PBHU Technical Sub-Unit

(Updated on 16.12.2020)

STATUS OF TECHNICAL ISSUES - WPC04 : Pantu Junction to Btg. Skrang


As at 16.12.2020
Next Action Technical
No. Issue Action taken Latest Status
by Status
Remarks

Technical Sub-Unit PBHU


opinions as below:
(1) WPC to revised their
submitted Method Of
Statement (MOS) to
indicate 9m height of CFRP
wrapping as per consultant
comments

(2) WPC to clearly state in


Muhandis to write to JKRS on the the MOS on how to carry
Proposed Rectification Works
Muhandis responded ICE comments recommendation. SRE WPC04 out the work such as:-
to Column Pier 1 & 2 At Batang (2a) any overlapping of
to Opus on 7th September. approved method of statement for RET of
1 Skrang Bridge (using Carbon Closed CFRP throughout 9m height
ICE Technical Comment Closed 0n structural strenghtening works for Muhandis
Fibre Reinforcement Polymer of CFRP wrapping,
23th Sept 2020 column at pier 1 and pier 2 on
(CFRP) wrapping system) (2b) indicate thickness of
27.11.2020 (TSRS). each layer of the CFRP
wrapping (submitted MOS
stated 3 layer of CFRP
wrapping) and
(2c) specify which company
will carry out this technical
work on site
(3) WPC to revised the
proposed CFRP drawing
based on Item (1) and Item
(2) above and ensure all the
cross section or detail is
clearly shown.

Muhandis responded to ICE's second


comments via email on 19th Oct Review meeting held on
2020. Pending ICE and Muhandis final 9.12.2020. Muhandis to
Embankment Failure at CH
JKRS PBHU forwarded ICE comments recommendation submit remedial
2 15+200 to CH 15+400 (Bukit Muhandis Open
to Muhandis. ICE replied on 2.11.2020, All item treatment only for
Bangunan)
closed. Muhandis to submit official failure area at CH 15+200
letter with detail drawing to JKRS to CH 15+400 officially
PBHU for review.

Received from Muhandis on


JKRS PBHU requested Muhandis to 15/10/2020. ICE's comments
Slope Failure at CH 16+050 Muhandis/
3 submit Report on Causes of Failure forwarded to Muhandis on 19th Oct Open
(RHS) PBHU
and Proposed Remedial Works. 2020 by email. Muhandis to response
to ICE

Page 1 of 3
PBHU Technical Sub-Unit
(Updated on 16.12.2020)

STATUS OF TECHNICAL ISSUES - WPC04 : Pantu Junction to Btg. Skrang


As at 16.12.2020
Next Action Technical
No. Issue Action taken Latest Status
by Status
Remarks
RET to issue a letter to WPC to rectify
the work.

ZM to converse with Muhandis to Additional Land


JKRS PBHU forwarded latest ICE submit final design acquisition to be based
Gunite Slope Failure at report/calculation/ drawing properly
4 comments to Muhandis on Muhandis Open on JKR's submission to
CH25+200 to CH25+300 (LHS) endorsed. May call in KKR, JKR
2/10/2020. L&S Department on
Malaysia to review the final design 29.7.2020.
Skype meeting on 5.11.2020.
Muhandis to submit alternative
design by 19.11.2020

Received from Muhandis on


JKRS PBHU requested Muhandis to 15/10/2020. ICE's comments
Slope Failure at CH 53+050 Muhandis/
5 submit Report on Causes of Failure forwarded to Muhandis on 19th Oct Open
(RHS) PBHU
and Proposed Remedial Works. 2020 by email. Muhandis to response
to ICE

Received from Muhandis on


JKRS PBHU requested Muhandis to 15/10/2020. ICE's comments
Slope Failure at CH64+400 Muhandis/
6 submit Report on Causes of Failure forwarded to Muhandis on 19th Oct Open
(RHS) PBHU
and Proposed Remedial Works. 2020 by email. Muhandis to response
to ICE

JKRS PBHU requested Muhandis to


Slope Failure at CH 68+539A Received from Muhandis on Muhandis/
7 submit Report on Causes of Failure Open
(RHS) 15/10/2020. Pending ICE comments. PBHU
and Proposed Remedial Works.

Page 2 of 3
PBHU Technical Sub-Unit
(Updated on 16.12.2020)

STATUS OF TECHNICAL ISSUES - WPC04 : Pantu Junction to Btg. Skrang


As at 16.12.2020
Next Action Technical
No. Issue Action taken Latest Status
by Status
Remarks
1.Discussion on 28.10.20. Agenda of Meeting with MUHANDIS, Mr Adrian
the meeting : a)Briefing on the matter (PSK), KAZ, URW Sub-unit and Tech
by MUHANDIS (on ori design , status Sub-unit on 1.12.20 at 9 am :
of construction progress at the a)To accomodate the 10m clearance,
affected site, any proposed revised the FRL profile has been lowered as
design if any well as the road standard. (design
Meeting on 30th Oct 2020 at 9 a m. speed 100km/h to 90km/h).
PMSB to provide b) KAZ to meet SEB and convey the
a) 12.5m cross section at CH73+842 design change.(all satisfy 10 m except
to CH73+900 (current situation). 2 location at CH 73+864.55 with
b) Concept of piled embankment clearance of 9.9746m and CH
submit to JKRS cc to ICE 73+883.87 with clearance of
c) Picture of current site conditions 9.7752m).
Meeting with Perunding
d) MOM c) JKRS PBHU URW sub-unit will
KAZ, PKSB, PMSB, PS
Further discussion was carried out closely monitor KAZ on their follow
Konsultant, PBHU JKR HQ
Insufficient Overhead Pylon with PS Consultant on 3th Nov 2020 up action with SEB
MUHANDIS/ on 1.12.2020 to convey
Clearance from Surcharge to discuss on how to lower down the d)PMSB to submit a current level of
8 Tech Sub- Open Revised Plan & Profiles
Level and Final Clearance at level to satisfy SEB requirement earthwork at centre line for CH
unit drawings. Perunding KAZ
CH73800 to CH73900 73+707 to CH 74+200 by Friday,
wrote to SEB for
4.12.2020.
consideration on
e)JKRSPBHU to call a meeting on civil
3.12.2020.
with PMSB.

2.Mr Yet whatsapp on 12.11.20


requesting MUHANDIS to submit P/P
drawings from CH73+500 to
CH74+200 as per discussion and
decision on 3.11.20 together with
cross section indication height of
cables above FRL.
MUHANDIS / PS COnsultant
submitted revised Plan Profiles
drawings on 19.11.2020.

Page 3 of 3