Site Acceptance Test Report For 33Kv Cable: Contractor: Consultant: End Client
Site Acceptance Test Report For 33Kv Cable: Contractor: Consultant: End Client
Page: 1 of 2
Project: CONSTRUCTION OF 306 VILLAS – AL SAAD
Date: 03.02.2020
TEST REPORT FOR 33 kV CABLE
To Station: NRMAH-GD Feeder No: A05
From Station: SAAD PY Feeder No.:H06
To Joint Loc. Joint location no.12
R – (Y+B+E) 202
Y – (B+R+E) 5000 V DC 60 sec 271
B – (R+Y+E) 256
SIGNATURE
03.02.2020 03.02.2020 03.02.2020
DATE
Contractor: Consultant: End Client:
Page: 2 of 2
Project: CONSTRUCTION OF 306 VILLAS – AL SAAD
Date: 03.02.2020
TEST REPORT FOR 33 kV CABLE
To Station: NRMAH-GD Feeder No: A05
From Station: SAAD PY Feeder No.:H06
To Joint Loc. Joint location no.12
4. REMARKS:
5. EQUIPMENT DETAILS:
Calibration
Sl.No Instrument Name Make / Model Serial No
Valid
1 IR Tester Megger/MIT515 101574096 10.03.2020
SIGNATURE
03.02.2020 03.02.2020 03.02.2020
DATE