Project Name: Shop 4m x 4m

Custome Name: Geedi Date: 04/02/2019

No Item Description Length m Width m Height m Unit Quantity Rate Amount


1 Mobilazation ls $ 1,000.00
2 Site Clearance 4 4 SQM 16 2 $ 32.00
3 Excavation Foundation 16.8 0.4 0.8 CUM 5.376 25 $ 134.40
4 Lean Concrete 16.8 0.4 0.1 CUM 0.672 300 $ 201.60
5 Mansonry Foundation 16.8 0.4 1.6 CUM 10.752 40 $ 430.08
6 Foundation Beam 16.8 0.4 0.2 CUM 1.344 150 $ 201.60
7 Backfiling 3.4 3.4 0.9 CUM 10.404 6 $ 62.42
8 Hallow Blocks Bellow Lin 16 4 SQM 64 18 $ 1,152.00
9 Lintel Beam 16 0.2 0.2 CUM 0.64 150 $ 96.00
Hallow Blocks Above
10 the Lintel 16 2 SQM 32 18 $ 576.00
Corrugated Irone
11 Sheets 4 4 SQM 18.4 22 $ 404.80
12 Plastering Interior /exteri 16 6.2 SQM 198.4 6.5 $ 1,289.60
13 White Washing 16 6.2 SQM 198.4 2 $ 396.80
14 Distampering 16 6.2 SQM 198.4 3 $ 595.20
15 Ceilling 4 4 SQM 16 14 $ 224.00
16 Floor Tiles 4 4 SQM 16 12 $ 192.00
17 Windows 1.2 1 SQM 1.2 100 $ 120.00
18 Wood Door Pcs 1 250 $ 250.00
19 Electric 4 4 SQM 16 5 $ 80.00
20 Fasia 16 lm 16 2 $ 32.00

Grand Total $ 7,470.50