You are on page 1of 1

Project Name: Umm Wu’al Phosphate Project F73015

Contract Number: 16-KB-023


Project Location: Wa’ad Al shammal,KSA

BUILDINGS WATER PROOFING AND DAMP PROOFING CHECKLIST Report No.


Tag Description: Tag No.:
P. O. No.: Inspection Classification Area/Unit:
Contractor: GAC GAC  MPC  Turnover System:
Work Package: PMC  Other  Sub – System:

Item Description of Check GAC PMC


Verify use of correct asphalt material:
01 Bitumen roofing felt
02 Horizontal damp proofing
03 Mastic asphalt
04 Hot application asphalt
05 Bituminous adhesives
06 Bituminous roofing
07 Polyethylene sheet
08 Insulation material
09 Roof slope falls to roof drains
Inspect application of asphaltic materials per design:
10 Surface preparation
11 Coats, laps and thickness
12 Methods of application
13 Temperature of material and surface
14 Manufacturer’s warranty intact

Notes:

GAC PMC MPC

Name: Name: Name:

Signature: Signature: Signature:

Date: Date: Date: