You are on page 1of 17

Weekly report

Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

CCS ACTIVITY DESCRIPTION


ACT NO.
External interlock work had been done 70%
01
Marble for entrance wall had been done 100%
03
Marble for entrance floor had been done 98%
04
epoxy paint in the second basement floor had been done 100%
08
epoxy paint in the first basement floor had been done 80%
09
False ceiling works in the second floor had been done 100%
10
False ceiling works in the third floor had been done 100 %
11
False ceiling works in the fourth floor had been done 100%
12
False ceiling works in the gym floor had been done 100%
13
Aluminum work for first floor had been done 95%
14
Aluminum work for second floor had been done 95%
15
Aluminum work for third floor had been done 95%
16
Aluminum work for fourth floor had been done 95%
17
Aluminum work for gym floor had been done 95%
18
Stair case handrail had been done 70%
19
Balcony handrail had been done 100%
20
Kitchen cabinet for fourth floor had been done 100%
21
Light fitting in the control room,Lv room had been done 90%
22
Light fitting in the boundary had been done 100%
23
Lv room works had been done 100%
24
Wiring accessories in the first basement had been done 100%
25
Wiring accessories in the second basement had been done 100%
26
Light fitting in the second basement had been done 100%
27
Control room works had been done 80%
28

This report must be submitted no later than 9:00 a.m. Sheet 1 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

Gate barrier installation had been done 80%


29
Fire breaching inlet unstallation had been done 100%
30
Final fix for sprinkler in the ground floor had been done 100%
31
Grills and diffusers in the fourth floor had been done 100%
32

This report must be submitted no later than 9:00 a.m. Sheet 2 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 3 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 4 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 5 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 6 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 7 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 8 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 9 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 10 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 11 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 12 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 13 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 14 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 15 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 16 of 17


Weekly report
Project: 2B + G + 4Floors + Gym

Contractor: Alfa Contractor Report No : 41


Date 19 July – 25July 19
To: Renders Engineering Consultant
: Eng. Atef

This report must be submitted no later than 9:00 a.m. Sheet 17 of 17

You might also like