Professional Documents
Culture Documents
BoG Presentation 24 June 2023
BoG Presentation 24 June 2023
Foundation (MHEF)
Hospital Expansion Project
Meeting of Board of Governors, June 24, 2023
EXPANSION PROJECT - MMIH
MAIN HIGHLIGHTS:
Area: 200,000 SQFT
Start Date Of Project: August 15, 2020 BLOCK - 05
BLOCK - 04 BLOCK - 06
CONSULTANTS AND CONTRACTORS
CONSULTANTS:
CONTRACTORS:
4th Floor
3rd Floor
2nd Floor
1st Floor
PROGRESS GRAPH
GENERAL WARD INTERIOR MOCK-UP
ROOM:
3D VIEW OF GENERAL WARD
PRIVATE WARD INTERIOR MOCK-UP
ROOM:
3D VIEW OF GENERAL WARD
BASEMENT OFFICES BLOCK
Pictorial Progress
Work progress is as under;
• Civil Works 95% Complete.
• False Ceiling Works 95% Complete.
• ID Works 95% Complete.
• Electrical Works 95% complete.
• HVAC System 95% complete
• Fire-fighting & Sprinkler 95% complete.
• I.T. Works 90% Complete.
• Furniture 80% Installed.
Target Dates
• Finance, HR, Marketing & MHEF Furniture
have been Placed.
• Work in Progress at Executive Areas &
Finance Marketing rework.