Professional Documents
Culture Documents
Method Statement: The Royal Commission of Jubail & Yanbu
Method Statement: The Royal Commission of Jubail & Yanbu
Method Statement
Page 1 of 6 Rev 0
Issued by:
Date Description Prepared Checked Approved
TABLE OF CONTENTS
Page 2 of 22 Rev 0
1. TITLE.
2. SCOPE OF WORK
General description.
Plant and equipment.
Materials.
Site planning & preparation
Work methodology.
Organisation, Responsibilities & Supervision.
Work Force.
4. ENVIRONMENTAL ISSUES
Environmental Impact assessment.
E S & H Contractor Requirements
Contractual Requirements.
Emergency Procedures.
5. QUALITY ASSURANCE
Contractual Requirements.
Critical works.
Inspection & Testing.
Follow up & Evaluation.
6. APPENDICES
Page 3 of 22 Rev 0
7. TITLE
The purpose of this method statement is to illustrate how the existing fence and shelters will be removed from site in proper and safe way.
SCOPE OF WORK
General Description
The scope of this method of statement is to cover the demolishing methodology of the following:
Chain link fence (internal & external)
Shelters
Toilet
Tents
Water station
Lighting pole
Road guard rail
Materials
All materials which will be extracted from the demolishing process will be sent to the designated landfill area by RC and here is the summery of some of
it:
Chain link fence and its accessories.
Page 4 of 22 Rev 0
Road guard rail and its accessories.
Excavated materials.
Lightening poles
All underground utilities which will be found while excavation.
Project Details:
Project Name : Reinforced of Community Irrigation System, Phase -IV
Project No: 575 C-35
Project Location : Jubail
Page 5 of 22 Rev 0
Traffic Management Plan
Page 6 of 22 Rev 0
Page 7 of 22 Rev 0
Permits and certificates explain in detailed in Environmental Safety & Health Contractor Requirements
Telephone will be an communication on site
Work Methodology
Demolish of the chain link fence:
Cut the tie wires between the extension bar and the fence wire mesh.
Cut the tie wires between the extension wire and the fence wire mesh.
Cut the tie wires between the fence posts and the fence wire mesh.
Unscrew the bolts of the corner clamps which connect the fence post with the tension bar.
Remove the tension bar and the tension wire.
Remove the fence wire mesh.
Discover the underground utilities such as cable power by using the cable detector.
Start excavation around the fence posts in order to remove it.
Break the concrete foundation by using mechanical or electrical Jack Hammer.
Load the fence materials and send it to the designated area.
Restore the ground level to the original state.
Page 8 of 22 Rev 0
Send all materials to the designated area.
Project Manager/Construction Manager it will be the responsibility of the project manager to ensure that all involved personnel are familiar with the requirements and
implementation of this procedures as applicable to the construction activates. He shall be coordinating with QA/QC at the required stage of the work by issuing an in-house
inspection request to check & inspect the work and to notify Royal Commission by RFI for Witnessing or release of Hold Points.
Quality Control Manager Responsible of the overall discipline of the QA/QC inspection, verification of the Project Specification, Documentation and QC records for final
acceptance.
HSE Manager Responsible for Safety implementation and ensuring all safety requirements has been implemented within the construction areas.
Superintendent/Supervisor ensure compliance by all labours and equipment, operators and other associated craftsmen’s during demolition works to the requirement of
this procedure, project control procedures and test plan, relevant drawings, safety procedures and Royal Commission Standard Section:02220 Guideline Specification for Site
Demolition secure all necessary Demolition/confined space and Permits.
Quality Control Engineer Monitor Daily activates and verify compliance with Royal Commission Specification and IFC drawings, ensure that activities are conducted in
accordance with ITP Demolition works.
Safety Officer ensure all permits are available prior to commencement of any work. Ensure that all works are carried out in a very safe manner, they will identify any
unsafe working condition and immediately rectify the situation, and issue warning for unsafe act of workers, keep close coordination with Royal Commission HSE Engineer for
implementation of Safety Procedures. Report all Incidents to Royal Commission HSE Engineer.
Page 9 of 22 Rev 0
Store Keeper responsibility is to identify the location and maintain preservation of the materials or equipment at the storage area and keeping the record and
control all the materials/equipment that released.
Page 10 of 22 Rev 0
SAFETY AND HEALTH
Risk Assessment
Page 11 of 22 Rev 0
Be careful in entering and exiting in high
4 winds.
Proper use of parking brake.
Maintains vehicle brakes
WORKING Do not lean equipment against truck or place
FROM AND Blind spot, hit by Possibility equipment.
AROUND equipment. personnel injury. Under wheel line of travel.
VEHICLES Do not park near utility appurtenances.
Perform safety circle walk around to prevent
running over utility.
Appurtenances (phone pads, valve sets, and
anchors).
Follow road speed limits
Equipment properly secured
Traffic accident / Fire extinguisher available
nsportation of materials and incident, Falling objects, Operator should possess a valid Saudi
equipment at Fire hazards driving / operator license
Property damage
work site. Assign banks man to guide/ signal heavy
equipment from maneuvering.
Hand tools shall be in good condition
Vehicle compliance for off-road conditions
Excavation By Hitting existing Personnel injury, A Valid work permit on site.
Equipment and underground facilities. Property damage Before starting job, conduct Tool Box Talk.
Hand Tools. Collapse or cave in of and Fatality Use cable detector to identify existing buried
soils. facilities at the beginning of excavation and at
Falling of equipment’s or the bottom of each slit trench.
workers inside. Area Barricaded with Hard and Deep
Noise. excavation signboard shall be posted.
Physical Hazard Excavated pit shall be inspected before the
Soil contamination work begins and at start of each shift.
Ground Disturbance Maintain at least 1M wide clear space around
Underground facilities the edge of excavation to the barriers, to
Insufficient side slope prevent falling of objects on to the persons
digging the pit.
Ladder to be installed for access & egress.
Proper access to the ladder shall be provided
& maintained.
Page 12 of 22 Rev 0
A standby vehicle with required first aid kit
shall be present near worksite at all times.
Strictly need to control any Movement of
equipment’s near excavation.
The Equipment operator must have a valid
third party (TUV) certificate.
Reverse alarm and light shall be operative.
Provision of inspected, color coded and
properly grounded generator, color coded
electrical cables and putting fire extinguisher
in place.
Bobcat shall be inspected by third party (TUV)
and the operator shall have a valid third party
certificate (TUV), reverse alarm and light shall
be operative.
The personnel shall use hearing protection
equipment when needed.
Ensure proper shoring and/or sloping for
depths more than 1.8 meters.
Appropriate PPE shall be with proper hand
tools
Manual Excavation Use only hand shovels.
Excavation Approval shall be attached on the
permit.
Provide fire extinguishers.
Deep excavation sign board shall be posted.
20 Adequate number of sun shelters shall be
provided at site During Hot Season.
Maintain Daily Based good housekeeping
Dust Personnel Spray water to reduce dust & Use of certified
Uneven ground Injury,Propert equipment only.
Poor house keeping damage The equipment (Excavator, jcb, Dump truck)
shall be inspected by TEKFEN and Sadara
Noise. The personnel shall use hearing protection
Ground Disturbance. equipment when needed.
Improper access/ egress. Provide proper Access \Egress
Unnecessary material must remove from the
Page 13 of 22 Rev 0
ground
Trips and fall.
Hand and Eye Injury. Allow only skilled and trained personnel to
Pinch Points. execute the work.
mantling and Re-installation of Failure of lifting Personnel injury, Keep away from line of fire.
Fence /Guard equipment. Property Damage Use appropriate PPE.
rail and Fatality Observe correct usage of power tools.
Equipment may hit or
Inspect tools regularly.
damage existing
structure or property Never stand under the suspended load.
during dismantling.
Whenever practicable, mechanical lifting aids
eg.crane, forklifts ,trucks etc., shall be used to
alleviate the requirement for manual handling
Back due to manual
Supervision will assess weight ,center of
material handling
gravity etc. and determine the number of
Individual capability
persons required to carry out the work safely
Poor lighting conditions
Personnel shall be trained in manual handling
Inadequate space
techniques
Tripping \slipping
Avoid manual load lifting if possible if not the
Improper lifting load
terial handling(manual check and ensure that the load is below the
beyond the capacity of the Personnel Injury,
lifting\lowering recognized permissible limit
individual Property Damage
of material ) Workers fit for the activity shall be engaged
Improper lifting techniques
Area shall be illuminated with adequate
Lack of training instruction
lighting
& supervision
Good housekeeping standards shall be
Slippery
maintained at all times to avoid slip ,trips
surface\overcrowded place
and fall
Improper housekeeping
Train the staff for good posture
Use slip resistance shoe with toe protection
and hand gloves with sufficient sip to avoid
insecure hold
Working at Lack of adequate lighting Property Damage,
Height Reptile movements personnel( injury Ensure 100% tie off during working at
Poor concentration and Fatality) elevated area.
Work Pressure Working areas must barricade with warning
10 Human Error tape.
Page 14 of 22 Rev 0
Reflective vest to be provided for all members
of the crew.
Ambulance with first aid kit and Doctor/Nurse
Poor eye vision at night
to be available at all times during the night.
Sleepiness
Ensure constant supervision.
Fatigue
Emergency Contact Numbers posted the
Lack of training
entire site Locations.
Wear appropriate PPE
Proper training
Lifting and Failure of rigging gear Personnel injury, Conduct daily inspection of equipment and
Rigging and equipment Property Damage rigging gear before each use.
Working at
Heat stress workers
extry Provide rest shelter and cold drinking water
for workers
Probability (P)
Possible Lost time injury or permanent disability 2 - Low 4 - Low 6 - Medium 8 - Medium
Single fatality or permanent disablity of 3 or
Likely 6 - Medium 9 - Medium 12 - High
more person
Very Likely multiple fatalities 4 - Low 8 - Medium 12 - High 16 - High
5 - Medium 10 - High 15 - High 20- High
Page 15 of 22 Rev 0
Safety Footwear
Eye Protection
Specific Hand Gloves
Hearing Protections
Coverall
Fall Protection
Welding hoods
Respiratory Protection
Emergency Procedures
In case of emergency the following procedures should be follow:
Stop work immediately.
All workers should evacuate the working area to the nearest assembly point.
Notify RC representative at the same time of the emergency case.
Call all emergency disciplines like Ambulance or Police or the Civil Defense Unit.
Report the accident to RC representative.
Permit requirements
Lifting
Working @ Height
Excavation
ENVIRONMENTAL ISSUES
ENVIRONMENTAL REGULATIONS
1. Contractor is to ensure that all materials, whether in solid, liquid or gaseous form that are procured for the Project are supplied with
Material Safety Data Sheets (MSDS) by the Vendor and passed onto the Senior Store man.
Page 16 of 22 Rev 0
2. Senior Store man is to ensure the correct storage of all hazardous materials in accordance with the relevant MSDS.
3. Senior Store man is to ensure the correct storage of all hazardous materials in accordance.
4. Risk assessment to be completed before any chemicals are brought to site – handling, storage and use.
5. All employees shall be provided with the necessary PPE as identified in the MSDS and/or risk assessment for the particular work
activity. Contractor is to ensure compatibility between different types of PPE when more than one is to be worn at the same time (i.e.
eye and hearing protection).
6. Respirators and dust masks are to be selected according to the hazard present;
dust, fumes vapors etc. See MSDS for specific requirements. All respirators to be ‘face fit tested’ for each user. Users shall be clean
shaven to ensure suitable skin/mask seal is achieved.
Pollution Control
7. All containers of oil, fuel or chemicals shall be labeled and identified with contents and capacity.
8. All materials and chemicals will be stored in a manner that conforms to their MSDS requirements.
Page 17 of 22 Rev 0
19. Select appropriate PPE. If the spilled substance cannot be identified, treat it as highly toxic and utilize the most appropriate form of
protective clothing
20. Contain the spill:
Use booms or pool to contain spill and stop it spreading; and
Barricade incident with cones / new jersey barriers to control traffic movement until incident is cleared.
21. Dispose of contaminated materials (be it soil, water or spill kit materials) initially an appropriate container (open-top steel drum), and then
off-site using approved waste contractor.
QUALITY ASSURANCE
Contractual Requirements
Quality Assurance shall be provided to ensure that materials, Construction and Workmanship are in compliance with the plans and specification
and applicable requirements of the standard and codes mentioned in Method Statement. For Guidelines Specification for Site Demolition Section
02220.
Critical Works
Protect and maintain all existing Utilities to remain from damage in the proximity of the facilities to be demolished
Locate and mark existing Utilities to remain using high visible tags or flags, with identification of utility type: protect from damage due to
subsequent construction, using substantial barricades if necessary.
APPENDICES
Page 18 of 22 Rev 0
Method Statement
Those names listed below confirm receipt of the method statement and have had the contents explained to them/understand it and are aware of the site
ES&H requirements.
Name Employer Date Signature
Note to contractor supervisor – Any significant change from this method statement requires it to be revised and resubmitted before work can
commence.
Page 19 of 22 Rev 0
Page 20 of 22 Rev 0