2013 SSB Campaign Lesson Learnt Register

Operating Project Discipline ORP


ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
1 Lesson UIA - SMEP 2013 Transportation HSE Execute NA NA LTS 3000 Installation campaign has been completed with ‘0’ TRCF • Maintain good record for future campaign
Learnt Asia & Structure and ‘0’LTI.
Installation
2 Lesson UIA - SMEP 2013 Transportation HSE Execute NA NA UCUX Submission exceed the target • Maintain good record for future campaign
Learnt Asia & Structure (Target 1:400, Achievement 1: 352)
Installation
3 Lesson UIA - SMEP 2013 Transportation HSE Execute L(3) 3 Issue: • Any new requirement need to be notify officially
Learnt Asia & Structure SSB Marine impose new requirement on STCW 95 for Marine to CONTRACTOR
Installation crew (i.e. Problem in applying safety passport).

Consequence:
This new requirement does not captured in the base contract.

Why:
No official notification were given to CONTRACTOR

4 Lesson UIA - SMEP 2013 Transportation HSE Execute L(2) 1 Issue: • To change the chef with local taste preference.
Learnt Asia & Structure Food quality is not up to expectation. Suggestions to change chef To include campboss in Daily Supervisor Meeting
Installation was not materialized. onboard.

Consequence:
Crew was not happy with the standard of food

Why:
Issue was not brought up to management. Line of reporting loss
somewhere.
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
5 Lesson UIA - SMEP 2013 Transportation HSE Execute L(1) 1 Issue: • Safety stand down and reminder to crew to
Learnt Asia & Structure Sliding door shower room shattered. report any faulty equipment immediately to
Installation marine focal person.
Consequence:
One broken piece (from upper-portion of the sliding door) fell on • To perform regular checks on all existing glass
crew personnel's left hand dorsum and resulted minor cut injury. doors sliding mechanism and repair as required on
monthly basis.
Why:
Excessive side force on jammed glass door led the door in stress •To affix warning signage on all sliding glass doors.
causing the glass to break.
• Plan to replace shower sliding door glass with
shower curtain or to install safety film (tinted) on
the glass.

6 Lesson UIA - SMEP 2013 Transportation HSE Execute L(1) 1 Issue: • Contractor will emphasize on Environmental
Learnt Asia & Structure Housekeeping of major items (slings, welding cables, etc) are issues in future campaign and to continue educate
Installation excellent, but littering (candy wrapper, cigarette buts, plastic the crew about housekeeping issue including
biscuit rap, etc) seems to be rampant among crew. littering element

7 Lesson UIA - SMEP 2013 Transportation HSE Execute L(1) 1 Issue: Contractor need to perform more regular drills
Learnt Asia & Structure During the ship abandonment drill, the time taken to do a full exercise to get people to familiarize with mustering
Installation headcount were more than 15 minutes, which is not acceptable. on the barge.

Consequences:
May lead to fatality in actual condition.

Why:
Relocation of life raft station for some personnel, especially
those who stay in 4 man cabin. Crews who involved with the
changes were not familiar with new emergency evacuation plan
( life raft station) .
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
8 Lesson UIA - SMEP 2013 Transportation PMT & Planning Execute L(6) 3 Issue: • Project Baseline Schedule to be approved prior to
Learnt Asia & Structure No approval on the Project Baseline Schedule. the installation campaign. At least the duration &
Installation activities must be agreed. Due to the dynamic
Consequence: nature of CAT1 project, any changes after that can
Installation campaign commenced before the Project Baseline be recorded / captured in the next subsequent
Schedule being approved and still in Revision 05R even after the revision, XXC.
completion of offshore campaign.
• Approval of project baseline schedule will be
Why: implemented in future projects
Multiple changes on the installation sequence and no agreement
reached between both parties on some of the
handover/MCD/sailaway dates.
9 Lesson UIA - SMEP 2013 Transportation Manpower Execute L(4) 2 Issue: • sub contractor must be reminded on the
Learnt Asia & Structure Management 1) Menck's technician - UKOOA medical report was not accepted requirement of project / client to avoid crew stand-
Installation by client (SSB) and need to redo in Malaysia by while waiting for the processing of medical
2) Menck - changing of technician for same project/client report & stamping passport
3) 3rd party crew without medical/Boseit
stamping on the Shell passport • Sub contrator is to ensure their crew SHPP are
complied prior joining.
Consequence:
1) Crew need to stand-by onshore and wait for medical report
prior joining barge
2) New technician needs to redo the medical & stamping Boseit
in Malaysia
3)Crew stand-by onshore to get the SHPP stamping prior joining
barge

Why:
Last minute notification from TLO.
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
10 Lesson UIA - SMEP 2013 Transportation QA Execute L(2) 1 Issue: • All documents must be reviewed upon
Learnt Asia & Structure (Documentation) Prolong review cycle i.e more than 2 weeks of installation submission regardless of the installation date to
Installation analyses and installation procedures avoid last minute changes.

Consequence: • COMPANY shall endouvour to revert to


1) Standby prior installation due to unapproved installation CONTRACTOR with any such amendments or
procedure. comments no later than two weeks after receipt of
2) Insufficient time for CONTRACTOR to incorporate comments. documents.

Why:
Multiple changes on the installation sequence and last minute
ammendments made on the procedures.

11 Lesson UIA - SMEP 2013 Transportation QA Execute L(2) 1 Issue: • Both parties to discuss on the document's
Learnt Asia & Structure (Documentation) Unclear status of Eyeball ROV procedures after Rev 03R. requirement to be able to close the issue prior
Installation mobilization.
Consequence:
Eyeball ROV Procedures were sent to offshore unapproved.

Why:
COMPANY mentioned that the comments were not fully
incoporated in the procedures. Lack of communications between
Diving representative from both TLO and SSB during the review
cycle.
12 Lesson UIA - SMEP 2013 Transportation Marine Execute L(6) 2 Issue: • Towing tug from outside Batam shall arrive in
Learnt Asia & Structure Delay of towing tug sailaway from Batam after onhire of Batam by afternoon as agent requires approx. 6
Installation transportation barge. hours to obtain the port clearance.

Consequence: • To onhire vessel early (am) and ensure delivery


Delay of sailaway from Batam to SKOB for grillage works. of MGO on schedule.

Why:
1) Late arrival of towing tug at Batam. Hence, delay in getting
port clearance.
2) Delay bunkering of towing tug in Singapore.
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
13 Lesson UIA - SMEP 2013 Transportation Marine Execute L(6) 2 Issue: • Owner to ensure readiness of barge prior onhire
Learnt Asia & Structure Delay of sailaway of Teras 335 (LADR-A Jacket) from Batam. date
Installation
Consequence: • CONTRACTOR to prepare a checklist on readiness
1) Delay of sailaway from THHE. of the barge prior onhire date
2) Delay in preparation of grillage works.

Why:
Barge Teras 335 was at beaching position, waiting for next high
tide to depart
14 Lesson UIA - SMEP 2013 Transportation Marine Execute M(9) 3 Issue: • To revisit the service agreement between OIC
Learnt Asia & Structure Last minute withdrawal by vessel owner for towing tug Salvaree and Subcontractors for future projects.
Installation to tow POE Giant 22 (F14DR-A Piles & Misc.) from MMHE yard,
Pasir Gudang to field.

Consequence:
Potential delay of sailaway transportation set from loadout yard
to field. CONTRACTOR had to use another towing tug, Magellan 1
who was on standby for another barge at THHE Yard, Port
Kelang.

Why:
1) The vessel received commitment from another charterer
2) Change of offshore installation schedule results to the delay of
vessel onhire date
3) No official confirmation from COMPANY on the acceptance of
some relaxations of technical criteria
4) Short charter period, but too many inspections involved and
owner required more time to close all punchlist
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
15 Lesson UIA - SMEP 2013 Transportation Marine Execute M(5) 5 Issue: • Every transportation barge must be thoroughly
Learnt Asia & Structure Internal/ external tank leaking of transportation barge POE Giant inspected external and internally. It should be
Installation 3 (D12DR-A Jacket) during loadout at yard. reinspected if certain areas are not covered in
Found tank 2P was filled up with water (supposed to be empty). previous inspection.

Consequence: • Not to use the same barge if problematic from


1) Delay of loadout activity and sailaway to field. the previous project/ campaign unless it has been
2) Delay of of offshore installation activity and exposed to MWB completely rectified and verified by MWS
LTS3000 standby
3) POE Giant 3 was tilting towards the port side. • To verify and review any gaps exists in the
inspection by MWS.
Why:
1) Barge was rejected from previous project due to breached hull • To make internal ballast tanks inspection as a
and not repaired completely. Barge was accepted without compulsary item.
knowing the actual condition of the barge.
2) No internal tank inspection carried out by MWS surveyor prior • To formally communicate to OIC that nomination
to mobilization. The internal tank was flooded during inspection of transportation barge shall be timely and in strict
thus making inspection unsafe to proceed. compliance to contract requirements.
1" Hole was found on the hull of the barge (about 1m from the
tank floor and 8 m from the bow).

16 Lesson UIA - SMEP 2013 Transportation Marine Execute L(3) 1 Issue: • The transportation of flooding equipment via
Learnt Asia & Structure Delay of Britoil 60 to arrive at MMHE due to flooding equipment Britoil 60 was decided on the final hour, the mode
Installation clearances from Batam. of transportation shall be decided in the manner in
which it does not disrupt any departure schedule.
Consequence:
Delay of arrival at MMHE resulted delay in sailaway for launch
barge, Holmen Antlantic from MMHE to field.

Why:
1) Miscommunication between operation, logistics and marine
department.
2) Late notification and decision made on mode of transportation
for flooding equipment.
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
17 Lesson UIA - SMEP F23R-A M3 & D12DR- Marine Execute L(1) 1 Issue: • Charter hire of marine spreads to be planned in
Learnt Asia A Installation No supply boat for 2 weeks due last minute contract withdrawal advance.
from vessel owner after completion of firm charter duration.

Consequence:
Potential shortage of project material, fuel and food supply.

Why:
No immediate replacement due to unavailability in market Vs
client requirements.

18 Lesson UIA - SMEP F23R-A & D12DR-A Marine Execute L(3) 1 Issue: • Owner to be more proactive on any breakdown
Learnt Asia Installation Delay on anchor operations at F23R-A & D12DR-A and ensure sufficient spares are available onboard.

Consequence:
Longer operation and fatigue for AHT1 to run anchor alone.

Why:
1) AHT2 (David Tide II) brokedown and late client approval
(OVID) due to slow response from owner of replacement AHT
(Miclyn Venture) .
2) Custom clearance of spare parts couldnt be done on weekend
(to be confirmed by Marine)

19 Lesson UIA - SMEP F23R-A M3 Operation & Execute L(1) 1 Issue: • Any new requirements from SSB regarding lifting
Learnt Asia Installation Work basket does not have BS EN 14502 standard. equipments need to notify CONTRACTOR at least 4
(Warehouse) months prior to mobilisation since manufacturing
Consequence: will take 12 weeks.
Client may issue a stop work instruction.

Why:
1) New requirement from SSB TA.
2) Unavailability of work basket which comply CLIENT
requirement in the market in this region
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
20 Lesson UIA - SMEP F14DR-A, LADR-A, Operation & Execute L(1) 1 Issue: • Early planning and preparation must be done for
Learnt Asia D12DR-A Structure Installation Class approval of diving system onboard LTS3000. works need weeks/months to be completed.
Installation
Consequence: • To have concurrence and final decision between
Mob was almost delayed. CONTRACTOR & LTSSPL at early stage to avoid
wastage of time.
Why:
1) A lot of last minute discussion and no final decision on placing
of diving platform
2) New requirement from industrial (to have class system on Air
Diving System.)
21 Lesson UIA- SMEP BEDP-A Cellar Deck Operation & L(1) 1 Issue: • COMPANY, CONTRACTOR, and Fabricator to
Learnt Asia Extension Installation Installation Existence of protruding slug catcher service platform beyond the ensure no structure installed beyond the pre-
pre-installed bumper at BEDP-A deck. installed bumper prior sailaway.
(Note :The slug cather service platform protrusion is shown in
the AFC and yard as-built drawings.) • Pre-lift inspection must be carry out in more
details to detect any potential clashing missed out
Consequence: during inspection at fabrication yard
Damaged to the protruding slug catcher service platform during
installation.

Why:
Clash with the existing structure.
22 Lesson UIA- SMEP BEDP-A Cellar Deck Operation & L(3) 1 Issue: • COMPANY to present all structures model as per
Learnt Asia Extension Installation Installation Protruding SDV deck underneath the BEDP-A cellar deck was not transportation/ installation mode during PDMS
properly presented in PDMS model review.

Consequence: • COMPANY to include a cellar deck perspective


1) The barge layout has to be revised at late stage and new view in the AFC (if applicable).
transportation analysis need to be performed.
2) Risk of structure/boat damage during alongside to LTS3000. • To consult with Marine captain to check on
marine constraint in tie-down planning.
Why:
The protruding SDV deck clash with main piles on the same • CONTRACTOR to refer AFC drawings and cross-
transportation barge. check with PDMS model
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
23 Lesson UIA- SMEP BEDP-A Cellar Deck Operation & L(3) 1 Issue: • COMPANY to present all structures model
Learnt Asia Extension Installation Installation Pre-installed guides at BEDP-A Deck potential clash with landing including installation guides / bumpers during
platform brace discovered at late stage. PDMS review.

Consequence: • CONTRACTOR should highlight the potential clash


Revisit the guides design & clash check at late stage when preparing the drawings.
(1 day before load out).
• CONTRACTOR to have frequent site visit for
Why: verifications.
Potential clash with landing platform braces.
24 Lesson UIA - SMEP LADR-A Jacket Operation & L(4) 2 Issue: • The routing design shall consider the tiedown
Learnt Asia Installation Installation 1) Location and position of jacket flooding/venting/grout position (i.e 6 oclock orientation for top row jacket
packet/pile gripper tube routing very close to the tiedown leg and 12 oclock orientation for bottom row
braces. jacket leg).

Consequence:
1) Minimal clearance between the tubing with tie down
attachment. This requires extreme care when cutting the
tiedown braces to avoid damage to the tubings which could
jeopardise the grout packer and pile gripper activation.

Why:
1) The tube routing design does not consider tiedown location.
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
25 Lesson UIA - SMEP LADR-A Jacket Operation & L(3) 1 Issue: • Use mechanical clamp for long pile upending
Learnt Asia Installation Installation Grout packer punctured and failed to be fully inflated (3 out of 4
pile sleeves). • Grind flush the upending trunnion after flame cut
if upending the pile using trunnions.
Consequence:
Delay (additional 1.5 days) in overall grouting operation due to
the need to set grout plug at pile sleeve A2, B1 and B2 as means
of grout seal .

Why:
Based on COMPANY's investigation and complimented by
Pronal's investigation findings, the grout packer failure was
neither due to product defect nor damage during installation at
yard. This is QC'ed with factory acceptance test and yard function
test. The 6mm pile upending trunnion residual protrusion and
sharp edges on the surface of the trunnion after flame cut could
have punctured the grout packer.

26 Lesson UIA - SMEP LADR-A Jacket Operation & L(3) 1 Issue: • Survey contractor to clearly state/advice on their
Learnt Asia Installation Installation Survey equipment restriction during transit fix. equipment capability/constraint in order for
CONTRACTOR to plan for the transit fix activity.
Consequence:
MWB need to be within 10km from the proposed transit fix
location during the work.

Why:
Limited transmitter signal coverage between MWB and AHT.

27 Lesson UIA - SMEP LADR-A Topside Operation & Execute L(2) 1 Issue: • Fabricator shall fabricate the stopper plate with
Learnt Asia Installation UT has not been done on weldment joints of the stopper plate of splice end profiled to match the type of weld
the LADR-A boatlanding clamp required as shown in AFC drawing.

Consequence: • The stopper ring plate in 2 pcs shall be trial-fitted


Rectification work need to be done. at yard to ensure alignment and ensure it matches
each other.
Why:
The stopper plate joint connection provided was not as per
drawing.
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
28 Lesson UIA - SMEP LADR-A Topside Operation & Execute L(4) 2 Issue: • OIC to advise those facilties that are susceptible
Learnt Asia Installation Insufficient protection on topside main deck facilities. to damage during lifting (including slings rig up and
rig down), and propose means of protection.
Consequence:
A number of facilities were damaged when lowering down the • Better weight estimation with realistic
heavy lift slings due to swell experienced that resulted the crane allowances. Use auxiliary block if possible that
hook block to swing uncontrollably. works faster and gives better control to avoid
excessive movement.
Why:
1) Discrepancy of LADR-A topside actual recorded lift weight
(630MT) and estimated lift weight (750MT) . Too much of
allowances were applied on the weight that gives an over-
estimated weight resulting to the used of Main Hook.
2) Not sufficient protection on the main deck for the equipments.
3) Close proximity between the heavy lift slings and
equipment/pipings on the topside main deck. Potential clashes
were identified during rig up of the slings. However, swinging of
the lifting slings after topside set down (sling in slacked
condition) was overlooked.

29 Lesson UIA - SMEP F14DR-A Jacket Operation & Execute L(2) 1 Issue: • The vendor that supply the remote flooding
Learnt Asia Installation Fabricator that supply the Remote Flooding System on the jacket sytem on the jacket shall be responsible and
refuse to participate for offshore execution work. perform the function test as per offshore
requirement and execute the remote flooding
Consequence: operation at offshore
1) Last minute appointment of remote flooding vendor due to no
vendor willing to participate due to lialibility issue • Onshore function test on the flooding system
2) Vendor not familiar with the system which is not supply, install shall be conducted with the same equipments and
and pre-commissioning by them personnel that will execute the job at offshore
3) Onshore testing of the system was not conducted at yard
using the offshore equipment
4) Jacket upending operation was delayed due to wrong
compartment flooded. Subsequently, it was found that the
connection on the HPU was wrongly connected by vendor.

Why:
The system was supplied, installed and pre-commisioned by
different Vendors at Yard, hence there is no integration on the
system by a Sole Vendor.
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
30 Lesson UIA - SMEP F14DR-A Jacket Operation & Execute L(4) 2 Issue: •The vendor must ensure the grout strength
Learnt Asia Installation Grout strength not meet the 24 hours design requirement and achieved during onshore trial mix shall achieved
ISO consistency calculation the design requirement at offshore with certain
amount of contingencies to take environmental
Consequence: effect
Delay in overall offshore installation progress
•Vendor to provide more data on previous crush
Why: test result using fresh water
1) Vendor could not achieved the grout strength requirement
during offshore trial mix . • To perform grout mixing and testing prior to
2) Insufficient data to estimate the grout strength projection at grout vessel mobilization to offshore (i.e at port)
28 days
•CONTRACTOR to request for lab and offshore test
results during bidding stage .

31 Lesson UIA - SMEP F14DR-A Platform Operation & Execute L(4) 1 Issue: • To ensure a more efficient communication
Learnt Asia Installation Installation No immediate repair done when damaged umbilical was found. between Barge Foreman and Crane Operator
Repair was only done when second umbilical damage.
• Hammer umbilical condition should be
Consequence: monitored closely especially during piling and sling
Delay in completing jacket piling change-out

Why: • Scheduled maintenance on the OIC's hammer,


Hammer umbilical did not carefully and closely monitored during provide appropriate spare parts and conduct
underwater piling and hammer sling change-out function test

32 Lesson UIA - SMEP F14DR-A Jacket Operation & L(3) 1 Issue: • All markings shall be checked and measured by
Learnt Asia Installation Installation The choker slings lifting point was wrongly marked by Fabricator, both Fabricator and CONTRACTOR based on
not as per CONTRACTOR drawing CONTRACTOR's drawing prior sailaway to field.

Consequence:
Delay in overall offshore installation progress
Pre-rig choker slings need to be relocated at offshore

Why:
Lack of monitoring at yard by Fabricator and CONTRACTOR
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
33 Lesson UIA - SMEP F14DR-A Jacket & Operation & Execute L(3) 1 Issue: • COMPANY, CONTRACTOR, and Fabricator need
Learnt Asia Topside Installation Installation 1) Fabricator did not provide shackles for boatlanding safety to check every shiploose items required for
chain in the shiploose items offshore installation are as per AFC Drawing and
2) Bolt and nut for jacket seadeck handrails were not provided by captured in the master shiploose items.
Fabricator
3) Stairway ladder landing to be fabricated and installed

Consequence:
1) The safety chain installation for boatlanding could not be
performed during jacket installation
2) The handrails might be loose. Already been issued in the
F14DR-A Topside Punchlist.
3) Modification works and additional item for stairway ladder
landing had to be provided by CONTRACTOR.

Why:
The shackles,bolt,nut and shiploose items for stairway ladder
landing were not included in the shiploose list and were not
properly checked at Yard prior loadout.

34 Lesson UIA - SMEP F14DR-A Jacket Operation & Execute L(3) 1 Issue: • Fabricator need to strictly follow the approved
Learnt Asia Installation Installation Buoyancy tank temporary support saddle was wrongly welded to CONTRACTOR installation aids drawing provided in
the boatlanding by Fabricator not as per CONTRACTOR drawing. Loadout Coordination Manual
The issue was identified by CONTRACTOR representative during
final walkabout prior sailaway

Consequence:
Extra work at yard prior sailaway by Fabricator

Why:
Lack of monitoring at yard by Fabricator
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
35 Lesson UIA - SMEP F14DR-A Jacket Operation & Execute L(2) 1 Issue: • COMPANY should take into consideration for
Learnt Asia Installation Installation F14 Jacket final level not achieved within tolerance. jacket levelling load using the upending padeye
during design stage including the anticipated on-
Consequence: bottom weight. Padeye capacity should be the
1) Longer duration needed to level the jacket . same as shackle capacity.

Why:
1) Jacket level could not be achieved due to limitation on the
padeye capacity which limiting the levelling load.
2) The upending padeye was not designed for jacket levelling.

36 Lesson UIA - SMEP F14DR-A Jacket Operation & Execute L(2) 1 Issue: • COMPANY should take into consideration on
Learnt Asia Installation Installation Boatlanding clamp stubs clash with boatlanding horizontal brace installation point of view during design stage
during installation.
• PDMS review shall be performed during early
Consequence: stage with the consideration of installation point of
1) The boatlanding clamp stubs are required to be shiploosed view to identify any clashes.
and install on the boatlanding post.
2) Difficulty to adjust the clamp stubs on the king post to suit •CONTRACTOR to highlight earlier on any concern
actual MSL observation. related to installation during load out coordination
3) The flange connection holes need to be modified to oblong meeting
type

Why:
1) The clashing was not identified during design stage.
2) The boatlanding design was not considered on the offshore
installation operation.
37 Lesson UIA - SMEP F14DR-A Topside Operation & Execute L(3) 1 Issue: • Fabricator to ensure the handrails and grating are
Learnt Asia Installation Dimensions of gratings and handrails provided are not as per IFC provided as per IFC drawings.
drawings.

Consequence:
Modification works needs to be done.

Why:
Unproper check by the Fabricator
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
38 Lesson UIA - SMEP F14DR-A Topside Operation & Execute L(3) 1 Issue: • Weighing report to include CONTRACTOR
Learnt Asia Installation Inaccurate first issued weighing report by provided to estimated heavy lift rigging weight for accurate
CONTRACTOR COG.

Consequence:
Delay in finalizing heavy lift rigging awaiting confirmed weighing
report and COG from COMPANY.

Why:
Weighing report provided to CONTRACTOR was not
incorporating CONTRACTOR's rigging weight and COG.

39 Lesson UIA - SMEP F14DR-A Topside Operation & Execute L(3) 1 Issue: • COMPANY to provide accurate COG
Learnt Asia Installation During loadout, topside was found tilted not as per expected
based on confirmed COG. Based on CONTRACTOR checking, the
confirmed COG was found not accurate.

Consequence:
Topside tilting during lifting and installation was not as per
approved rigging calculation and potential damages to the
structure

Why:
COG confirmed by COMPANY is not accurate

40 Lesson UIA - SMEP F14DR-A Topside Operation & Execute L(3) 1 Issue: • COMPANY to clearly specified scope demarcation
Learnt Asia Installation Scope of supply and installation of support can was not specified for the supply and installation of support can in
clearly contract.

Consequence:
Additional arrangement need to be done at the anchorage for
final dimensional survey

Why:
Miscommunication between Fabricator and CONTRACTOR prior
to cast-off from SKOB upon completion of grillage and support
can installation
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
41 Lesson UIA - SMEP F23R-A Module 3 Operation & Execute NA NA Good Practice: • CONTRACTOR and COMPANY to continue good
Learnt Asia Installation Installation Good coordination between COMPANY and CONTRACTOR for coordination.
installation bumper and guide and holdback/orientation tugger
padeye arrangement. Identify critical items and follow up with close
discussion.
Consequence:
Smooth and safe offshore installation to install Module 3 at tight
space in between Module 2 and flare tower.

Why:
The bumper and guide and holdback/orientation tugger padeye
arrangement are crucial during Module 3 offshore installation.

42 Lesson UIA - SMEP F23R-A Module 3 Operation & Execute L(3) 1 Issue: • CONTRACTOR to have proper checking prior to
Learnt Asia Installation Installation Grillage welding quality issue during handover to COMPANY cast off from SKOB and handover to COMPANY

Consequence:
Additional work by fabricator causing delay in sailaway

Why:
Poor quality of grillage welding

43 Lesson UIA - SMEP D35PG-A Cellar Deck Operation & Execute L(3) 1 Issue: • COMPANY to provide accurate COG.
Learnt Asia Extension Installation Inaccurate COG provided by COMPANY which cause excessive
tilting during lifting and installation. • To record the additional load (shiploose items)
imposed on structure & to acquire a revised COG
Consequence: with shiploose item.
Difficulty during lift-off and installation and potential damage on
the equipment

Why:
1) The final loadout discipline weight is less than considered
discipline weight in weighing report for the installation,hence
altering the final CoG.
2) The presence of shiploose items at one end of the deck
extension.
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
44 Lesson UIA - SMEP D35PG-A Cellar Deck Operation & Execute L(3) 1 Issue: • All fixed structures must be fully welded on
Learnt Asia Extension Installation During lifting of D35 deck extension from material barge to weldment before hand over to installation team.
D35PG-A Cellar deck, one piece of stabbing guide dislodged and
fell on to material barge • The installation guide is to be welded as per
agreed drawing. QC inspector must check on the
Consequence: structure and to carry out NDT.
Potential personnel injury and property damage.
Difficulty to setdown Cellar Deck Extension
• COMPANY, OIC yard representative and
Why: Fabricator to inspect the guides prior to barge
1)The guide was only tack welded along 4 edges due to overlap sailaway.
of footprints between earmarked area of the guide and the
457mm diameter transportation support stool. • To maintain effective communication between
fabrication yard, load out team and offshore
2) Lack of continuity in transferring the decision taken at the Yard installation team on any pending issues or
and message transferred offshore. punchlist during fabrication.

• Perform overlap checks on proposed


transportation support stools' locations prior to
finalization.
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
45 Lesson UIA - SMEP D12DR-A Jacket Operation & Execute L(3) 1 Issue:
Learnt Asia Installation P4 Pile for leg A1, A2 & B2 has met refusal criteria according to • Based on offshore observations, it is
ISO 19902:2007 and manufacture (Menck) refusal criteria. recommended that dry-runs are carried out for pile
operations with emphasis on the sequence of
Consequence: operations and refusal criteria. This stems from the
1) Potential damage to the hammer and piles. aborted driving of P4 section of pile A1.
2) Target penetration cannot be achieved.
3) Delay in offshore installation progress.
• Ensure alignment between all relevant parties
Why: (COMPANY, OIC and hammer operators) on the
COMPANY remains in the midst of ascertaining the most likely detailed flow of operations i.e. expected
reason for the higher than expected soil resistance to driving blowcounts, refusal criteria and etc prior to the
(SRD). e. The outcome, upon completion, will be disseminated start of each piling sequence, particularly the
and captured here. sections of greatest concern.

Note: soil data at location was established based on known


empirical equations/relationships.

46 Lesson UIA - SMEP D12DR-A Jacket Operation & Execute L(3) 1 Issue: • Fabricator to provide proper list of shiploose
Learnt Asia Installation Shiploose items i.e. handrails and grating provided by Fabricator materials with drawings.
with no proper as-built drawing
•To consider including piece-marks of handrails
Consequence: and gratings in the Yard As-Built drawings
Difficulty and delay during installation

Why:
• The handrails and gratings piece marks are not indicated as
part of the final Yard As-Built drawings. Instead they are
indicated in the Issued for Construction (IFC) drawings.
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
47 Lesson UIA - SMEP D12DR-A Jacket Operation & Execute L(3) 1 Issue: • Fabricator,COMPANY & OIC to closely monitor
Learnt Asia Installation Transition piece not fabricated as per AFC drawing where Hi-Lo during trial fit at yard and verify the angle as per
at the joint between transition pieces and piles attributed to the AFC drawing.
batter angle being taken in its entirety by the transition pieces
instead of an equal split between them and the piles. • Emphasis on critical interface item at the yard
and ensure the actual boundary conditions are
Consequence: present during the trial fit.
Trial fit on the transition piece have been perform onboard to
verify the item was design as per AFC drawing and some •DC checks workpoint spacings to ensure proper
modification have been done to ensure the transition pieces are mating of jacket and topside.
fit during installation.
• Continue the good practice to verify product
Why: received as a meanwhile activity.
1) The absence of actual boundary conditions during trial fit i.e.
the dummy pile was not fabricated based on the actual pile
considering the batter angle.
2) Inaccurate DC report by Fabricator.

48 Lesson UIA - SMEP D12DR-A Jacket Operation & Execute L(3) 1 Issue: • Fabricator to provide accurate DC report.
Learnt Asia Installation Inaccurate DC report for boatlanding top clamp and bottom
guide that lead to inaccurate dimension during top and bottom • Proposal : COMPANY to get an independent
ring plate stopper installation at offshore. party to verify Fabricator's DC report.

Consequence:
1) Delay in boatlanding installation.
2) Boatlanding bottom stopper need to be removed and
relocated after adjusting the top ring plate and the bottom
stiffeners.

Why:
Inaccurate DC report by Fabricator.
49 Lesson UIA - SMEP D12DR-A Jacket Operation & Execute L(3) 1 Issue: Scheduled maintenance on OIC's hammer, provide
Learnt Asia Installation MHU 500T absorber problem and sensor error appropriate spare parts and conduct function test

Consequence:
Delay in piling operation

Why:
Lack of maintenance of equipment onboard
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
50 Lesson UIA - SMEP D12DR-A Jacket Operation & Execute L(3) 1 Issue: Review pile monitoring procedures. Check and
Learnt Asia Installation Damaged pile monitoring cable secure the pile monitoring cable properly as per
approved procedures.
Consequence:
Delay in piling operation

Why:
Lack of securing method of pile monitoring cable. Double check
the location of pile monitoring cable.

51 Lesson UIA - SMEP 2013 Transportation Operation & Execute L(3) 1 Issue: • For future campaign, custom team to be included
Learnt Asia & Structure Installation Non compliance to Customs Duties (Exemption) Order, Section in face to face meeting between COMPANY and
Installation 107 Condition (vi) & (v) that the Company shall keep record of CONTRACTOR.
the exempted materials.
• COMPANY to provide submission updates on
Consequence: DI/DE status to CONTRACTOR for monitoring
Goods are liable to duties . purpose

Why: • CONTRACTOR to provide evidence on material


No proper customs declaration (evidence) for importation & declaration to Custom.
movement of tax exempted materials (i.e Wirerope, ILT,
Hammer). • CONTRACTOR to declare surplus material to
Custom.
52 Lesson UIA - Eyeball ROV Services Operation & Execute L(3) 1 Issue: • Subcontractor should provide sufficient ROV's
Learnt Asia For LADR-A & F14DR- Installation ROV's spare parts spares
A Jacket Installation
Consequences: • Specific detail of critical spares should be
1) Down time may occur highlighted in the contract
2) Facing difficulties to carry out the job.
3) delay due to long lead time needed for ordering parts

Why:
Lack of spare parts provided onboard LTS3000
53 Lesson UIA - SMEP F14DR-A, LADR-A, Operation & Execute L(3) 1 Issue: • Issues will be further addressed to subcontractor
Learnt Asia D12DR-A Structure Installation WROV LARS was not protected, exposed to tugger wire during
Installation lifting activity.
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
54 Lesson UIA - SMEP F14DR-A, LADR-A, Operation & Execute L(3) 1 Issue: •Assure that the CONTRACTOR has only one
Learnt Asia D12DR-A Structure Installation Multiple Sub-Contractors designated senior person onsite (Diving Supt) who
Installation The prime Contractor on this campaign was TLO; and the diving is responsible for all underwater works: teams and
and ROV services were provided by 3 different Sub- performance, planning and execution. He should
Contractors:1) Air Spread - AME ;2) Work-Class ROV - TMT : coordinate the 3 teams and maximize the
3) Inspection Class ROV - ROVR. Intervention Policy for ROV and Diving, and have a
single authorized focal point for diving & ROV,
Consequences: responsible for a combined Safety Matrix, crew
There was some lack of continuity noted. change management, daily reports, dive plans,
JHA’s.
Why:
'Eyeball’ ROV was extra to the contract scope of work
specifications, provided by TLO for their own resources onsite.
The Supv for Eyeball ROV team reported to any senior filed
engineer on duty, the rest came under the Contract Diving SUPT.

55 Lesson UIA - SMEP F14DR-A, LADR-A, Operation & Execute L(3) 1 Issue: • Recommend that CONTRACTOR submitting the
Learnt Asia D12DR-A Structure Installation Personnel Qualification / Approvals CV Document package for approval; includes
Installation photocopy of key pages of Professional Logbook
Why: and copies of specialist certificates (e.g. HV cert for
The process of approving Personnel is well in place, but ROV, Oxy-Arc Burning training cert for divers, etc).
sometimes we find out onsite that technically approved persons Final inspection onsite completes the mob process,
are not carrying IMCA Logbooks or other certificates required and the DA/CSR file system offshore shall have a
under contract specification and Company / OGP guidelines. register of personnel during the duty cycle and
carry forward to handover.

56 Lesson UIA - SMEP F14DR-A, LADR-A, Operation & Execute L(3) 1 Issue: In this case it is recommended that the onsite
Learnt Asia D12DR-A Structure Installation Professional Logbook Endorsement DA/CSR review the CV documents and certs on
Installation hand, observe performance, then endorse the
Why: Logbook with signature and Company Chop
In several cases with Eyeball ROV crew, a brand new logbook was verifying the years of experience and
sent offshore, to comply with Company regulations, and vaguely commencement date of logbook.
endorsed by the Sub-contractor, and even with 6+yrs in the trade
one Supv never used one. Also 3 out of 6 on the Eyeball team
were issued new IMCA Logbooks to comply onsite.
Operating Project Discipline ORP
ID Type Region Risk Severity Description Recommendation
Unit Name Category Phase
57 Lesson UIA - SMEP F14DR-A, LADR-A, Operation & Execute L(3) 1 Issue: • Marine class generators to be available.
Learnt Asia D12DR-A Structure Installation Although system built to class Contractor failed to get class cert Class involved very early.
Installation as AME reported class needed a Marine class approved
generator for emergency backup. • Air Dive systems to have class certificates.
Deviation had to be raised.
• Please note that the same applies for saturation
Why: systems.
• No class certificate for the system onboard although long
notice has been given • TLO to purchase class generator set

58 Lesson UIA - SMEP F14DR-A, LADR-A, Operation & Execute L(3) 1 Issue: CONTRACTOR to conduct subcontractor audit.
Learnt Asia D12DR-A Structure Installation Inexperience contractor used for the supply of the inspection
Installation class ROV

Why:
1) Lack of kowledge on SMEP contract specifications, IMCA
guidance.
2) Manuals and project document demanded a lot of review
time.
3) Unclear on the expectation demanded and resulting to
difficulty in closing out of the 3rd Party audit of the system
59 Lesson UIA - SMEP F14DR-A, LADR-A, Operation & Execute L(3) 1 Issue: CONTRACTOR to appoint a focal person totally
Learnt Asia D12DR-A Structure Installation There is no evidence to show CONTRACTOR review Diving and dedicated to do the work and ensure this happens.
Installation ROV subcontractor’s documents or procedures or inspect
subcontractors systems to ensure safety and compliance to
SMEP and IMCA guidance.