LETTER OF TRANSMITTAL
December 6, 2018
Engr. Rc Lucas Instructor.
Department of mechanical Engineering
Bataan Heroes Memorial College Balanga City, Bataan 2100
Dear Sir,
In partial fulfilment in ME-510 (Air Conditioning Design). We hereby submit this Split
type Air Conditioning System for Senior Citizen with 80 Capacity, a project where we have
devoted most of our time, effort and perseverance. The forging statement and data are
carefully prepared in accordance with your guidelines and requirements. However we shall
deeply needed and appreciate your correction and suggestion for further improvement of this
project.
1
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Acknowledgement
In every work, there are individuals that serve as inspiration and extend ne hands in
their own simple ways. No matter what the size of their action, they ready-made this work
possible.
First and foremost, we gratefully thank are creator, Lord and Savior, Jesus Christ, for
the wisdom, strength and heart to do this design. For giving us the right of live by his grace and
mercy, we will whole-heartedly serve.
We also thank our beloved instructor, Engr. Rc. Lucas for his dedication to his
profession. The knowledge that they imparted us will always be in our mind, including the
creation of this work our appreciation extend.
To our family, for their sincere support, be it emotionally, spiritually and financially. No
words can express our deepest gratitude to you.
To our fellow classmates, dear friends and beloved comrades, we thank you for bearing
with us in this endeavour.
2
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Dedication
The accomplishment of this book was such a big challenge for the author that I could not help
but think that it was made possible because of unselfish assistance, inspiring guidance and
encouragement of the following person to whom I owe a debt of thankfulness and gratitude
beyond measure. To My Family Engr. RC Lucas BSME 5A Friends And most of all, to LORD
GOD, for answering my prayers and for giving me strength even though I wanted to give up
and throw in the towel, thank you so much DEAR LORD.
3
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Abstract
The modem commercial or office building consists of the HVAC system which is Heating
Ventilation Air-conditioned. In this report, we'll going to identify the purpose and goals of HVAC
System, describe HVAC types, describe HVAC parts and describe how this part works
together or its working cycle. Besides to air-conditioning there are ventilation systems like
ceiling fan, fresh air supply and exhaust fan where ceiling fan is used is used for ventilate the
air with rotating blades and exhaust fan is used to displace the inside air to the outside
environment, fresh air supply is Used to displace the inside air to the Outside environment by
supplying fresh air from the outside air.
4
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
CHAPTER I
Problem and it’s Background
5
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Introduction
Air-conditioning system have been used in many parts of the world. The application of
air conditioning can be considered in many aspects of the industry today. May it be inside
someone's home, within a commercial establishment, or inside a plant facility with delicate
substances that is needed to be maintained at a certain temperature. Truly, the study of air
conditioning is essential for one who aim's to be a successful mechanical engineering. Many
experts can teach us on the introductory of the basic fundamentals of air conditioning, but
according to the Oxfords Dictionary, air conditioning is considered to be a system for
controlling the humidity, ventilation, and temperature in a building or vehicle, typically to
maintain a cool atmosphere in warm conditions. Within this definition, we can conclude that air
conditioning is a process in which the atmospheric temperature of a certain limited space is
manipulated in achieving the desired temperature for the give purpose of what is needed.
Different requirement can be considered in many aspects when it comes to air conditioning.
But in all this, how can we relate this with the application of theories and studies to the comfort
of people, especially in function halls or meeting rooms.
With an in-depth study and calculations to be considered, this study is aimed to create an
efficient air conditioning design in the 300 m 2 Multi-purpose hall. A split-type air conditioning
system is chosen to be used in the said facility.
6
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
7
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Chapter II
Conceptual Framework
8
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
In this chapter includes the ideas, relevant theories, related literatures and studies conceptual
and/or frame work and definition of terms. Those that were included in this chapter help in
familiarizing information that are relevant and similar to the present study.
Relevant Theories
First we need to understand the fundamentals of heat. The amount of heat energy present in
the air and refrigerant is measured as the temperature. There are two different temperature
scales most commonly used, Fahrenheit and Celsius.
I. Sensible Heat: When the heat that is applied to a substance merely raises its
temperature, but does not change its physical state. It is the heat which, added to or
subtracted from a substance, produces the changes in temperature indicated on
thermometer. (i.e. It is the heat that you feel or sense)
II. Latent Heat: The heat released or absorbed by a substance when it changes its
physical state to another with no change in temperature. (i.e. ice to liquid and liquid to
vapor)
9
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
10
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
classification of the services appearing in the list, excluding those in which the minimum area
of the building requiring them is especially large and deviates significantly from most of the
others in the list. Those services remaining therein had primary potential for being included in
the model.
11
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
6. Distribution of the residential units over the site: The disposition is influenced by the size of
the site and the type of construction ground-hugging or saturated. This data must be taken into
account in any consideration of deployment of the complexes and the services each one will
house. For example, on a site having extensive distribution, it will be necessary to scatter the
complexes more widely and to determine the services in each of them according to its
accessibility to the target population.
12
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
CHAPTER III
Methodology
13
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Methodology
This study used the spilt-type air conditioning system design for it is the simplest and most
recommended type of system with regards to the area of the hall. The experts said that using
this type of system can minimize the use of ducting and it could less the expenses in the
multipurpose hall.
Based on the book of Split Systems from Carrier Corporation, a split system is an air-
conditioning or heat pump system that uses refrigerant as the heat exchanger fluid and has an
evaporator, compressor, and condenser as separate components. In most modern commercial
applications, the compressor and condenser are combined into a single piece of equipment
called a condensing unit. Refrigerant piping, custom-designed to meet the physical
requirements of each individual application, connects the system components.
There are certain advantages in using split-type system, especially in establishments like the,
multi purpose hall.
Flexibility- split systems disregards the use of ducting, which can be a heavy factor on
the aesthetics, and allows the engineers to adjust depending on the needs of the facility.
Simplicity considered as the simplest system for commercial applications Other systems
like the chilled water systems or centralized systems. etc, requires more components
and maintenances.
Costs-with relevance to the simplicity of the design fewer components are needed to
have the system efficiently running unlike other systems.
14
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
CHAPTER IV
Design and Layout
15
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
The type of AC system design used in this study is a split-type system AC design This is based
on various field expert advices considered in designing an air conditioning system. The design
is also considered to be much preferable by various studies that involves the creation of such
systems in a multi purpose hall The system is also used due to its different factors which
involves its flexibility with the design, its simple outline that still highlights the aesthetics that
the multi purpose hall embodies, and its cost efficiency with the equipment and materials
Needed.
CAUTION:
Do not operate the air conditioner for long periods with the air flow direction set
ownward in cooling or dehumidifying mode Otherwise, condensation may occur on the
surface of the horizontal louver causing moisture to drop on to thefloor or on furnishings.
When the air conditioner is started immediately after it was stopped, the
oizontal louver might not move for approximately 10 seconds.
Open angle of the horizontal louver should not be set to0 small, as COOLING or
HEATING performance may be impaired due to too restricted air flow area.
Do not move the honizontal louver manually, otherwise the horizontal louver will
be out of sync. Please cease operating, unplug power for a few seconds, then
restart the air conditioner.
17
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Before maintenance
Turn the system off before cleaning To clean, wipe with a soft, dry cloth Do not use
bleach or abrasives NOTE Power supply must be disconnected before cleaning the
indoor unit
CAUTIONS:
A cloth dampened with cold water may be used on the indoor unit if it is very dirty.
Then wipe it with a dry cloth. Do not use a chemically treated cloth or duster to clean the
unit.
Do not use benzine, thinner, polishing powder, or similar solvents for cleaning.
These may cause the plastic surface to crack or deform.
Never use water hotter than 40°C/104"F to clean the front panel, it could cause
deformation of discoloration.
Clean the AlR FILTER with a vacuum cleaner or water, then dry it up in cool Place..
18
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
4. Remove the Air Freshening Filter from its supporting frame (on some models). Clean the air
freshening filter at least once a month, and replace it every 4-5 months. Clean it with vacuum
cleaner, then dry it in cool place.
5. Install the air freshening filter back into position.
6. Insert the upper portion of air filter back into the unit, taking care that the left and right edges
line up correctly and place filter into position.
Replacement of air filter and air freshening filter
1. Remove the air filter.
2. Remove the air freshening filter
3. Install a new air freshening filter.
4. Reinstall the air filter and securely close the front panel.
Preparation for extended non-operation
Pre-season inspection If you plan to idle the unit for a long time, perform the
following:
(1) Clean the indoor unit and filters.
(2) Operate the fan for about half a day to dry the inside of the unit
(3) Stop the air conditioner and disconnect power.
(4) Remove the batteries from the remote controller. The outdoor unit requires periodic
maintenance and cleaning. Do not attempt to do this yourself. Contact your dealer or service
provider. Check that the wiring is not broken off or disconnected. Clean the indoor unit and
filters. Check that the air filter is installed. Check if the air outlet or inlet is blocked after the air
conditioner has not been used for a long time.
Caution:
Do not touch the metal parts of the unit when removing the filter. Injuries can occur
when handling sharp metal edges.
Do not use water to clean inside the air conditioner. Exposure to water can destroy the
insulation, leading to possible electric shock.
When cleaning the unit, first make sure that the power and circuit breaker are turned off.
19
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Do not wash air filter with hot water at more than 40°C/104°F. Shake off moisture
completely and dry it in the shade. Do not expose it directly to the sun, it may shrink.
20
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
21
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
22
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
DESIGN CONSIDERATION
23
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
CHAPTER V
DESIGN AND COMPUTATION
24
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
WALLS AREA
FRONT WALL
DIMENSION SIZE (m)
LENGTH 18.7
HEIGHT 3.5
RIGHT WALL
DIMENSION SIZE (m)
LENGTH 16.65
HEIGHT 3.5
LEFT WALL
DIMENSION SIZE (m)
LENGTH 16.65
HEIGHT 3.5
25
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
WINDOWS AREA
FRONT WINDOW x6
DIMENSION SIZE (m)
LENGTH 1.20
HEIGHT 1.20
RIGHT WINDOW x2
DIMENSION SIZE (m)
LENGTH 1.20
HEIGHT 1.20
LEFT WINDOW x4
DIMENSION SIZE (m)
LENGTH 1.20
HEIGHT 1.20
DOORS AREA
FRONT DOOR
DIMENSION SIZE (m)
LENGTH 1.87
HEIGHT 2.04
RIGHT DOOR x4
DIMENSION SIZE (m)
LENGTH 0.90
HEIGHT 2.04
LEFT DOOR
27
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
SIDE WALL AREA (m2) WINDOW DOOR AREA (m2)
AREA(m2)
FRONT 18.7 8.64 3.8148
BACK 18.7 N/A N/A
LEFT 16.65 2.88 6.936
RIGHT 16.65 5.76 3.8148
TOTAL 243.04 17.28 14.5656
TOTAL WALL AREA = Wall back + Wall front + Wall left + Wall right-(Window front + Window
left +Window right +Door front +Door right +Door left)
TOTAL WALL AREA =243.04-(17.28+14.5656) = 211.1944m2
TOTAL WINDOW AREA =17.28m2
TOTAL DOOR AREA=14.5656m2
28
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Design Outdoor temperature = 32C, t1
Design Indoor temperature=24C, t2
U=1/RT=1/0.687=1.456 w/m2K
Q=UA(t1-t2)= 1.456 w/m2K (243.04m2)(32-24)
Total heat load of wall =2,830.9299 W
MATERIALS R, m2-K/W
Sand And Gravel, Aggregates 0.0825
Plywood 6mm 0.05196
Ceramic Tiles 0.0625
Total RT =0.197
From the table 4-11 p76 Refrigeration and Airconditioning by Stoecker, for heat absorbing
glass for regular sheet;
SC=0.64
31
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
For the heat transmitted through the transparent surfaces, Q s
Qs=(SHGFmax)(SC)(CLF)(A)
=450(0.64)(0.37)( 4.2646)
=454.438W
32
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Heat gain 100 W
Sensible heat gain 60%
Qp=100W(0.6)=60W .
From table 4-9, p74 by stoEcker, for cooling load factor per person
CLF for working 6 hrs=0.79
No. of occupants =105
Qos=60(105)(0.79)= 4,977W
From table 4-7, p73 by stoEcker, for heat gain from occupants;
Standing;
Heat gain 150 W
Sensible heat gain 50%
Qp=150W(0.5)=75W .
From table 4-9, p74 by stoEcker, for cooling load factor per person
CLF for working 2 hrs = 0.58
No. of occupants =15
Qos=50(15)(0.58)= 435W
33
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Hours of Operation=6hrs
From table 4-6, p72 by stoecker; Cooling load factor for 6hrs
CLF=0.78
QLS=(Lamp rating) (no. of lamps) (Fu) (Fb) (CLF)
=100(30) (1) (1.2) (O.82) = 2952W
TOTAL = 960W
34
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Qil=3000(0.152) (0.0235-0.0112) = 5.61W
Heat Loads
Wall 2,830.9299W
Door 284.321W
35
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Window 815.616W
Appliances 960W
TOTAL 29,098.0048W
36
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
37
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Total Installation and Labor cost = Php 16,110
Billing of Materials for Repairing of Space Left and Elevation of Condensing unit
Materials Cost of Material Quantity Total Cost
Cement 1 sack per 250 4 1000
space
Sand and Gravel 50/0.2 4 1000
Concrete Mix/m3
Hollow Block 16” 19 40 760
Angle Bar 3/16x1 280 7 1960
Total 4,720
38
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Cost of AC/unit: Php 62,000
Estimated Salvage Value at end of life: 8,750
Estimated Life Year of Unit: 10yrs
Depriciation During the year= Dep. Factor(Cost/Unit- Salvage Value)
Cost/Unit-Salvage Value=Php 53,250 By Method of Sum of the Yr Digits
Year Year in Depriciation Depreciation Book Value at
Reverse Factor1 During the Year the End of the
Year (PHP
1 8 8/36 8/36(53,250) 49,416.67
2 7 7/36 7/36(53,250) 39,062.5
3 6 6/36 6/36(53,250) 30,187.5
4 5 5/36 5/36(53,250) 22,791.67
5 4 4/36 4/36(53,250) 16,875
6 3 3/36 3/36(53,250) 12,437.5
7 2 2/36 2/36(53,250) 9,479.16
8 1 1/36 1/36(53,250) 8,000
Sum of Years = 36 Years
39
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Computation of Buying Expenses for the AC Unit
AC Model Unit SRP(PHP) NO. of AC Units Total Cost(PHP)
Panasonic Window Php 28,500 14 399,000
Type Air
Conditioning- CW-
SC125VPH
Total Buying Expenses =Php 399,000
Computation of Installation and Labor Cost
Estimated Pay/day of Each Worker: Php: 537/day
No. of workers per 2units: 2workers/2units
No. of Days of Installation Period= Preparation for Installation + Installation period + Clean up
= 2+2+1
No. of Days of Installation period= 5 days
Total Installation and Labor cost = (Est. pay/day)(No. of Workers/unit)(8)(no. of Days)
= 537(2/2)(14)(5)
Total Installation and Labor cost = Php 37,590
40
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
November 8.8 6 30 2.7 14 59875.2
December 8.8 6 31 2.7 14 61871.04
42
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
CHAPTER VI
Conclusion and Recommendation
43
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Conclusion
Therefore we conclude that we need 5 AirConditioning units to satisfy and give comfort to the
occupant in Multipurpose hall. And also I want to conclude that using of Split type
AirConditioning units will save power consumption and money.
Recommendation
Would like to recommend to this design, that the multi purpose hall that will be on the left by
the current installed AC unit.
44
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
ATTACHMENT
45
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
THERMAL RESISTANCE OF UNIT AREAS OF SELECTED BUILDING
MATERIALS @24OC MEAN TEMPERATURE
THERMAL
46
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
47
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
48
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL
Bataan Heroes Memorial College
Roman Super High-Way 2100 City of Balanga, Bataan
Tel. / Fax No. (047)237-2383 Email@bhmc.edu.ph
Mechanical Engineering Department
Appendixes
49
AIR-CONDITIONING DESIGN OF A 12 TR SPLIT-TYPE SYSTEM OF MULTI PURPOSE HALL