Professional Documents
Culture Documents
Item No. : I
Description : PERMITS, FEES, OTHERS
Quantity : 1.00 LOT
Others :
1.0 Construction Safety & Health :
1.1 Safety Signages / Accessories 1.00 lot 35,000.00 35,000.00
1.2 Hard Hats, Safety Shoes & Belts, etc., & First Aid Packages. 1.00 lot 60,000.00 60,000.00
2.0 Temporary Facilities :
2.1 Contractor's Field Office / Bunkhouses. 1.00 lot 60,000.00 60,000.00
Item No. : II
Description : SITE WORKS
Quantity : 912.43 CU.M.
A. MATERIALS
Description Qty Unit Unit Cost Amount
EARTHWORKS : P P
Excavation 286.50 cu.m 450.00 128,925.00
Gravelfill 19.66 cu.m 1,400.00 27,524.00
Backfill 286.50 cu.m 450.00 128,925.00
SOIL TREATMENT :
Termite Proofing Materials 1.00 lot 40,000.00 40,000.00
Total - Materials : P 325,374.00
B. LABOR
Description No. Days Rate Amount
Total - Equipment : P -
ITEM ESTIMATED DIRECT COST (A+B+C) : P 414,374.00
ITEM ESTIMATED INDIRECT COST :
Profit 5% 20,718.70
OCM 8% 33,149.92
VAT 12% 56,189.11
TOTAL ITEM ESTIMATED INDIRECT COST : P 110,057.73
TOTAL ITEM COST (Direct Cost + Indirect Cost) : P 524,431.73
ITEM UNIT COST / CU.M. : P 574.76
A. MATERIALS
Description Qty Unit Unit Cost Amount
195.32
Footing cu.m.
Rebars 2,311.00 kls P 44.00 P 101,684.00
Ready-Mixed Concrete, 3,000 psi. 49.55 cu.m 4,300.00 213,065.00
Column 51.76 cu.m.
Rebars 6,288.00 kls 44.00 276,672.00
Ready-Mixed Concrete, 3,000 psi. 51.76 cu.m 4,300.00 222,568.00
Beam / Roof beam 50.06 cu.m.
Rebars 6,658.00 kls 44.00 292,952.00
Ready-Mixed Concrete, 3,000 psi. 50.06 cu.m 4,300.00 215,258.00
Footing tie beam 17.09 cu.m.
Rebars 2,681.00 kls 44.00 117,964.00
Ready-Mixed Concrete, 3,000 psi. 17.09 cu.m 4,300.00 73,487.00
Suspended Slab 40.84 cu.m.
Rebars 3,412.00 kls 44.00 150,128.00
Ready-Mixed Concrete, 3,000 psi. 40.84 cu.m 4,300.00 175,612.00
Slab on fill 35.57 cu.m.
Rebars 1,094.00 kls 44.00 48,136.00
Ready-Mixed Concrete, 2,500 psi. 35.57 cu.m 4,300.00 152,951.00
Formworks & Scaffoldings
Steel forms 1.00 lot 50,000.00 50,000.00
Ordinary plywood 1/4 " thk 200.00 shts 650.00 130,000.00
Assorted coco 680.00 lngth 150.00 102,000.00
Assorted nails 50.00 kls 80.00 4,000.00
Miscellaneous 1.00 lot 20,000.00 20,000.00
-
Total - Materials : P 2,346,477.00
B. LABOR
Description No. Days Rate Amount
Item No. : IV
Description : MASONRY WORKS
Quantity : 352.00 SQ.M.
A. MATERIALS
Description Qty Unit Unit Cost Amount
Concrete Hollow Blocks (CHB) Laying :
Concrete Hollow Blocks (CHB), 6". 352.00 sq.m P 680.00 P 239,360.00
Miscellaneous 1.00 lot 25,000.00 25,000.00
Total - Materials : P 264,360.00
B. LABOR
Description No. Days Rate Amount
Foreman 1.00 20.00 P 500.00 P 10,000.00
Skilled Laborer 4.00 20.00 380.00 30,400.00
Laborer 7.00 20.00 280.00 39,200.00
Total - Equipment : P
ITEM ESTIMATED DIRECT COST (A+B+C) : P 343,960.00
ITEM ESTIMATED INDIRECT COST :
Profit 5% 17,198.00
OCM 8% 27,516.80
VAT 12% 46,640.98
TOTAL ITEM ESTIMATED INDIRECT COST : P 91,355.78
TOTAL ITEM COST (Direct Cost + Indirect Cost) : P 435,315.78
ITEM UNIT COST / SQ.M.: P 1,236.69
Item No. : V
Description : STEEL WORKS
Quantity : 1.00 LOT
A. MATERIALS
Description Qty Unit Unit Cost
Roof Framing
Truss -1 2 units
Angle Bar, 2" x 2" x 3/16" x 6m 5.00 length 1,600.00
Angle Bar, 1 1/2" x 1 1/2" x 3/16" x 6m 4.00 length 950.00
Truss -2 2 units
Angle Bar, 2" x 2" x 3/16" x 6m 9.00 length 1,600.00
Angle Bar, 1 1/2" x 1 1/2" x 3/16" x 6m 7.00 length 950.00
HT-1 2 units
Angle Bar, 2" x 2" x 3/16" x 6m 10.00 length 1,600.00
Angle Bar, 1 1/2" x 1 1/2" x 3/16" x 6m 8.00 length 950.00
HT-2 4 units
Angle Bar, 2" x 2" x 3/16" x 6m 14.00 length 1,600.00
Angle Bar, 1 1/2" x 1 1/2" x 3/16" x 6m 13.00 length 950.00
HT-3 6 units
Angle Bar, 2" x 2" x 3/16" x 6m 38.00 length 1,600.00
Angle Bar, 1 1/2" x 1 1/2" x 3/16" x 6m 28.00 length 950.00
HT-4 4 units
Angle Bar, 2" x 2" x 3/16" x 6m 31.00 length 1,600.00
Angle Bar, 1 1/2" x 1 1/2" x 3/16" x 6m 42.00 length 950.00
HT-5 1 units
Angle Bar, 2" x 2" x 3/16" x 6m 6.00 length 1,600.00
Angle Bar, 1 1/2" x 1 1/2" x 3/16" x 6m 7.00 length 950.00
HT-6 4 units
Angle Bar, 2" x 2" x 3/16" x 6m 11.00 length 1,600.00
Angle Bar, 1 1/2" x 1 1/2" x 3/16" x 6m 9.00 length 950.00
HT-7 8 units
Angle Bar, 2" x 2" x 3/16" x 6m 17.00 length 1,600.00
Angle Bar, 1 1/2" x 1 1/2" x 3/16" x 6m 12.00 length 950.00
HT-8 4 units
Angle Bar, 2" x 2" x 3/16" x 6m 9.00 length 1,600.00
Angle Bar, 1 1/2" x 1 1/2" x 3/16" x 6m 5.00 length 950.00
HT-9 2 units
Angle Bar, 2" x 2" x 3/16" x 6m 12.00 length 1,600.00
Angle Bar, 1 1/2" x 1 1/2" x 3/16" x 6m 12.00 length 950.00
Purlins
LC-150 x 50 x 14 x 1.2mm x 6m 130.00 length 650.00
Sag Rods
Deformed Bar, 10mm Ø x 6m 40.00 length 163.00
Standard nuts & washer 1.00 lot 5,000.00
Anchorage
Steel Plate, 12.5mm thk 67.00 pcs 2,200.00
Anchor Bolts, 20mm dia. X 200mm 134.00 pcs 350.00
Steel Plete, 6mm thk 298.00 pcs 1,300.00
Bolts, 12mm dia. 298.00 pcs 50.00
J -Bolts, 12mm dia. 298.00 pcs 100.00
Miscellaneous (Including: welding rods / acytelene / oxygen / red 1.00 lot 40,000.00
lead )
Other Works
Cyclone Fence & Steel Rafter
L = 20.70 m ; W =11.20 m = 3.00 m
Tubular Steel Post, 200mm x 200mm x GA #14 24.00 lngth 8,000.00
Tubular Steel Post, 150mm x 50mm x GA #16 126.00 lngth 3,500.00
Mesh Galvanized Cyclone Wire, 50mm 50mm x GA#10 210.00 sq.m. 450.00
Miscellaneous (Including: welding rods / acytelene / oxygen / red 1.00 lot 20,000.00
lead )
Total - Materials : P
B. LABOR
Description No. Days Rate
Foreman 1.00 40.00 P 500.00 P
Skilled Laborer 7.00 40.00 380.00
Laborer 10.00 40.00 280.00
Total - Labor : P
C. EQUIPMENT
Description No. Days Rate
Total - Equipment : P
ITEM ESTIMATED DIRECT COST (A+B+C) : P
ITEM ESTIMATED INDIRECT COST :
Profit 5%
OCM 8%
VAT 12%
TOTAL ITEM ESTIMATED INDIRECT COST : P
TOTAL ITEM COST (Direct Cost + Indirect Cost) : P
ITEM UNIT COST / LOT: P
8,000.00
3,800.00
14,400.00
6,650.00
16,000.00
7,600.00
22,400.00
12,350.00
60,800.00
26,600.00
49,600.00
39,900.00
9,600.00
6,650.00
17,600.00
8,550.00
27,200.00
11,400.00
14,400.00
4,750.00
19,200.00
11,400.00
84,500.00
6,520.00
5,000.00
147,400.00
46,900.00
387,400.00
14,900.00
29,800.00
40,000.00
192,000.00
441,000.00
94,500.00
20,000.00
1,908,770.00
Amount
20,000.00
106,400.00
112,000.00
238,400.00
Amount
120,000.00
96,000.00
216,000.00
2,363,170.00
118,158.50
189,053.60
320,445.85
627,657.95
2,990,827.95
2,990,827.95
Date
DETAILED COST ESTIMATES
Item No. : VI
Description : TINSMITHING
Quantity : 448.80 SQ.M.
A. MATERIALS
Description Qty Unit Unit Cost Amount
Ga 24 GI roofing 75.00 pcs P 1,000.00 P 75,000.00
GI Steel gutter 120.00 l.m. 300.00 36,000.00
Hardi senepa 120.00 l.m. 150.00 18,000.00
GI ridge roll 165.00 l.m. 250.00 41,250.00
Miscellaneous 1.00 lot 10,000.00 10,000.00
Total - Materials : P 180,250.00
B. LABOR
Description No. Days Rate Amount
Foreman 1.00 13.00 P 500.00 P 6,500.00
Skilled Laborer 4.00 13.00 380.00 19,760.00
Laborer 5.00 13.00 280.00 18,200.00
Total - Equipment : P
ITEM ESTIMATED DIRECT COST (A+B+C) : P 224,710.00
ITEM ESTIMATED INDIRECT COST :
Profit 5% 11,235.50
OCM 8% 17,976.80
VAT 12% 30,470.68
TOTAL ITEM ESTIMATED INDIRECT COST : P 59,682.98
TOTAL ITEM COST (Direct Cost + Indirect Cost) : P 284,392.98
ITEM UNIT COST / SQ.M. : P 633.67
A. MATERIALS
Description Qty Unit Unit Cost Amount
A. MATERIALS
Description Qty Unit Unit Cost Amount
Lighting Fixtures
A*15Watts LED Glass Tube T8 with starter, 1200mm
Daylight 230V with 12" x 48",Wide Recessed Aluminum 11.00 sets P 1,600.00 P 17,600.00
Reflector Louver Type
B*8Watts LED Glass Tube T8 with starter, 600mm Daylight
230V with 12" x 24",Wide Recessed Aluminum Reflector 22.00 sets 1,100.00 24,200.00
Louver Type 1yr warranty
Duplex Universal Outlet w/ Ground & Safety Shutter ,Block 51.00 sets 320.00 16,320.00
Type & Wide Series
Aircon Multi Universal
Single Gang Outlet w/ Outlet
Groundw/, Wide
Ground wide
series series
( For
3.00 sets 500.00 1,500.00
Emergency Lamp ) 3.00 sets 500.00 1,500.00
Single Gang Switch w/ LED, Wide series 33.00 sets 200.00 6,600.00
Two Gang Switch with LED, Wide Series 10.00 sets 220.00 2,200.00
Three Gang Switch w/ LED, Wide series 3.00 sets 240.00 720.00
Three Ways Switch w/ LED, Wide series 10.00 sets 350.00 3,500.00
Wiring Works
Stranded Wire 3.5mm² THW 14.00 box 3,200.00 44,800.00
Stranded Wire 5.5mm² THW 8.00 box 4,800.00 38,400.00
Stranded Wire 30mm² THW 80.00 l.m. 280.00 22,400.00
Stranded Wire 8,0mm² ( Must be Green for Ground Wire) 1.00 box 8,000.00 8,000.00
Stranded Wire 2.0 mm² ( Must be Green for Ground Wire) 6.00 box 2,200.00 13,200.00
Rough-in Works (Incl. Conduits, Boxes, Tapes & Fittings)
PVC Pipe 20mm 500.00 lengths 200.00 100,000.00
PVC elbow 40mm 10.00 pcs 70.00 700.00
PVC Pipe 40mmØ 15.00 lengths 330.00 4,950.00
PVC electrical tape (3M) 5.00 doz 380.00 1,900.00
PVC solvent 400cc 4.00 cans 380.00 1,520.00
PVC Utility Box, 2x4 112.00 pcs 20.00 2,240.00
PVC Junction Box, 2x4x4 with cover 127.00 pcs 17.00 2,159.00
Copper Grounding Rod 1/2 x 5 ft with Clamp 1.00 lot 1,000.00 1,000.00
Concrete Pullbox Manhole 800mm x800mm inside w/
chekered plate cover
1.00 lot 4,000.00 4,000.00
Protective Device
NEMA Panel Board (Metal Panel)with Two (2) Blank Spare
and Grounding Terminal Block 1.00 set 40,000.00 40,000.00
Main CB:
1 - 125AT, 230V, 2P, 60Hz, 25 KAIC BOLT-ON
Branches:
9- 15AT, 2P, 230V,60hz 10 KA Rail Type
7- 20AT , 2P, 230V60hz, 10KA Rail Type
6- 30AT , 2P, 230V60hz, 10KA Rail Type
NEMA 3R Manual Transfer Switch( MTS) 150AT 3P 25kaic
Bolt-on with Voltmeter, Ammeter, 2 Pilot LED lamp 1.00 set 8,000.00 8,000.00
Concrete Pedestal 12' x12' x 16FT (See Plans) 1.00 lot 10,000.00 10,000.00
Others
Total - Equipment : P
ITEM ESTIMATED DIRECT COST (A+B+C) : P 692,099.00
ITEM ESTIMATED INDIRECT COST :
Profit 5% 34,604.95
OCM 8% 55,367.92
VAT 12% 93,848.62
TOTAL ITEM ESTIMATED INDIRECT COST : P 183,821.49
TOTAL ITEM COST (Direct Cost + Indirect Cost) : P 875,920.49
ITEM UNIT COST / LOT : P 875,920.49
Item No. : IX
Description : WATERPROOFING
Quantity : 42.30 SQ.M.
A. MATERIALS
Description Qty Unit Unit Cost Amount
WATERPROOFING :
Sika top or equivalent 4.00 gal P 950.00 P 3,800.00
Synthetic brush 3.00 pcs 100.00 300.00
Miscellaneous 1.00 lot 4,000.00 4,000.00
Total - Materials : P 8,100.00
B. LABOR
Description No. Days Rate Amount
Foreman 1.00 2.00 P 500.00 P 1,000.00
Skilled Laborer 1.00 2.00 380.00 760.00
Laborer 1.00 2.00 280.00 560.00
Total - Equipment : P
ITEM ESTIMATED DIRECT COST (A+B+C) : P 10,420.00
ITEM ESTIMATED INDIRECT COST :
Profit 5% 521.00
OCM 8% 833.60
VAT 12% 1,412.95
TOTAL ITEM ESTIMATED INDIRECT COST : P 2,767.55
TOTAL ITEM COST (Direct Cost + Indirect Cost) : P 13,187.55
ITEM UNIT COST / SQ.M. : P 311.76
Item No. : X
Description : SEPTIC TANK
Quantity : 1.00 EACH
A. MATERIALS
Description Qty Unit Unit Cost Amount
CHB 4 " 238.00 pcs P 16.00 P 3,808.00
Portland cement 26.00 bags 230.00 5,980.00
Washed sand 1.69 cu.m. 1,400.00 2,366.00
Washed gravel 1.62 cu.m. 1,400.00 2,268.00
Fine sand 0.32 cu.m. 1,400.00 448.00
Deformed bars 10 mm Ø 22.00 length 163.00 3,586.00
Tie wire # 16 1.00 kls 70.00 70.00
Ordinary plywood 1/4 " 3.00 shts 650.00 1,950.00
Coco lumber 5.00 lngths 150.00 750.00
Assorted nails 3.00 kls 80.00 240.00
PVC pipe 100 mm Ø 2.00 length 700.00 1,400.00
PVC tee 100 mm Ø 4.00 pcs 170.00 680.00
PVC clean - out 100 mm Ø 4.00 pcs 250.00 1,000.00
PVC solvent 400 cc 1.00 can 380.00 380.00
Waterproofing materials 1.00 lot 10,000.00 10,000.00
Miscellaneous 1.00 lot 10,000.00 10,000.00
Total - Materials : P 44,926.00
B. LABOR
Description No. Days Rate Amount
Foreman 1.00 5.00 P 500.00 P 2,500.00
Skilled Laborer 2.00 5.00 380.00 3,800.00
Laborer 4.00 5.00 280.00 5,600.00
Total - Equipment : P
ITEM ESTIMATED DIRECT COST (A+B+C) : P 56,826.00
ITEM ESTIMATED INDIRECT COST :
Profit 5% 2,841.30
OCM 8% 4,546.08
VAT 12% 7,705.61
TOTAL ITEM ESTIMATED INDIRECT COST : P 15,092.99
TOTAL ITEM COST (Direct Cost + Indirect Cost) : P 71,918.99
ITEM UNIT COST / EACH : P 71,918.99
Item No. : XI
Description : PROJECT BILLBOARD / SIGN BOARD
Quantity : 1.00 EACH
A. MATERIALS
Description Qty Unit Unit Cost Amount
Tarpaulin 1.00 lot P 1,500.00 P 1,500.00
Brace (Lumber) 15.00 length 140.00 2,100.00
Common Wire Nails 5.00 kls 70.00 350.00
Marine Plywood 1/4 x 4 x 8 2.00 shts 950.00 1,900.00
Miscellaneous 1.00 lot 1,000.00 1,000.00
Total - Equipment : P -
ITEM ESTIMATED DIRECT COST (A+B+C) : P 9,170.00
ITEM ESTIMATED INDIRECT COST :
Profit 5% 458.50
OCM 8% 733.60
VAT 12% 1,243.45
TOTAL ITEM ESTIMATED INDIRECT COST : P 2,435.55
TOTAL ITEM COST (Direct Cost + Indirect Cost) : P 11,605.55
ITEM UNIT COST / EACH : P 11,605.55
A. MATERIALS
Description Qty Unit Unit Cost Amount
MOBILIZATION / DEMOBILIZATION 1.00 lot P 50,000.00 P 50,000.00
Foreman P P -
Skilled Laborer -
Laborer -
Total - Labor : P -
C. EQUIPMENT
Description No. Days Rate Amount
Total - Equipment : P
ITEM ESTIMATED DIRECT COST (A+B+C) : P 50,000.00
ITEM ESTIMATED INDIRECT COST :
Profit 5% 2,500.00
OCM 8% 4,000.00
VAT 12% 6,780.00
TOTAL ITEM ESTIMATED INDIRECT COST : P 13,280.00
TOTAL ITEM COST (Direct Cost + Indirect Cost) : P 63,280.00
ITEM UNIT COST / LOT : P 63,280.00