3 Permit Reciever
Erection of base Sole boards to be correct length for Permit Issuer
frame standard and Unsupported frame or soft ground Scaffolding Supervisor
bracing standard being erected at HSE Manager
ground level 3 planks to be used for temporary HSE Officer
work plateform Scaffolding Inspector
Work Engineer
Base plates and screw jack used under
all the frame and standards
4 Erection of working Manual handling 2 persons to pass material to high lift Permit Reciever
platform. Permit Issuer
Split uneven decks installed Working decks to be at same height at Scaffolding Supervisor
least 12-inch overlap on every HSE Manager
scaffolding plank whenever necessary.
HSE Officer
Base frames not adequately
braced or supported.
5 . Erection of edge Climbing on the outside of climbing on the outside of scaffold will Permit Reciever
protection, ladder & scaffold be prohibited. Permit Issuer
toe board and Gin Scaffolding Supervisor
wheel Ladder will be installed to serve as safe HSE Manager
access to all scaffold users
HSE Officer
Scaffolding Inspector
Falling from height When getting the materials in the Permit Reciever
canvas bucket, worker / scaffolder shall Permit Issuer
comply with 100% tie off on permanent Scaffolding Supervisor
structure or installed lifelines HSE Manager
Scaffolder / worker shall not stand in HSE Officer
the edge of a scaffold platform to get
the materials from canvas bucket.
Implement double hook
Scaffold adequately braced to prevent Permit Reciever
movement while edge protection is Permit Issuer
Movement of Scaffold
fixed Scaffolding Supervisor
Handrail positioned not below 950mm HSE Officer
and above 1150mm of the working
platform on all sides Scaffolding Inspector
Edge protection incomplete Mid rail, top rail and toe board shall be Permit Reciever
installed Permit Issuer
Scaffolding Supervisor
HSE Officer
Temporary Construction Facility
Contract No: 660004138
compatible.
Scaffold frames and components made
by different manufacturers shall not be
inter mixed unless the parts and
materials are specifically made to
compatible.
from walkways
Always implement proper
housekeeping during, before and after
work.
10 Demobilization Vehicular accident Permit Reciever
Ensure PWAS on equipment is Permit Issuer
functional. Scaffolding Supervisor
Ensure PWAS on equipment is HSE Manager
functional.
Reflective vest shall be utilized HSE Officer
Construction Manager
SAPM Safety
Temporary Construction Facility
Contract No: 660004138
Safety Officer