17 of 17