Normal Crash
Imm. Time Normal Time Crash Cost
Activity Description Predec. (Wks) Cost ($) (Wks) ($)
1 Select Administrative & Medical Staff - 12 12,000 11 13,000
2 Select Site and Do a survey - 9 50,000 7 64,000
3 Select Equipment 1 10 4,000 5 7,000
4 Prepare Final Construction Plan and Layout 2 10 16,000 8 20,000
5 Bring utilities to site 2 24 120,000 14 200,000
6 Fill positions in nursing, support staff, mainte 1 10 10,000 6 16,000
7 Purchase and take delivery of equipments 3 35 500,000 25 530,000
8 Construct the Hospital 4 40 1,200,000 35 1,260,000
9 Develop an Information System 1 15 40,000 10 52,500
10 Install the quipments 5, 7, 8 4 10,000 1 13,000
11 Train nurses and support staff 6, 9, 10 6 30,000 5 34,000
Gantt Chart
Activity
11
10
1
Weeks
0 10 20 30 40 50
1
Weeks
0 10 20 30 40 50
59 2 500,000 7 8 5
59 0 1,200,000
63 36 40,000
63 0 10,000
9 6
69 0 30,000 10
1,992,000
552,000
80,000
2,624,000
11
50 60 70
FLOAT
50 60 70
FLOAT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
Normal
Imm. Time Normal Crash
Activity Description Predec. (Wks) Cost Time
1 Select Administrative & Medical Staff - 12 12,000 11
2 Select Site and Do a survey - 9 50,000 7
3 Select Equipment 1 10 4,000 5
Prepare Final Construction Plan and
4
Layout 2 10 16,000 8
5 Bring utilities to site 2 24 120,000 14
Fill positions in nursing, support staff,
6
maintenance and security 1 10 10,000 6
7 Purchase and take delivery of equipments 3 35 500,000 25
8 Construct the Hospital 4 40 1,200,000 35
9 Develop an Information System 1 15 40,000 10
10 Install the quipments 5, 7, 8 4 10,000 1
11 Train nurses and support staff 6, 9, 10 6 30,000 5
Normal Duration
Normal Cost
New Duration
Savings in OH
Saving of Penalty
Incremental Cost of Crashing
Net Cost
Gantt Chart
Activity
11
10
4
10
Acti
9
1
Weeks
0 10 20 30 40 50
ES Duration Float
Crash Incr New
Cost Cost/Wk Duration Incr Cost ES EF LS LF FLOAT 1
13,000 1,000 12 0 0 12 2 14 2
64,000 7,000 9 0 0 9 0 9 0
7,000 600 10 0 12 22 14 24 2
20,000 2,000 10 0 9 19 9 19 0
200,000 8,000 24 0 9 33 35 59 26
16,000 1,500 10 0 12 22 50 60 38
530,000 3,000 35 0 22 57 24 59 2
1,260,000 12,000 40 0 19 59 19 59 0
52,500 2,500 15 0 12 27 45 60 33
13,000 1,000 1 3,000 59 60 59 60 0
9
34,000 4,000 6 0 60 66 60 66 0
69
2,624,000
66
24,000
60,000
3,000
2,543,000
50 60 70
uration Float
1 2
7 8 5
9 6
10
11
Normal
Imm. Time Normal Crash
Activity Description Predec. (Wks) Cost Time
1 Select Administrative & Medical Staff - 12 12,000 11
2 Select Site and Do a survey - 9 50,000 7
3 Select Equipment 1 10 4,000 5
Prepare Final Construction Plan and
4
Layout 2 10 16,000 8
5 Bring utilities to site 2 24 120,000 14
Fill positions in nursing, support staff,
6
maintenance and security 1 10 10,000 6
7 Purchase and take delivery of equipments 3 35 500,000 25
8 Construct the Hospital 4 40 1,200,000 35
9 Develop an Information System 1 15 40,000 10
10 Install the quipments 5, 7, 8 4 10,000 1
11 Train nurses and support staff 6, 9, 10 6 30,000 5
Normal Duration
Normal Cost
New Duration
Savings in OH
Saving of Penalty
Incremental Cost of Crashing
Net Cost
Gantt Chart
Activity
11
10
9
8
7
6
5
4
3
2
8
7
6
5
4
3
2
1
Weeks
0 10 20 30 40 50
ES Duration Float
Crash Incr New
Cost Cost/Wk Duration Incr Cost ES EF LS LF FLOAT 1
13,000 1,000 12 0 0 12 1 13 1
64,000 7,000 9 0 0 9 0 9 0
7,000 600 10 0 12 22 13 23 1
16,000 1,500 10 0 12 22 49 59 37
530,000 3,000 35 0 22 57 23 58 1
1,260,000 12,000 40 0 18 58 18 58 0
52,500 2,500 15 0 12 27 44 59 32
13,000 1,000 1 3,000 58 59 58 59 0
9
34,000 4,000 6 0 59 65 59 65 0
69
2,624,000
65
32,000
80,000
5,000
2,517,000
50 60 70
n Float
2
1
7 8 5
9 6
10
11
Normal
Imm. Time Normal Crash
Activity Description Predec. (Wks) Cost Time
1 Select Administrative & Medical Staff - 12 12,000 11
2 Select Site and Do a survey - 9 50,000 7
3 Select Equipment 1 10 4,000 5
Prepare Final Construction Plan and
4
Layout 2 10 16,000 8
5 Bring utilities to site 2 24 120,000 14
Fill positions in nursing, support staff,
6
maintenance and security 1 10 10,000 6
7 Purchase and take delivery of equipments 3 35 500,000 25
8 Construct the Hospital 4 40 1,200,000 35
9 Develop an Information System 1 15 40,000 10
10 Install the quipments 5, 7, 8 4 10,000 1
11 Train nurses and support staff 6, 9, 10 6 30,000 5
Normal Duration
Normal Cost
New Duration
Savings in OH
Saving of Penalty
Incremental Cost of Crashing
Net Cost
Gantt Chart
Activity
11
10
2
8
1
Weeks
0 10 20 30 40 50
ES Duration Float
Crash Incr New
Cost Cost/Wk Duration Incr Cost ES EF LS LF FLOAT 1
13,000 1,000 12 0 0 12 0 12 0
64,000 7,000 9 0 0 9 0 9 0
7,000 600 10 0 12 22 12 22 0
16,000 1,500 10 0 12 22 48 58 36
530,000 3,000 35 0 22 57 22 57 0
1,260,000 12,000 40 0 17 57 17 57 0
52,500 2,500 15 0 12 27 43 58 31
13,000 1,000 1 3,000 57 58 57 58 0
9
34,000 4,000 6 0 58 64 58 64 0
69
2,624,000
64
40,000
80,000
7,000
2,511,000
50 60 70
n Float
1 2
7 8 5
9 6
10
11
Normal
Imm. Time Normal Crash
Activity Description Predec. (Wks) Cost Time
1 Select Administrative & Medical Staff - 12 12,000 11
2 Select Site and Do a survey - 9 50,000 7
3 Select Equipment 1 10 4,000 5
Prepare Final Construction Plan and
4
Layout 2 10 16,000 8
5 Bring utilities to site 2 24 120,000 14
Fill positions in nursing, support staff,
6
maintenance and security 1 10 10,000 6
Purchase and take delivery of
7
equipments 3 35 500,000 25
8 Construct the Hospital 4 40 1,200,000 35
9 Develop an Information System 1 15 40,000 10
10 Install the quipments 5, 7, 8 4 10,000 1
11 Train nurses and support staff 6, 9, 10 6 30,000 5
Normal Duration
Normal Cost
New Duration
Savings in OH
Saving of Penalty
Incremental Cost of Crashing
Net Cost
Gantt Chart
Activity
11
10
9
8
7
6
5
4
3
2
8
7
6
5
4
3
2
1
Weeks
0 10 20 30 40 50
ES Duration Float
Crash Incr New
Cost Cost/Wk Duration Incr Cost ES EF LS LF FLOAT 1
13,000 1,000 12 0 0 12 0 12 0
64,000 7,000 9 0 0 9 0 9 0
7,000 600 10 0 12 22 12 22 0
16,000 1,500 10 0 12 22 48 58 36
530,000 3,000 35 0 22 57 22 57 0
1,260,000 12,000 40 0 17 57 17 57 0
52,500 2,500 15 0 12 27 43 58 31
13,000 1,000 1 3,000 57 58 57 58 0
9
34,000 4,000 5 4,000 58 63 58 63 0
69
2,624,000
63
48,000
80,000
11,000
2,507,000
50 60 70
ation Float
1 2
7 8 5
9 6
10
11
Normal
Imm. Time Normal Crash
Activity Description Predec. (Wks) Cost Time
1 Select Administrative & Medical Staff - 12 12,000 11
2 Select Site and Do a survey - 9 50,000 7
3 Select Equipment 1 10 4,000 5
Prepare Final Construction Plan and
4
Layout 2 10 16,000 8
5 Bring utilities to site 2 24 120,000 14
Fill positions in nursing, support staff,
6
maintenance and security 1 10 10,000 6
Purchase and take delivery of
7
equipments 3 35 500,000 25
8 Construct the Hospital 4 40 1,200,000 35
9 Develop an Information System 1 15 40,000 10
10 Install the quipments 5, 7, 8 4 10,000 1
11 Train nurses and support staff 6, 9, 10 6 30,000 5
Normal Duration
Normal Cost
New Duration
Savings in OH
Saving of Penalty
Incremental Cost of Crashing
Net Cost
Gantt Chart
Activity
11
10
2
8
2
1
Weeks
0 10 20 30 40 50
ES Duration Float
Crash Incr New
Cost Cost/Wk Duration Incr Cost ES EF LS LF FLOAT 1
13,000 1,000 12 0 0 12 0 12 0
64,000 7,000 7 14,000 0 7 0 7 0
7,000 600 8 1,200 12 20 12 20 0
16,000 1,500 10 0 12 22 46 56 34
530,000 3,000 35 0 20 55 20 55 0
1,260,000 12,000 40 0 15 55 15 55 0
52,500 2,500 15 0 12 27 41 56 29
13,000 1,000 1 3,000 55 56 55 56 0
9
34,000 4,000 5 4,000 56 61 56 61 0
69
2,624,000
61
64,000
80,000
26,200
2,506,200
50 60 70
ration Float
1 2
7 8 5
9 6
10
11
Imm. Duration Labour Material
Activity Description Predec. (Wks) Cost Cost
1 Elevator Pit Making - 3 10,000 50,000
2 Cast Elevator Shaft 1 24 0 0
3 Fix Guide Rails, Service Ladder 2 4 40,000 200,000
4 Install Counterweight 3 1 10,000 40,000
5 Install Elevator Car 3 3 60,000 330,000
6 Roof Over Elevator Shaft 4,5 3 5,000 0
7 Make Machine Room 6 4 5,000 0
8 Install Hoist Motor 7 3 15,000 300,000
9 Install Controller 7 1 4,000 500,000
10 Attach Wire Rope 8 2 10,000 45,000
11 Install Controls on each floor 2 3 20,000 100,000
12 Complete Electrical Connections 8,9,11 3 25,000 40,000
13 Programme Controller 9 2 40,000
14 Test The elevator 10,12,13 3 10,000
Total 254,000 1,605,000
1 Material and Labour Cost for each activity are incurred as soon as the activity begins
2 The Project has to be finished in 48 Weeks
3 If Activities 7,8,10,11 & 12 can be expedited by 1 week each by paying 20% more of labour cost,
activities will you expedite? Why?
ES EF LS LF FLOAT
0
0
0
0
0
0
0
0
0
0
0
0
0
0
ctivity begins
0
Wk 0 1 2 3 4 5 6 7 8 9 10 11
ES 60 60 60 60 60 60 60 60 60 60 60 60
LS 60 60 60 60 60 60 60 60 60 60 60 60
Cumulat
2000
1800
1600
1400
1200
1000
800
600
1800
1600
1400
1200
1000
800
600
400
200
0
0 2 4 6 8 10 12 14 16 18 20
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 ### ### ### ### ### ### ### ### ###
60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 ### ### ### ### ### ### ### ### ###