Professional Documents
Culture Documents
Thesis Estimation and Costing Feb 07-02-2021
Thesis Estimation and Costing Feb 07-02-2021
A project submitted in fulfilment of the requirements for the award of the degree of
Bachelor of science in Civil engineering from City University
This is to certify that the project entitled “A STUDY ON ESTIMATION AND COSTING
OF A FIVE STORIED RCC RESIDENTIAL BUILDING IN BOGURA CITY ” is done by
Md.Rajib Hossain bear’s ID No:163410521,
Md.Jahidul
Islam bear’s ID No:163410549, Md.Mehedi Hasan bear’s ID
No:163410501 in partial fulfilment of the requirements of Bachelor of Science in Civil
Engineering degree from City University, Dhaka, Bangladesh.
The project has been carried out under my guidance and is a record of work carried out
successfully. No part of this project consists of materials copied or plagiarized from
any published or unpublished works.
Supervised by
---------------------------
Senior Lecturer
Date:00-00-00
---------------------------
-----------------------Md.Rajib Hossain
Md.JahidulIslam
ID:163410521 ID:163410549
--------------------------
Md.Mehedi Hasan
ID:163410501
ACKNOWLEDGEMENT
Firstly, we would like to gratefulness with mighty esteem to our Allah for
the completion of this project work.
TABLE OF CONTENTS
PAGES
TITLE……………………………………………………………… 00.00
CERTIFICATE…………………………………………………….00.00
DECLARATION…………………………………………………...00.00
ACKNOWLEDGEMENT…………………………………………00.00
CHAPTER 1
INTRODUCTION…………………………………………………00.00
1.1 GENERAL…………………………………………………….00.00
1.2 PROJECT DESCRIPTION…………………………………00.00
1.3 OBJECTIVE OF THIS STUDY…………………………….00.00
1.4 SCOPES OF THE STUDY………………………………….00.00
1.5 OUTLINE OF THE PROJECT……………………….……00.00
CHAPTER 2
2.1 BUILDING……………………………………………………00.00
2.2 TYPES OF BUILDING………………………… …………...00.00
2.3 LOAD TRANSFER PATH IN FRAME STRUCTURE……00.00
2.4 COMPONENR OF BUILDING ……………………………..00.00
2.5 FOUNDATION……………………………………….……….00.00
2.6 PLINTH………………………………………………………..00.00
2.7 WALL………………………………………………………….00.00
2.8 BEAM………………………………………………………….00.00
2.9 SLAB…………………………………………………………...00.00
2.10 COLUMN………………………………………………….…..00.00
2.11 TYPE OF COLUMN……………………………………….…00.00
2.12 DESIGN OF TIED COLUMN…………………………….….00.00
2.13 DESIGN OF SPIRAL COLUMN…………………………….00.00
2.14 FLOOR……………………………………………………..….00.00
2.15 DOOR, WINDOWS…………………………………………...00.00
2.16 STAIR………………………………………………………….00.00
2.17 ROOF……………………………………………………….….00.00
2.18 WATER TANK………………………………………………..00.00
2.19 BUILDING FINISH…………………………………………...00.00
2.20 BUILDING SURVICES……………………………………….....00.00
2.21 RETROFITTING……………………………………………...….00.00
2.22 WHY RETROFITTING REQUIRED………………………..…00.00
2.23 CODE……………………………………………………………....00.00
2.24 THE MAIN PURPOSE OF BUILDING CODE…………..…….00.00
2.25 BANGLADESH NATIONAL BUILDING CODE (BNBC)….....00.00
2.26 LOADS……………………………………………………………..00.00
2.27 SEISMIC ZONE OF BANGLADESH……………………………00.00
2.28 WIND LOAD……………………………………………………….00.00
2.29 EARTHQUAKE LOAD CALCULATION………………………00.00
2.30 SPECIFICATION OF MATERIALS ………………………….…00.00
2.31 CEMENT……………………………………………..…………..…00.00
2.32 BRICK……………………………………………………………….00.00
2.33 WATER………………………………………………….……….….00.00
2.34 FINE AGGREGATE: SAND…………………………………....…00.00
2.35 COARSE AGGREGATE: STONE CHIPS……………….…....…00.00
2.36 COARSE AGGREGATE: BRICK CHIPS……………………….00.00
2.37 WHAT IS ESTIMATION………………………………….…….…00.00
2.38 PURPOSE OF ESTIMATION……………………………………..00.00
2.39 DATA OF ESTIMATION……………………………………….….00.00
2.40 NECESSARY OF ESTIMATION AND COSTING……………...00.00
2.41 TYPES OF ESTIMATION……………………………….………...00.00
2.42 IMPORTANT POINTS ABOUT ESTIMATION…………….…...00.00
2.43 PWD RATE SCHEDULE
CHAPTER 3
3.1 ARCHITECTURAL DRAWING………………………………..………..00.00
3.2 STRUCTURAL DRAWING……………………………………………….00.00
CHAPTER 4
ANALYSIS OF PROJECT ESTIMATION AND COSTING……………….00.00
4.1 SLAB……………………………………………………………….….….…00.00
4.2 BEAM………………………………………………….……………………..00.00
4.3 COLUMN………………………………….……………..…………….……00.00
4.4 FOOTING…………………………………………………………..………..00.00
4.5 BRICK WORK………………………………………………………..……..00.00
4.6 PLUMBING, ELECTRICAL AND OTHERS……………………………00.00
4.7 COMPARISON BETWEEN PWD RATE AND ESTIMATED RATE…00.00
CHAPTER 5
CONCLUSION
5.1 CONCLUSIONS…………………………………………..00.00
5.2 RECOMMENDATION…………………………………..00.00
REFERENCES
ABBREVIATIONS:
FF = Floor finish
DL = Dead load
LL = Live load
𝜌 = Reinforcement ratio
𝑀𝑢 = Factored moment
𝑃𝑢 = Factored load
1.1 GENERAL
One of the key factors in construction industry is estimating and costing. Accurate
estimation is very important as the success and quality of a construction or project
depend on it. And cost analysis of a construction is generally developed at all of the
stages of the investment process. The loss and profit of a construction or project is
strictly dependent on proper estimating and costing. Slight variation of the
construction cost can hamper the overall success of a real estate enterprise and it can
also hamper the financial stability of the developer. In this paper, a complete guideline
for estimating of projects is provided with respect to architectural, structural, electrical
and plumbing design. The item wise estimation and costing of a 5 storied residential
building in Bugora city is performed in the spread sheet analysis and the discussion of
result and recommendations are provided.
CHAPTER 1: Introduction
CHAPTER 5: Conclusion
CHAPTER 2
LITERATURE REVIEW
BUILDING
A building is a structure with a roof and walls standing more or less permanently in
one place, such as a house or factory. Buildings come in a variety of sizes, shapes and
functions, and have been adapted throughout history for a wide number of factors,
from building materials available, to weather conditions, to land prices, ground
conditions, specific uses and aesthetic reasons. Buildings serve several needs of
society – primarily as shelter from weather, security, living space, privacy, to store
belongings, and to comfortably live and work. A building as a shelter represents a
physical division of the human habitat (a place of comfort and safety) and the outside
(a place that at times may be harsh and harmful).
Types of buildings
Building can be classified into different categories from different perspective. Many
buildings fall into multiple categories simultaneously. In general, building can be of
following types:
Residential Buildings
Educational Building
Institutional Building
Assembly Building
Business Building
Mercantile Building
Industrial Building
Storage Building
Hazardous Building
Why types of buildings are a concern:
1. To know the design load for the building
2. To know the best orientation of the building as per its purpose of use.
Load Transfer Path
Load transfer path depends on the type of structure of the building. Broadly, building
structures can be of 2 types:
1. Frame structure / Non-load bearing structure
2. Load bearing structure
Frame structure: Frame structure consists of slab, beam, column, foundation
which bear all the loads of building. Here the walls of the building are usually for
partition purpose, these partition walls do not take part in the load bearing
mechanism of the building.
Load transfer paths in frame structure
Loads passing path for typical frame structure:
Topically in frame structures, load passes from slab to beam, beam to column and
finally column to foundation.
Fig: Load transfer path in flat plate Fig: Flat plate structure
structure
i. Super structure: This is the part of the building above the ground surface that
is visible after the completion of the construction work. Example: Plinth, column,
beam, slab etc.
ii. Sub structure: This is the part of the building below the ground surface that is
not visible after the completion of the construction work. Example: Foundation, shore
pile etc.
Foundation
Plinth
Walls
Beams
Columns
Floors
Doors, Windows
Stairs
Roof
Building finishes
Building service
Foundation: Foundation transfers all kind of load coming from the super structure to
the soil in such a way that it doesn’t exceed the bearing capacity of the soil of that
place.
Necessity of Foundation:
• To distribute the weight of structure over a large area without stressing the soil
beyond its capacity.
• To load the sub-stratum evenly and prevent unequal settlement or differential
settlement.
• To provide a level surface that facilitates subsequent construction works.
To take the structure deep into the ground and thus increase its stability by preventing
overturning.
Type of Foundation:
Plinth: This is the floor of the building immediately above the ground surface. Plinth
Fig: Plinth
Walls: In frame structure, walls are constructed for partition purpose, walls provide
separation of floor spacing and also protect the inside space from sun, rain and other
direct weathering effect. In load bearing structure, walls participate in load transfer
procedure of the building.
BEAMS:
Beams are horizontal members which take load coming parallel to its cross section. It
can also take axial loads. Beams are mainly designed to resist bending.
Classification of Beam:
Introduction:
Assumptions:
The main task of a structural engineer is the analysis and design of structures.
The two approaches of design and analysis will be used.
Design of a section:
This implies that the external ultimate moment is known, and it is required to
compute the dimensions of an adequate concrete section and the amount of steel
reinforcement. Concrete strength and yield of steel used are given.
ANALYSIS OF A SECTION:
This implies that the dimensions and steel used in the section (in addition to
concrete and steel yield strengths) are given, and it is required to calculate the
internal ultimate moment capacity of the section so that it can be compared
with the applied external ultimate moment.
Beam Types
▫ Singly reinforced section
▫ Doubly reinforced section
Flexure Equation:
Classification of slab
Can be broadly classified into two categories:
1. One way slab
2. Two ways slab
Other categories:
1. Edge supported slab/ slab on beam
2. Flat slab
3. Flat plate slab
4. Waffle slab
Columns:
Columns are vertical members that mainly take axial load (predominantly
compression).
Classification of column:
Types of column:
Strength is governed by the strength of the material and dimension of the cross
section
Slender Column
When (klu/r)>100
Ties
Spiral
Steel pipe
Concrete
filled
Top floor
Intermediate
floor
Slab
Beam
Column
According to ACI Code 10.3.6.1, the design strength for tied column
• 16 db of longitudinal reinforcement
• 48 db of tie bar
The ties shall be so arranged that every corner and alternate longitudinal bar shall
have lateral support provided by the corner of a tie having an included angle of not
more than 135°.No bar shall be farther than 6 in. clear on either side from such a
laterally supported bar. Where the bars are located around the periphery of a
circle, complete circular ties may be used. Details in Figure 5.3.
4bar
6bar
>6in
< 6" <
6"
>6 in
<
6"
12 bar
Max 6in
6" max
16 bar
6 " max
Concrete cover
Minimum 1 "
( ACI Code 7.7.1.c )
For
bundled
bar = db≤ 2
in (ACI
Code 7.7.4
)1.5 d b >
1 in
Lap Splices:
Code requirements for lap splices are given in Table 5.1. Details of lap
splices at typical interior column are shown in Figure 5.4. In addition,
for offset bar following should be observed:
ACI Code 7.8.1.4, offset bars shall be bent before placement in the
forms.
Reduction by
Longitudinal Bars in Compression (ACI Code
12.17.2.4 and
12.17.2.5)
All bars of equal fc’ > 3000 psi fy ≤60,000 psi ls = 0.0005 fydb For Tied:
sizes ≥ 12 in. Effective area ≥
(ACI Code 0.0015hs
12.16.1) ls= ls * 0.075
fy > 60,000 psi ls = (0.0009 fy – For Spiral:
24)* db ≥ 12 in. ls = l s *
0.75
For Larger Bar (ACI Code12.16.2 ) : Lap splices are generally prohibited for
No. 14 or No.18 bars, however, for compression only, lap splices are permitted
for No14, or No. 18 bar to No. 11 bars or smaller bars.
According to ACI Code 10.3.6.1, the design strength for spiral column
4Ag
D=
π
Select D as whole number (say, D = 30 in.)
Step 5: Check for Steel Ratio
πD 2
Ag =
4
Putting this Ag, in equation (5-4), ρg is calculated
If ρg = 0.01 ≈ 0.08, Design is ok
Ast = Ag * ρg
Now choose required bar size satisfying the ACI Code
10.9.2 requirement i.e.minimum number of bars
should not be less than 6.
But>1.5 in
dc
D dc Ss = Pitch
A sp
db
(a) (b)
8.90Asp f y
Ss = dc (Ag/Ac-1) f 'c But 1 in. < Ss < 3 in (ACI Code 7.10.4.3)
Step 10: Placement of spirals
Top ofslab
Slab + beam
End of spiral at
( ACI Code 7.10.4.6)
(Start of spiral
ACI Code 7.10.4.6)
Extra1-12" turn
beam reinforcement
for Anchorage
( ACI Code 7.10.4.4 )
2D
End of
( ACI Code 7.10.4.8
Column capital
D
Stair:
A stair may be defined as series of steps suitably arranged for the purpose of
connecting different floors of a building. It may also be defined as an arrangement of
treads, risers, stringers, newel posts, hand rails and baluster, so designed and
constructed as to provide an easy and quick access to the different floors, rendering
comfort and safety to the users. The enclosure containing the complete stairway is
termed as staircase.
Stairs may be made from various materials like timber, stones, bricks, steel, plain
concrete or reinforced concrete. The selection of the type of material to be used to
depend upon the aesthetical importance, funds available, durability desired and fire
resisting qualities expected.
Roof: It is the top surface of the building which usually protects the building from
rain, sun, light, snow etc.
Water Tank
Tanks for retaining water can be broadly divided into three categories i.e.
(1) Under Ground tanks
(2) Tanks resting on ground
(3) Tanks supported on staging or elevated tanks.
Both underground tanks as well as tanks resting on ground are normally circular or
rectangular in shape. An elevated tank on the other hand serves as an important architectural
feature, and is therefore, shaped to suit the Aesthetic requirement of the surrounding
besides circular, square and rectangular tanks, Intel type tanks, polygonal tanks spherical
tanks, conical tanks etc. arc some of the commonly adopted shapes for elevated tanks. The
tank proper is supported on staging which may consist of well braced columns or an
enclosed shaft. The staging columns may be straight or tapered and the lank could be
treated with moldings or other decorative feature to make the structure more attractive.
Building Finishes: Building finishes make the building complete to live in, such as
plastering, placing tiles/ mosaic, painting, white washing etc.
Building services: These are mainly the utility parts of a building such as water
supply, electricity connection, gas connection, sanitation system etc.
Fig: Retrofitting
CODES:
A code is a set of technical specification and slanders that control important details of
design and construction. The purpose of codes is to produce sound structures so that the
public will be protected from poor or inadequate design and construction.
Two types of codes exist. One type, called a structural code, and another type, called a
building code. The American Concrete Institute (ACI) building code 318-95, covering
the design of reinforced concrete buildings. In Bangladesh a code is established known
as Bangladesh National Building Code. The American Institute of Steel Construction
Specification (AISC), covering the design of steel buildings.
Building Codes are rules meant to stipulate the minimum standards that must be
followed when a building is being constructed. They must follow these codes to gain
permission for planning and construction from the authorities. The main purpose of a
building code is to secure the health, safety, and overall well-being of its occupants by
ensuring proper standards in the construction and design of buildings. Most countries
and territories have their own building codes set to the general needs of the
stakeholders of their relevant territories. And Bangladesh is no exception.
BANGLADESH NATIONAL BUILDING CODE (BNBC):
The Bangladesh National Building Code (BNBC) was first published in 1993 to
regulate the construction of buildings and maintain and uphold them to certain
standards. Before the code, the only laws pertaining to construction was the Building
Construction Act, enacted way back in 1952, during the Pakistan era. The need for the
Bangladesh National Building Code (BNBC) arose with a sudden growth and
development in the country, which led to a massive real estate boom starting in the
early 90s. The first version was published in 1993.
Techniques used in construction remained stagnant for some time, which resulted in
no changes or amendments in the code for a long while. It also added bureaucracy
which meant that the code would only be enacted as law in Bangladesh in the year
2006, with the amendment in Section 18A of the 1952 Building Construction Act. It
was also at first time amendments were made in the document. Further events and
massive growth in the real estate sector led to massive changes in 2017, where the
major amendments were made to the code to make it more relevant, which we will be
talking about later on in the article.
The Bangladesh National Building Code (BNBC) is overseen by the Housing and
Building Research Institute (HBRI). And they have taken help from the Bureau of
Research Testing and Consultancy (BRTC), Bangladesh University of Engineering
and Technology (BUET), and leading experts in the field to review and update the
code when necessary. This code establishes the minimum standards for construction,
design, material quality, proper usage, maintenance, and location of buildings. The
BNBC is meant to be applied by professionals working with construction projects,
including architects, safety inspectors, structural engineers, interior designers,
environmental scientists, contractors, and lawyers
LOADS
Buildings are subject to horizontal loads due to wind pressure acting on the buildings.
Wind load is calculated as per IS 875(Part III)-1987. The horizontal wind pressures
acting on vertical external walls and the exposed area of the buildings. Some of the
pressure acting on exposed surfaces of structural walls and columns is directly resisted
by the bending of these members. The infill walls act as vertical plates supported at top
and bottom by floor beams, thus transferring the loads at the slab level. The parapet
wall is at the terrace transfers the wind loads to the surface slab by cantilever action.
For simplicity, the wind loads acting on exposed surfaces of a given story are idealized
to be supported by upper and lower floors. begun to be understood, there is still a need
to understand more the nature of wind and its interaction with a tall building, with
particular reference to allowable defections and comfort of occupants.
Total base shear in a given direction shall be determined from the following equation
ZIC
V= w
R
Where V= total base shear
Z=seismic zone co-efficient.
R= response modification co-efficient for structural system.
W= total static dead load.
C= numerical co-efficient given by
1 . 25 s
C= 2
3
T
S= site co-efficient for soil characteristics.
T= fundamental period of vibration in second and determined by
3
T =Ct ( h n ) 4
n
V =F t =∑ F i
i=1
( V −F t ) w x h x
Fx= n
∑ w i hi
n=1
i. Design Specification:
a) Method of design : Ultimate Strength Design
b) At septic tank & water reservoirs :
fc’= 3000 psi ,
fy = 60000 psi
fy = 60000 psi
ii. Standard:
a. For design ACI code was used
b. For calculating Dead Load (DL), Live Load (LL), Earthquake
Load (EQ) and Wind Load (WL) were followed.
c. Simplified load combinations of ACI 318-02 are
U = l.4D
U = l.2D + 1.61L+0.5Lr (Lr =load of roof slab)
U = l.2D + 1.6Lr + (1L or 0.8W)
U=1.2D+1.6W+1L+0.5 Lr
U=1.4D+1.0EQ+1.0L
U=0.9D+1.6W
U=0.9D+1E
Use Combination
SPECIFICATION OF MATERIALS:
The full specifications of the materials for the construction of the building are given
below:
CEMENT:
Cement is Ordinary Portland Cement conforming to the requirements of the Standard
Specifications for Portland cement Type-I. ASTM C-150 r BDS 232: 1993. BNBC 2.4,
5.2.1 unless otherwise specified. Cement was delivered in bags by the manufacturer
with the brand name, type of cement and weight of each bag marked on the bag.
Sample test of cement was done from the laboratory designated by the Engineer for
every consignment of cement. Bulk cement which partially set or which contains
lumps of caked cement was rejected. The use of cement reclaimed from discarded or
used bags was not permitted.
Fig: Cement
BRICK:
General features
Brick is a compressive member
Made from clay
Brick structures are generally known as masonry structures where individual
bricks are bonded with mortar
Fig: Brick structure
Types of brick
Pressed: Have a deep frog in one bedding surface and a shallow frog in
other one
Wire cut: 3 or 4 holes through them constituting up to 25% of the total
volume of the brick
Fig: Different types of brick
Brick dimensions:
General Dimension: 10”x5”x3‟‟
Nominal size: 9.5”x4.5”x2.75”
Nominal size is a fictitious dimension which is considered in
evaluating the quality of brick work
It represents neither the actual dimension (without
plaster/mortar work) nor the overall thickness (with
plaster/mortar work)
WATER:
The water used in mixing and curing concrete was tested by methods described in
AASHTO test Method T-26. Water was clean and free from salt, oil, acid, vegetable or
other substance injurious to the finished product. Water used in construction work was
potable.
WHAT IS ESTIMATION?
Estimate is a calculation of various items of an engineering works so as to know its
approximate cost and quantities of various kinds of materials required with labor
involved for its satisfactory completion.
Estimate is the anticipated or probable cost of work and is usually prepared before the
construction is taken. Enable owner / client, knowledge of the cost involved in
proposed work or projects. Enables him to arrange funds in addition to taking a basic
managerial decision as to whether the work is to be undertaken at all or the proposed
work needs to be modified.
This is done from plans other drawings, specifications etc. on based this, internal
approvals mainly administration and financial are obtained.
Purpose of Estimating
1) To ascertain the necessary amount of money required by the owner to complete the
proposed work.
2) For public construction works, estimates are required in order to obtain
administrative approval, allotment of funds and technical sanction.
5) To assess the requirements of Tools, Plants and Equipment required completing the
work according to the program.
6) To fix up the completion period from the volume of works involve in the estimate.
7) To draw up a construction schedule and program and also to arrange the funds
required according to the programming.
8) To justify the investment from benefit cost ratio. (For ideal investment, this ratio
should be more than one).
DRAWINGS
SPECIFICATION
RATES
DRAWING
PLAN
AT A SCALE OF 1 CM = 1 METRE
DETAILED DRAWINGS
AT A SCALE OF 1 CM = 20 CM
SPECIFICATION
GENERAL SPECIFICATIONS
DETAILED SPECIFICATIONS
RATES
Rates per unit of various items of work include:
The rate of various materials which are used in construction.
Labor wages and categories
Location of work its distance from source of material and cost of transport
Rates can be obtained from P.W.D. schedule of rate book or can be calculated
by “Analysis of Rates” method.
TYPES OF ESTIMATES:
Tk.
92 Breaking of 50 mm down brick chips per %
850.00
cft
Tk. per %
93 Breaking of 20 mm down brick chips
950.00 cft
Tk. per %
94 Breaking of 12 mm (1/2") down brick chips
1,200.00 cft
Tk. per %
95 Breaking of 20 mm down stone chips
2,000.00 cft
Tk. per %
96 Breaking of 12 mm down stone chips
2,200.00 cft
Tk.
97 Placing and removing of shutter for formwork per sft
15.00
Tk.
98 Making steel shutter for formwork per sft
75.00
Tk.
99 Making steel door-window frame and shutter per sft
65.00
Tk.
100 Making fixed steel glazed frame per sft
55.00
Tk.
101 Making steel grill per sft
45.00
Tk.
115 1st class/Picked jhama standard bricks per % 0
8,700.00
nos
Tk. per % 0
116 Automatic Machine made1st class standard bricks
9,000.00 nos
1st class 10 holes machine made 9.5" x 4.5" x 2.75" / 237.5 mm x Tk. per % 0
117
112.5 mm x 68.75 mm size ceramic bricks 18,900.00 nos
9.5" x 4.5" x 2.75"/ 237.5 mm x 112.5 mm x 68.75 mm size machine Tk. per % 0
118
made solid klinker facing bricks 13,500.00 nos
9.5" x 4.5" x 2.75" / 237.5 mm x 112.5 mm x 68.75 mm size 10 hole Tk. per % 0
119
machine made rockface/textured klinker facing bricks 13,500.00 nos
9.5" x 4.5" x 2.75"/ 237.5 mm x 112.5 mm x 68.75 mm size 3 hole Tk. per % 0
120
machine made reinforcing facing bricks 21,500.00 nos
8" x 4" x 2"/ 200 x 100 x 50 mm machine made hard pressed klinker Tk. per % 0
121
facing bricks 19,000.00 nos
8" x 2" x 2"/ 200 x 50 x 50 mm machine made klinker facing red or Tk. per % 0
122
maroon strips 16,000.00 nos
Tk. per % 0
123 200 mm x 62 mm x 16.51 mm machine made clay wall tile red strips
18,500.00 nos
Tk. per % 0
124 200 mm x 62 mm x 12.7 mm machine made clay wall tile beige strips
21,000.00 nos
Tk. per % 0
125 200 mm x 62 mm x 8.9 mm machine made clay wall tile red strips
16,400.00 nos
C8 EARTH/SAND
Tk.
169 Royalty of earth per % 0
1,715.00
cft
Tk. per % 0
170 Royalty of sand
6,000.00 cft
Tk.
171 Royalty of turf per % sft
15.00
Tk. per %
172 Sand (F.M. 0.8)
900.00 cft
Tk. per %
173 Sand (F.M. 1.2)
1,400.00 cft
Tk. per %
174 Sand (F.M. 2.2)
4,500.00 cft
C1
STEEL
0
Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935- Tk.
199 per M.
2006 - B300 and Ratio fy to fu =>1.25 58,000.00
ton
Grade 400(400Mpa / 400N/mm2 ≈ 60900psi/ 60 Grade), BDS-6935- Tk. per M.
200
2006, B400: and ratio fy to fu => 1.25 60,500.00 ton
Tk. per M.
201 M.S sheet
60,500.00 ton
Tk. per M.
202 M.S. angle, T and Z-section, Channel etc.
55,000.00 ton
FIG:3D VIEW
FIG: EAST ELEVATION
FIG: WEST ELEVATION
FIG: NORTH ELEVATION
FIG: SOUTH ELEVATION
FIG: SECTION(A-A)
FIG: SECTION BB
FIG: GROUND FLOOR PLAN
CHAPTER 4
ESTIMATAION AND COSTING
……………………………………………………………………
………….……EXCEL SHEET………………
CHAPTER-5
CONCLUSIONS:
A huge number of building estimation and costing (from five-storied to
twenty) have been undertaken in the major cities of Bangladesh now a
days. All of the building estimation includes some elements in common
such as drawing, design, financial matters, estimating and legal
considerations. The project should adhere to zoning and building code
requirements. Building codes are legal documents that provide a means
to safeguard life as well as protect the public welfare through regulating
the design, construction practices, construction material quality location,
occupancy, and maintenance of buildings and structures. In this study all
collected data were analyzed and selected problems were compared on
the basis of practical situation, ACI Code, standard books, google
information or other research paper & newspapers.
RECOMMENDATION:
Before starting the construction work, the engineer must be sure about all
steps of the project.
The workers have to be skilled & well concerned about their jobs.