Professional Documents
Culture Documents
Method Statement For RCC Works
Method Statement For RCC Works
METHOD STATEMENT
Content Page No
1) Introduction 4
2) Scope 4
3) Responsibilities 4
4) Equipment 4
5) Procedure 5
6) Safety Measures 6
7) Risk Assessment 6
8) ITP 9
9) Risk Matrix 10
METHOD STATEMENT FOR
3. RESPONSIBILITIES
3.1. The contractor’s approved shop drawing for RCC structural elements shall be
available for inspection by the Engineer.
3.2. All shuttering and reinforcement is to be checked and approved by the Engineer.
3.3. The site engineer shall check that levels are as indicated on the drawings and are
correct. Should there appear to be any discrepancies, the contractor shall correct
levels in consultation with the Engineer.
3.4. The site engineer shall be deemed to have satisfied himself as to the shuttering
and reinforcement works.
3.5. The Project Manager shall be responsible for ensuring that all works are carried out
strictly in accordance with this Method Statement, the requirements of the client
and the overall contract documents.
3.6. The site safety in-charge to ensure that all the works are carried out strictly in
accordance with safety norms.
3.7. The Project Manager shall ensure the preparation and testing of concrete cubes for
compressive strength as specified.
3.8. The Project Manager shall ensure curing as specified and utmost quality shall be
maintained through the works.
7. RISK ASSESSMENT
DOC REF NO FORM RA-011
RISK ASSESSMENT
REV
HAZARD / ACTVITY ASSESSED: REINFORCEMENT WORKS DATE
Severity Likelihood Risk Level Control Measures Existing / to be
Minor = 1 Possible=1 Risk = Severity Low
SN Work Activity / Hazard Identified Cause of Hazards Hazard Effect x Likelihood
Minimize Risk by / Control Measures implemented with target time for
Major = 2 Probable=2 Medium implementation
Fatal = 3 Certain = 3 High
F ailure to follow the safety injury, 1.provide proper working platform to work at height above 2 meter
Working at heights
2 rules while working at permanent Disability, 2 2 4 medium 2.Use proper ppe always such as body harness Immediate
1.Falling from height
heights Fatality 3.Trained people & effective communication
Distributing of steel on position Injury to the person 1, Conduct tool box talk before engaging the work in the job
Improper supervision and 2, Avoiding stacking of steel near to the edges of the slab
2 1.Falling of material during unloading, fracture and material 1 2 2 Low Immediate
not using proper PPE 3, Ensure clear access way from obstacles for frequent movement of
shifting & stacking damage
workers
8. ITP
RESPONSIBLE REFERENCE TYPE OF ACCEPTANCE VERIFYING INSP & TEST CODE
No. DESCRIPTION OF ACTIVITY
PERSON DOCUMENT INSPECTION CRITERIA RECORDS NAF DEC
ITP for Concrete Works.
1 Drawings & Quality Documentation
Preparation of relevant drawings and Project manager, Approved for construction All documents approved or Method Statement,
Review of documents DS
1.1 method statement, Inspection and QA/QC Eng. drawings/ approved as noted. drawings, HSE plan &
Test Plan, HSE procedure. HSE officer Project Specifications Comments – Incorporate and ITP approval
Proceed with works
Project Manager,
Approval for : All documents to be
QA/QC
1. Concrete supplier. Project Specifications approved as noted. Prequalification DS
1.2 Engineer Review of documents
2. Third party materials testing Comments – Incorporate and documents.
(with supplier/
laboratory. Proceed with works
subcontractor)
Materials & Concrete mix
design to conform to
specifications and approved
by Engineer (Cement to BS-
Project Manager, 12, ASTM-150; Aggregates
Concrete mix design & material Project Specifications Material submittal.
1.3 QA/QC Engineer Review of documents. to BS 812,882 & table: 1,2 ; DS
testing prior to production (MIX DESIGN)
Concrete supplier. Water to BS 3148)
Conformity certificates for
admixtures and other
constituents shall be
submitted.
2 Materials and Testing
All Submittals to be
Project Specifications Review of documents & approved as noted. Product data through
2.1 Materials submittal and approval. Site Engineer
Samples Comments – Incorporate and submittal review DS
Proceed with works
Trial mix is carried out &
hardened concrete tested as
Witness the trial &
Concrete trial mix and all concrete Supplier/ QA/QC per BS-1881for strength Approved material
Tests. DS
2.2 constituents, admixtures, curing Eng. / Site Project Specifications requirements result submittal / tests
Review of documents &
materials, and repair materials. Engineer conforming to BS 5328 reports of conformity.
Samples.
part 4, and sulphate &
chloride contents.
Compliance with the
requirements of type II - BS
4449 for physical, chemical
Submission of steel reinforcement and Approved material
and mechanical properties.
accessories. (Spacers, Binding wire Project Specifications submittal DS
2.3 PM, Site Eng. Review of documents Tie wire shall be annealed
etc.) (sample mill
steel wire 16 gauge
Stressing anchors certificates)
complying with BS-4449
Anchors as per approved
(ZETAS) design.
9. RISK MATRIX