QUANTITY OF MATERIALS FROM FOUNDATION TO GABLE

MATERIALS QUANTITY UNIT PRICE TOTAL (GHC)


  3 Bedroom Unit Prices Estimate GHC
Quarry Stones 75 cubic 1600 per 25 cubic 4800
Sand 100 cubic 700 per 25 cubic 2800
Gravel 240 cubic 600 per 25 cubic 7200
Cement 300 22 per bag 6600
Iron rod 1.5 tons 1700 per ton 2550
Foundation blocks 6'' 1500 2.40 per block *
Hollow Quarry dust Block 5'' 3500 2.2 per block *
Metal steel board 100 170 per board *
2x4 wood 70 15 1050
binding wire 2 10 20
Polythene sheets for foundation 4 bundles 300 1200
Concrete nail 4 boxes 10 40
nails 4 boxes 30 per box 120
TOTAL 26,380