Name of Subwork: Widening of RCC Slab culvert at Km 34/8 of NH 230 (Madurai -

Thondi Road) (New No. NH 85)


Detailed Estimate 5 m Eff. Span

Sl.
Description No Length in m Breadth in m Depth in m Quantity
No
1 Dismantling the RR masonry as specified by departmental officers and
cleaning away the debris and carefully stacking the useful materials including
all labour and all other incidental charges etc., complete

Parapet 1 x 2 10.00 0.450 0.450 4.05


Wing walls 2 x 2 5.00 0.450 1.200 10.80
14.85 m3

2 Earthwork excavation in all calsses of soils except hard rock requiring blasting
and depositing on bank with all leads and lifts as per SS20B, including cost of
all labour, equipments and all incidental charges such as providing and
maintaining necessary cofferdams, sheeting,shoring, bracing, and their
subsequent removal, removal of all logs, stumps and other deleterious matter
and obstructions, trimming bottom of excavation backfilling, and clearing the
site and disposal of all surplus materials etc, complete as per relevant
standard specification for FOUNDATIONS FOR ABUTMENTS WING
WALL etc., complete
Left side & Right side

Abutment 1 x 2 (4.04+1.2)/2 4.700 2.000 49.26

Wings 1 x 2 (4.75+0.05)/2 2.840 2.000 27.26


76.52 m3

3 Vibrated cement concrete of grade M15 mix 1:1.5:3 using 40mm ISS HBG
metal including cost and conveyance of all materials to site and cement at site
including cost of formwork, soft water,labour charges for mixing,
transporting, laying and curing concrete, working at depths,Tools and Plants
and incidental charges such as maintaining of protective bunds, cofferdams,
shoring, strutting etc; complete as per relevant standard specification for
FOOTINGS OF ABUTMENT, WINGS, AND PIERS. 1 Cu.m(Below Sill
level)
Left side & Right side
Abutment

I Footing 1 x 2 (4.04+1.2)/2 4.700 0.200 4.93

II Footing 1 x 2 (4.04+1.2)/2 4.300 0.200 4.51


III Footing 1 x 2 (3.84+1.4)/2 3.900 0.400 8.17
Sl.
Description No Length in m Breadth in m Depth in m Quantity
No
((3.84+3.44)/2+1.
IV Footing 1 x 2 (3.9+3.5)/2 0.400 7.46
4)/2
Sl.
Description No Length in m Breadth in m Depth in m Quantity
No
Wings
I Footing 1 x 2 (4.75+0.05)/2 2.840 0.400 5.45
II Footing 1 x 2 (4.35+0.45)/2 2.440 0.400 4.68
((4.35+3.95)/2+0.
III Footing 1 x 2 (2.44+2.04)/2 0.400 4.12
45)/2
Abutment

Front Batter 1 x 2 (3.44+3.31)/2 (0.35+0.26)/2 0.800 1.65

Bearing 1 x 2 3.000 1.000 0.800 4.80

DirtWall 1 x 2 3.000 0.300 0.800 1.44

Rear Batter 1 x 2 (1.4+1.63)/2 (1.25+0.99)/2 0.800 2.71

Wing

Front Batter 1 x 2 (3.65+3.56)/2 (0.44+0.31)/2 0.800 2.16

Rear Batter 1 x 2 (0.75+1.01)/2 (1.1+0.87)/2 0.800 1.39

Centre Portion 1 x 2 2.000 0.500 0.800 1.60

Top Plug at sill


1 x 1 4.040 3.300 0.150 2.00
level
57.07 m3

4 Vibrated cement concrete M15 grade Mix 1:1.5:3 usnig 40 mm ISS size hard
granite broken metal including cost and conveyance of all materials to site and
cement at site including labour charges for mixing, transporting, laying,
curing concrete, working at heights, hire charges for Tools and Plants
including all other incidental charges etc, complete for SUBSTRUCTURE OF
ABUTMENTS WINGS AND PIERS -1 Cum (Above sill level)
Left side & Right side

Abutment

Front Batter 1 x 2 (3.31+3)/2 (0+0.26)/2 2.250 1.85

Bearing 1 x 2 3.000 1.000 2.250 13.50

DirtWall 1 x 2 3.000 0.300 3.000 5.40

Rear Batter 1 x 2 (1.63+2.5)/2 (0+0.99)/2 3.000 6.13

Wing
Sl.
Description No Length in m Breadth in m Depth in m Quantity
No
Front Batter 1 x 2 (3.56+3.3)/2 (0+0.31)/2 2.250 2.39
Rear Batter 1 x 2 (1.01+2)/2 (0+0.87)/2 3.000 3.93

Centre Portion 1 x 2 2.000 0.500 3.000 6.00

Parapet

over deck 1 x 1 5.960 0.500 0.600 1.79


over wings 1 x 2 2.300 0.500 0.600 1.38
42.37 m3
5 Vibrated reinforced cement concrete M25 grade Design Mix using ISS size
hard granite broken graded metal including cost and conveyance of all
materials to site and cement at site including labour charges for mixing,
transporting, laying, curing concrete, working at heights, hire charges for
tools and plants, including all other incidental chargeas, etc., complete for
BEDBLOCK OVER ABUTMENTS AND PIERS. -1 Cum (For Estimate
Purpose, mix (1:1.5:3)
Left side & Right side

Bed Block 1 x 2 3.000 1.025 0.500 3.08

3.08

6 Vibrated reinforced cement concrete M:25 using 20mm ISS HBG metal
including cost and conveyance ofall materials to site including cement which
will be supplied by the Department at the departmental stores or at site of
work and its cost recovered as stipulated in the special conditions appended
herewith including cost of form work, soft water, labour charges for mixing,
transporting, laying and curing concrete, working at depths, tools and plants
and incidental charges such as baling cut water, maintaining of protective
bunds, cofferdams, shoring, structting etc., complete asper relevent standard
specification, for DECKSLAB AND KERB -1Cum
Left side & Right side

Deck Slab 1 x 1 3.000 5.960 (0.58+0.5)/2 9.66

9.66

7 Supply of HYSD steel for Reinforcement for RCC work including bending,

placing and binding etc., for Deck slab, Bed Block & surface Reinforcement.
Deck Slab 1 x 1 2.78 2.78 MT

Super Structure= 2.78 MT


Sl.
Description No Length in m Breadth in m Depth in m Quantity
No
Bed Block 1 x 1 0.73 0.73 MT

Total Sub Structure= 0.73 MT

8 Providing and fixing kraft paper for full width of seating of deck spab and
including cost and conveyance to worksite labour for fixing the same in
correct position and all other incidental charges etc. complete.

L/S & R/S 1 x 2 3.000 1.025 6.15

6.15 m2

9 Providing and fixing 20 mm thick compressible fibre board in expansion joint


complete as per drawing and technical specifications

Area Calc. 1 x 2 3.000 (0.58+0.5)/2 3.24


Area of Single
1 x 1 12.000 0.250 3.00
Fibre
Total No of Fibre
1 x 1 3.24/3 1.08
req.
Total length of
1 x 2 12.000 24.00
Fibre req.
24.00 Rm

10 Providing and fixing 12mm thick corrugated copper plate in expansion joint
complete as per drawing and technical specifications

L/S & R/S 1 x 2 3.000 6.00


6.00 Rm

11 Providing and fixing 20 mm thick premoulded joint filler in expansion joint


for fixed ends of simple supported spans not exceeding 10 m to cater for a
horizontal movement upto 20 mm covered with sealent complete as per
drawing and technical specifications

L/S & R/S 1 x 2 3.000 6.00


6.00 Rm

12 Providing and filling joint sealing compound complete as per drawing and
technical specifications
L/S & R/S 1 x 2 3.000 6.00
6.00 Rm
Sl.
Description No Length in m Breadth in m Depth in m Quantity
No
13 Providing filter media behind the abutments and wings with clean III
graded material 53mm to 5.6mm to 600mm thick and well compacted in
layers with smaller sized towards the soil and bigger size towards the wall
including cost and conveyance to work site including all labours and other
incidental charges including hire charges for tools and plants employed etc.,
for filter media as per MOST's (Roads Wing) specifications for Roads and
Bridges " Fourth Revision Cl. 309-3-2-13 and 305 -4-4 etc., complete- 1Cum.
Left side & Right side

Abutment 1 x 2 (1.63+2.5)/2 0.600 3.000 7.43

Wings 1 x 2 (0.41+1.4)/2 0.600 3.000 3.26

D/d for pavement 1 x -2 1.200 0.600 0.455 -0.66

` or 10.04 m3
14 Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.30 Kg/sqm on the prepared bituminous /
granular surface cleaned with mechanical broom over existing concrete
surface.
Left side & Right side
Deck Slab 1 x 1 2.500 5.960 …. 14.9
14.90 m2
15 Providing and laying bituminous concrete with 100 - 120 THP hot mix plant
producing an average output of 75 tonnes per hour using crushed aggregates
of specified grading premixed with bituminous binder at 5.4 to 5.6% by
weight of total mix and filler, trnsporting the hot mix to site, laid over a
previously prepared surface with a hydrostatic paver finisher with sensor
control to the required grade, level and alignment and rolled with smooth
wheeled, vibratory and tandom rollers to acheieve the desired compaction as
per clause 509 of MORT & H specifications complete in all respects. over Deck
slab

Left side & Right side


Deck Slab 1 x 1 2.500 5.960 0.050 0.75
0.75 m3
16 Providing and fixing seepage pipes of 100mm dia. AC pipes of requied
lengths for abutments and wngs including cost and conveyance of all
materials to work site, cost and labour for 900mm dia. semi-spherical back fill
arangements with 100mm size broken ganite chips at the periphery and
labour charges for fixing, etc.,to drain of the BACKFILL IN THE
ABUTMENTS AND WINGS
Left side & Right side
Abutment 1 x 2 3 6
Sl.
Description No Length in m Breadth in m Depth in m Quantity
No
wings 1 x 2 2 4
10 Nos

17 Filling behind Abutments and wings with clean gritty gravel including cost
and conveyance of gravel to worksite, laying, handling charges and filling in
layers, tamping under optimum moisture content to get the maximum density
including watering, with all leads for water and all other incidental charges
etc,complete. -1 Cum
Left side & Right side
1 x 2 (1.63+2.5)/2 (1.01+2)/2 3.000 18.65

D/d for pavement 1 x -2 1.200 2.000 0.455 -2.18

deduct filter media -10.04


6.43 m3