Professional Documents
Culture Documents
Bill of Quantities document was prepared according to the Highway Schedule Rate
(HSR) 2016 rates. Some rate analyses are based on historic details of past BOQs in similar
projects and University of Moratuwa student ERP system. This includes profit margin, company
overhead margin and allowance for price escalation.
2 Design
2.1 Bore Hole Investigation Item 1 1495000 1,495,000
2.2 Hydrological Survey Item 1 500000 500,000
2.3 Detail CBR & DCP testing Item 1 500000 500,000
2.4 Basic and detail design-Substructure Item 1 33606000 33,606,000
2.5 Basic and detail design-Superstructure Item 1 35000000 35,000,000
2.6 Basic and detail design-Road works Item 1 2330000 2,330,000
2.7 Traffic surveying Item 1 250000 250,000
Topographic surveying and GPS point
2.8 Item 1 500000 500,000
establishment
2.9 Quality Control & Quality Assurance Item 1 1758000 1,758,000
Other Engineering & technical
2.10 Item 1 1055000 1,055,000
management works
76,994,000
3 Mobilization
3.1 Clearing and Grabbing Item 1 1992500 1,992,500
Demolition of Structures and removal of
3.2 Item 1 225000 225,000
debris
Filling to makeup levels in tree removed
3.3 Item 1 160000 160,000
and demolish area
3.4 Erection of name boards/Plaque Item 1 80000 80,000
3.5 Construction of temporary access road Item 1 9124587 9,124,587
3.6 Construction of Temporary structures Item 1 330820 330,820
Provision Utility Damages/Shifting and
3.7 Item 1 1000000 1,000,000
rectification
3.8 Provision for temporary structures Item 1 300000 300,000
3.9 Provision for temporary acquisitions Item 1 250000 250,000
3.10 Initial Survey-Crack survey Item 1 100000 100,000
Mobilisation of all facilities machinery,
3.11 Item 1 100000 100,000
tools and equipment
13,662,907
5 Earthwork
5.1 Excavation in pile caps and abutments Item 1 670340 670,340
5.2 Excavation in retaining walls Item 1 32340 32,340
702,680
6 Superstructure
6.1 Concrete Item 1 6337500 6,337,500
6.2 PSC Beam Cost Item 1 371936480 371,936,480
6.3 Piers Item 1 40178619 40,178,619
6.4 Bridge kerb Item 1 3980800 3,980,800
6.5 Bridge Abutment Item 1 7264466 7,264,466
6.6 Drain pipes Item 1 3966120 3,966,120
6.7 Expansion joint Item 1 10018800 10,018,800
6.8 Dowels Item 1 143350 143,350
6.9 Bridge Bearings Item 1 0 0
6.10 Railing Item 1 45000000 45,000,000
6.11 Box Culvert Item 1 5473428 5,473,428
494,299,563
8 Other work
Demobilization Item 1 1850000 1,850,000
Maintenance work Item 1 3500000 3,500,000
Welded wire mesh fence (Road side)
Item 1 802500 802,500
safety net
Concrete Pre-cast Noise Barriers Item 1 9701666 9,701,666
15,854,166
Total 816,370,367
Profit 8% 85,653,579