CRS Balance works in details with Completion & TDC updated as on 19/02/2021

Deployed Number of
Sl. No. Item Unit Total Comp. Bal Qty Assigned to TDC Remarks
gang Manpower
1 SED Checking 801 763 38
a AKOLA - SIVNI SHIVAPUR_Connecting Shot Span 8 0 8
742 KM Only (3
b AKOLA - SIVNI SHIVAPUR Span 152 147 5 Abhishek Kamal 18
ladder)
Loop 2-10nos, Loop-
c SIVNI SHIVAPUR YARD Span 141 116 25 24/02/2021
3-15nos
d SIVNI SHIVAPUR - BARSITAKLI YARD Span 148 148 0
e BARSITAKLI YARD Span 82 82 0
f BARSITAKLI - LOHAGAD YARD Span 186 186 0
g LOHAGAD YARD Span 84 84 0
2 Ladder Trolly 801 776 25
connecting shot to
a AKOLA - SIVNI SHIVAPUR_Connecting Shot Span 8 0 8 be done in tower
wagon
b AKOLA - SIVNI SHIVAPUR Span 152 149 3
c SIVNI SHIVAPUR YARD Span 141 127 14
25/02/2021
d SIVNI SHIVAPUR - BARSITAKLI YARD Span 148 148 0
e BARSITAKLI YARD Span 82 82 0
f BARSITAKLI - LOHAGAD YARD Span 186 186 0 Dilip Rajkumar 9 768-775 balance
2nd ladder trolly to
g LOHAGAD YARD Span 84 84 0 be deplyoed after
22nd feb
CRS Balance works in details with Completion & TDC updated as on 19/02/2021
Deployed Number of
Sl. No. Item Unit Total Comp. Bal Qty Assigned to TDC Remarks
gang Manpower
3 Tower Wagon 801 591 210 1. Subjected to
a AKOLA - SIVNI SHIVAPUR Span 160 27 133 Subhas Manish 5 availability of
a1 Overlap towards Akola Nos. 9 0 9 traffic block &
a2 Overlap towards Shivni Shivpur Nos. 9 0 9 working
b SIVNI SHIVAPUR YARD Span 141 66 75 condition of
750-751 KM loop-1
b1 Overlap towards Akola Nos. 2 1 1 tower wagon.
& loop-2 Pending
b2 Overlap towards Shivni Shivpur Nos. 2 1 1 2. Required total
b2 Turn Out towards Akola Nos. 4 2 2 block hour 18hrs
b3 Turn Out towards Barsitakli Nos. 4 2 2 for T/W
b4 Cross-Over towards Akola Nos. 4 2 2 checking(daily
b5 Cross-Over towards Barsitakli Nos. 4 2 2 3hour) of total
c SIVNI SHIVAPUR - BARSITAKLI YARD Span 148 148 0 section.
c1 Overlap towards Shivni Shivpur Nos. 9 9 0
c2 Overlap towards Barsitakli Nos. 9 9 0
d BARSITAKLI YARD Span 82 80 2
d1 Overlap towards Shivni Shivpur Nos. 2 0 2
d2 Overlap towards Lohagad Nos. 2 2 0
d2 Turn Out towards Sivni Shivpur Nos. 1 1 0
d3 Turn Out towards Lohagad Nos. 1 1 0
d4 Cross-Over towards Sivni Shivpur Nos. 1 1 0
d5 Cross-Over towards Lohadag Nos. 1 1 0
e BARSITAKLI - LOHAGAD YARD Span 186 186 0
e1 Overlap towards Barsitakli Nos. 12 12 0
e2 Overlap towards Lohagad Nos. 12 12 0
f LOHAGAD YARD Span 84 84 0
f1 Overlap towards Barsitakli Nos. 2 2 0
f2 Overlap towards Amanwadi Nos. 2 2 0
f3 Turn Out towards Barsitakli Nos. 1 1 0
f4 Turn Out towards Amanwadi Nos. 1 1 0
f5 Cross-Over towards Barsitakli Nos. 1 1 0
f6 Cross-Over towards Amanwadi Nos. 1 1 0
CRS Balance works in details with Completion & TDC updated as on 19/02/2021
Deployed Number of
Sl. No. Item Unit Total Comp. Bal Qty Assigned to TDC Remarks
gang Manpower
4 ATD Remarks 80 4 76
a AKOLA - SIVNI SHIVAPUR_Connecting Shot Nos. 1 0 1 All work completed,
b AKOLA - SIVNI SHIVAPUR Nos. 16 0 16 Y Value remarks is
c SIVNI SHIVAPUR YARD Nos. 13 0 13 being attended, with
27/02/2021
d SIVNI SHIVAPUR - BARSITAKLI YARD Nos. 14 0 14 1 ladder.
e BARSITAKLI YARD Nos. 9 0 9
f BARSITAKLI - LOHAGAD YARD Nos. 19 4 15 Bhaskar Ramkishore 6 2nd ladder trolly to
g LOHAGAD YARD Nos. 8 0 8 be beplyed after
5 Remarks/Deficiencies 38.89 2.00 36.89
a AKOLA - SIVNI SHIVAPUR_Connecting Shot TKM 0.40 0.00 0.40
two additional
b AKOLA - SIVNI SHIVAPUR TKM 6.25 0.00 6.25 ladder to be
deployed
27/02/2021
c SIVNI SHIVAPUR YARD TKM 6.26 0.00 6.26
d SIVNI SHIVAPUR - BARSITAKLI YARD TKM 7.98 0.00 7.98
e BARSITAKLI YARD TKM 3.99 0.00 3.99
f BARSITAKLI - LOHAGAD YARD TKM 10.00 2.00 8.00 Dilip Surendra 12 2 ladder
g LOHAGAD YARD TKM 4.01 0.00 4.01
4 Platform Bond(Earthing) 12 10 2
a SIVNI SHIVAPUR YARD Nos. 6 6 0 Shiv Charan Surendra 4
27/02/2021
b BARSITAKLI YARD Nos. 4 4 0
c LOHAGAD YARD Nos. 2 0 2 Shelter Bond
5 Bonding(All Type) 38.49 38.49 0.00
a AKOLA - SIVNI SHIVAPUR_Connecting Shot TKM 0.40 0.40 0.00
SVW, LHD & BSQ
b AKOLA - SIVNI SHIVAPUR TKM 6.25 6.25 0.00 Shiv Charan Surendra 4
yard completed
c SIVNI SHIVAPUR YARD TKM 6.26 6.26 0.00 Gauraw Manish 12
all structure
d SIVNI SHIVAPUR - BARSITAKLI YARD TKM 7.98 7.98 0.00
completed
e BARSITAKLI YARD TKM 3.99 3.99 0.00
23/2/2020
f BARSITAKLI - LOHAGAD YARD TKM 10.00 10.00 0.00
g LOHAGAD YARD TKM 4.01 4.01 0.00
CRS Balance works in details with Completion & TDC updated as on 19/02/2021
Deployed Number of
Sl. No. Item Unit Total Comp. Bal Qty Assigned to TDC Remarks
gang Manpower
Earth Pit Cover/Improper earth sitting/ Earth
6 5 5 0
fitting
a SIVNI SHIVAPUR YARD LS. 1 1 0
b BARSITAKLI YARD LS. 1 1 0 22/02/2020
c LOHAGAD YARD LS. 1 1 0
d LC 87 LS. 1 1 0
e LC 89 LS. 1 1 0
7 Platform Finishing 3 2 1 Goverdhan
a SIVNI SHIVAPUR YARD LS. 1 1 0
22/02/2020
b BARSITAKLI YARD LS. 1 1 0
c LOHAGAD YARD LS. 1 0 1
8 No. Plate Missing 38.49 38.49 0.00
a AKOLA - SIVNI SHIVAPUR_Connecting Shot TKM 0.40 0.40 0.00
b AKOLA - SIVNI SHIVAPUR TKM 6.25 6.25 0.00
c SIVNI SHIVAPUR YARD TKM 6.26 6.26 0.00
23/02/2020
d SIVNI SHIVAPUR - BARSITAKLI YARD TKM 7.98 7.98 0.00
e BARSITAKLI YARD TKM 3.99 3.99 0.00
f BARSITAKLI - LOHAGAD YARD TKM 10.00 10.00 0.00
g LOHAGAD YARD TKM 4.01 4.01 0.00