Professional Documents
Culture Documents
Refer to Company's response to Pre - Bid Query no. 8 & 9, the process scheme will itself be
modified if cooler (with cooling pads) with additional vessel are to be added. Bidder would re-
iterate his concern to store hydrocarbon near to its boiling points along with Flash point and
this will ingress inherent safety risk for storage of large hydrocarbon storage (i.e. 30000
barrels). The high temperature will release massive vapor flashing and tank normally not
We understand that the storage will be below its boiling point thus in line with OGRA
91 install for handling of such vapor flashing.
regulations. RVP of stabilized oil below or equal to 8 psia will be acceptable.
Furthermore, if cooler is to be added as stated, then temperature of oil will be declined, in
this case, lighter hydrocarbon will be settled and RVP will increase. PPL is requested to
review RVP requirement of stabilized oil as conventional water bath heater (selected by
PPL) has temperature limitation due to water boiling point and lighter end are not completely
removed from oil hence RVP of stabilized oil increases from 7 psia.
Company's response to Pre - Bid Query 11 is noted. Water showering / circulation and
92 Noted
packing arrangement is not required.
Refer to Company's response to Pre - Bid Query no. 14, provision (with valve and blinds)
will be provided as upstream of HP Separator for Future Desalter as advised by PPL. Since
93 Noted
Desalter is not part of scope hence salt will not be separated upto desired vallue as stated
and therefore salt content in product oil will solely be based on inlet feed stream.
Refer to Company's response to Pre - Bid Query no. 17, no other CI injection is required Bidders recommendation is noted, however, bidder may add CI point on the additional
94
other than locations specfied in ITB. locations if identified subsequently.
Company's response to Pre - Bid Query 18 is noted. Bidder will consider facility inlet
operating condition as illustrated in provided simulation by PPL in PBC-1.
1. Noted.
2. The facility inlet PSV will be set at 1350 psig on Blocked Outlet condition. The Flare KOD
95 Noted
will be sized on 30 minutes hold-up time of liquid from PSV discharge (i.e. worst scenario
from all other PSVs).
3. Manual choke valve will provide to have fix pressure at upstream of PCV and to limit PCV
failure beyond relief load from design case (i.e. EPF inlet PSV blocked-outlet scenario).
Company's response to Pre - Bid Query 21 is noted.
96 For Point No. 5, quality of rejected water will be shared once bore water assessment to be Noted
performed after award of contract.
Company's response to Pre - Bid Query 27 is noted, however 10 barrels slug volume is
97 Noted
considered in HP Separator sizing for the same, as advised by PPL in ITB.
Company's response to Pre - Bid Query 28 is noted. PPL to note that 0.2 psi pressure drop
across 6" vent header for Tank in Dispersion Study of ITB is even higher than design
98 Noted, however, the tank design pressure can be upto 2.5 psig as per API 650.
pressure of Oil Storage Tank (i.e. 100 mm H2O), therefore Bidder has performed analysis
and found that vent line will be 8" (instead of 6") and vent stack dia will be 6" (instead of 4").
Refer to Company's response to Pre - Bid Query no. 30, Bidder has evaluated NACE
required as per MR-0175 and found that for 100 ppm H2S, if operating pressure reaches up
99 to 500 psig then NACE is applicable for the relevant equipment. In this EPF, only Noted
compressor is therefore required as NACE Compliant as per MR-0175. Remaining whole
facility including HP & LP Separators are not required as NACE compliant.
Bidder has NOT considered batch metering for oil before loading. Simple Turbine flowmeter Noted, however, provision to record storage tank level monitoring via dip should also
100
is considered for oil metering. Please confirm PPL requirement. be provided.
Refer to Company's response to Pre - Bid Query no. 45, Bidder proposes to use attached
specification for the procedure of Stress Analysis which was considered in past project as
101 Noted
understanding over these specifications is already developed between client and bidder.
Please confirm.
Company's response to Pre - Bid Query 48 is noted. Non-U Stamped vessels have been
102 Noted
considered from ASME certified workshops.
Company's response to Pre - Bid Query 49 is noted. Bidder will submit the Conceptual Plot Noted, however Company will verify the proposed plot plan in line with the
103
Plan along with Technical Proposal as basis of bid for company`s information. requirements of codes and standards and regulation, statutory requirments etc.
Company's response to Pre - Bid Query 54 is noted. Bidder will submit the Conceptual Plot
104 Please refer Company's response to Bidder's query no. 103 above.
Plan along with Technical Proposal as bidding basis for company`s information.
Company's response to Pre - Bid Query 55 is noted. However Bidder proposes to use
attached specification for Equipment design, Insultaion which was considered in past
project as understanding over these specifications is already developed between client and
Noted, however this may please be noted that those specification provided with ITB
105 bidder. Please confirm.
must be followed.
Furthermore, Valves specifications as mentioned in different Piping Specs are missing,
Please share.
Company's response to Pre - Bid Query 56 is noted. We are considering Gas Gensets for 3
106 Noted based on bidder's confirmation.
x 55% operating philosophy.
Company's response to Pre - Bid Query 61 is noted. We are considering all incoming and
107 Noted
outgoing feeder breakers with LSIG units
Company's response to Pre - Bid Query 62 is noted. As basic requirement, we are Noted, Bidder to supply the electrical system in compliance to the ITB requirement,
108
considering Load Flow and Short Circuit system studies for electrical system design. therefore, bidder to assess the requirement of electrical system studies at its own.
Company's response to Pre - Bid Query 63 is noted. However, where specific standards are
109 not provided, relevant international standards and good engineering practices shall be Noted
considered.
Refer to Company's response to Pre - Bid Query no. 71, BFA system with Smoke Detection
110 Noted
is being considered. We understand FM200 system is not required.
Refer to Company's response to Pre - Bid Query no. 72, Since soil report is not available,
therefore for Bidding Purpose, shallow foundations are being considered for this project with
allowable soil bearing capacity of 100 Kpa @ 1.5m depth from NGL / FGL.
Bidder is responsible for correctness of design of the facility with respect to its integrity
111
etc.
Clause # 12 (Page # 37 of Document - Last Bullet or Page # 68 of PDF File # 15121-ITB
DOCUMENT) states that Soil Report from EPC Contractor will be verified by Company Soil
Report.
Refer to Company's response to Pre - Bid Query no. 74, Sheds over Compressor & Genset
Company reiterate bidders to assess the requirment of shed as Plant O&M will be in
112 with Over Head Crane are not being considered in this Bid will be given as Optional in
bidders scope.
Techno Commercial Bid.
Refer to Company's response to Pre - Bid Query no. 76, Future 3 Tanks and their related
113 Noted
Civil Infrastructes like Tank Foundations, Dyke Wall etc. are not considered in bidder scope.
Refer to Company's response to Pre - Bid Query no. 78, 2.4m high Fence around facility is
114 Please refer Company's response to Bidder's query no. 87 above.
being considered for this project. Please confirm.
Company's response to Pre - Bid Query 80 is noted. Same will be discussed with PPL after
115 Please refer Company's response to Bidder's query no. 135 above.
Site Visit.
Refer to Company's response to Pre - Bid Query no. 81, SOW will be as per shared plot
116 Bidders query require further illustration.
plan along with our BID.
Refer to Company's response to Pre - Bid Query no. 82, this will be discussed & confirmed
117 Please refer Company's response to Bidder's query no. 88 above.
after Site Visit.
Refer to Company's response to Pre - Bid Query no. 83, followng is being considered as our
SOW for this BID:
MASJID: 20 ft x 8 ft x 2 Nos. Comnined Porta Cabins Containers
Noted, however Bidder to provide all the services to Company's personal as
118
mentioned in ITB.
RECREATIONAL AREA: 20 ft x 8 ft x 1 Nos. Porta Cabins Container.
Trucks & Bowsers Parkings are considered without any parkings shed / paved area.
6) CCR & MCC ROOM: 20 ft x 8 ft x 2 Nos. Combined Porta Cabins Container is considered
for this.