WORKS SCHEDULE January February March Remarks

SO No. Work Description 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th
Plan
12860 RG1 Perliet Cabinet Fabrication Actual On-Going
Plan
12900 RG1 AC Cabinet Repair Actual DONE
Plan
12693 PG plants Lighting Supports Actual Materials Is Ready

Plan
12990 PW Piperack Foundation Repair Actual On-Going
Plan
13117 Exhaust Fan Cover Repair/Rehab Actual Materials Is Ready

Plan
13118 Mezzanine Door Modification Actual Materials Is Ready

Plan
13188 DG3 Chiller Roof Replacement Actual Done
Plan
13188 DG2 Prep Hoist Roof Replacement Actual Materials Is Ready

Plan
13188 DG1 End Flashing Replacement Actual
Plan
13277 RG1 P211 Distillate Line to V121A/V121B viao V125 Actual
Plan
13284 RG1 Ejector Header Replacement Actual Done
Plan
13186 RG1 Modification of Manhole Cover for T421A/B Actual Materials Is Ready

Plan
13186 RG2 Provision of Isolation Valve for ZV531C and ZV541C Actual
Plan
13211 DG2 Prep Extension of Flooring Structure for 4th Floor Actual
Plan
13278 RG1 Temporary Diffuser to T223 Actual Done
Plan
13278 RG2 PWT1A Discharge Line Repair Actual
Plan
13278 DG2 Prep CW Line Repair 2nd Floor Actual Done
Plan
13279 Admin Building Repair (North Portion) Actual Materials Is Ready

Plan
13279 DG3 Lightning Arrester Repair Actual