Professional Documents
Culture Documents
1
GROUND IMPROVEMENT WORKS IN DFCCIL PROJECT -
A CASE STUDY
PROJECT INFORMATION
2
PROJECT DETAILS
Project :
DFCC Contract Package- CTP-11
Client:
Dedicated Freight Corridor Corporation of India Ltd.
Contractor:
EFRC (Express Freight Railway Consortium) - (TPL,
IRCON, MITSUI & Co. JV)
Scope:
Design and Execution of JNPT–VAITARANA Section of
WDFC- Total length 103km
3
ALIGNMENT PLAN
Scope of work Tunnel
Vasai Vaitarana
EW in filling 88 L cum
EW in cutting 42 L cum
Subgrade 20 L cum
Blanket 10 L cum
VIATARNA
END
DFCC (South)
JNPT
END
PMC-2R
(ZMT) Nilje Kharbao RFO
Legends:
Existing Track -
Proposed DFCC Track -
5
ALIGNMENT PLAN
6
ALIGNMENT PLAN
Kundevahal Detour
JNPT Jn Stn Ch. 13.30 to Ch. 14.90 Kundevahal Viaduct
Ch. 0+577 Ch. 15+148 Tunnel -1 Tunnel -2
Kalamboli Viaduct Kharbao Viaduct
Nilije Crossing Ch 92.420 Ch 94.3700
DFCC Track Ch. 28+990 Ch. 67+000
Kopar Viaduct
Ch. 51+000
IR Track
JNPT
Ch. -1+276
Datiwali Detour Vasai Detour Kopar Viaduct
ROB - Gawan PhataCh. 11+070.97 Prop Nilje RS Major Bridge 4 Kharbao Jn Stn
ROB - Vahale Dumale Ch. 12+143 Ch. 45.70 to Ch. 48.90 Ch. 82.00 to Ch. 98.625
Ch. 37+928 Nos. TDC : Jul-21 Ch. 72+578 VAITARANA
100.000
102.500
15.000
17.500
20.000
22.500
25.000
32.500
35.000
37.500
40.000
42.500
45.000
27.500
30.000
10.000
12.500
47.500
65.000
67.500
82.500
85.000
50.000
52.500
55.000
57.500
60.000
62.500
70.000
72.500
75.000
77.500
80.000
87.500
90.000
92.500
95.000
97.500
2.500
0.000
5.000
7.500
Chainage
7 7
NTC MOVEMENT
End of
JNPT Yard Nilje Yard Nilje Yard package
Ch. 50
Ch. 60
Ch. 30
Ch. 80
Ch. 20
Ch. 70
Ch. 10
Ch. -1.276 Ch. 37.5 Ch. 69.2 Ch. 101.6
10-Dec’21 15-Mar’21
09-Jan’22 08-Jun’22
May-20
May-21
May-22
Mar-20
Mar-21
Mar-22
Nov-19
Nov-20
Nov-21
Nov-22
Aug-19
Aug-20
Aug-21
Aug-22
Sep-19
Dec-19
Sep-20
Dec-20
Sep-21
Dec-21
Sep-22
Dec-22
Feb-20
Feb-21
Feb-22
Jun-19
Oct-19
Apr-20
Jun-20
Oct-20
Apr-21
Jun-21
Oct-21
Apr-22
Jun-22
Oct-22
Jan-20
Jan-21
Jan-22
Jul-19
Jul-20
Jul-21
Jul-22
Duration
Item Description Unit Scope Start Finish
(Months)
Sleeper Production & RDSO app. Nos. 10,000 2.0 31-Aug-19 15-Oct-19
Laying of track to start for Sec -1 TKm 104.72 6.3 15-Mar-21 10-Dec-21
Laying of track to start for Sec -2 TKm 133.73 5.0 09-Jan-22 08-Jun-22 8
8
GROUND IMPROVEMENT WORKS IN DFCCIL PROJECT -
A CASE STUDY
GROUND IMPROVEMENT
9
NEED GROUND IMPROVEMENT
GI with Grouts/Chemical
Admixtures
CHEMICAL STABILISATION
LIME STABILISATION
DEEP MIXING
JET GROUTING
11
GROUND IMPROVEMENT METHOD - ADOPTED
SOIL TYPE
MARINE CLAY
Soft clay layer <2m Soft clay layer >2m Soft clay layer >2m
12
GROUND IMPROVEMENT WORKS IN DFCCIL PROJECT -
A CASE STUDY
GROUND IMPROVEMENT
STONE COLUMNS
13
GROUND IMPROVEMENT – STONE COLUMN
Design Procedure
Construction Procedure
Confirmatory Testing
14
SUB SOIL PROFILE
Geotechnical Investigation
Soil Investigation @
Vane shear test @
every 250m
every 250m (to obtain
And the cross drainage
in-situ C values)
structure location
15
SUB SOIL PROFILE
16
SUB SOIL PROFILE
Table: Field SPT N values with depth Table: Cohesion values for Laboratory
Test results
17
DESIGN PROCEDURE
FLOW CHART FOR SOFT GROUND TREATMENT
`
Yes
Summarise the Loading from Embankment (Height and Loading Condition)
Summarise the design soil parameters form the Factual Design report
Summarise the Final Stone column arrangement, spacing, stage construction/preloading *1 Need adjust embankment height in consideration of residual settlement, three
height, maintaining time*1 and list the conclusions Summarise the Final PVD arrangement*2, spacing, stage
months after construction
construction height, maintaining time*1 and list the conclusions
*2 Depth of PVD shall be installed up to over consolidation layer
18
DESIGN PROCEDURE
19
DESIGN PROCEDURE
Embankment Geometry & Loading: Proposed Soil Type
Layer Description Thickness (m)
(As per GE:0014)
I Blanket Layer SQ3 0.6
Dead load (Ballast, Rail, Sleeper & Embankment fill) (DL) = 42.6kPa
21
DESIGN PROCEDURE
+
Capacity of the stone column resulting from
increase in resistance offered by the
surrounding soil due to surcharge over it
+
DIAMETER OF STONE COLUMN
Bearing support provided by the intervening
soil between the columns SPACING OF STONE COLUMN
23
DESIGN PROCEDURE
24
CONSTRUCTION PROCEDURE
25
CONSTRUCTION PROCEDURE
Installation Methodology:
Locations are marked for installation
The stone column assembly consists of concentric
cylinders, the outer cylinder having an enlarged lower
section with flights
Once the machine is at location, the assembly is forced
into the ground using high torque equipment, displacing the
soils primarily in the lateral direction. During installation the
base of the assembly is closed
Upon reaching target depth a hydraulic cylinder opens the
base of the assembly, exposing the internal stone feeding
mechanism, and engaging a gearbox that rotates the centre
stone feeding mechanism
26
CONSTRUCTION PROCEDURE
Installation Methodology:
Aggregate is loaded into the upper stone bin, and is fed
out of the base of the assembly as the tooling is extracted
from the ground.
The aggregates are compacted both vertically and
horizontally and the degree of compaction monitored by
real time torque output on the rig computer screen.
Once the stone column is completed, it is verified with
the depth and volume to reach the required torque value.
27
CONSTRUCTION PROCEDURE
28
CONSTRUCTION PROCEDURE
Construction Monitoring:
Once the equipment is assembled, it will be shifted to the
exact location of installation.
Initially trial stone columns are installed to know the exact
amount of torque required for installing 900mm dia columns
against volume v/s depth
The density of column is monitored in real time by the on-
screen torque display in the operators cabin. The real time
onscreen display also monitors depth versus torque
The operators & Engineers will know the initial assessment
of the required torque to produce for the required 900 mm
dia stone column by assessing the aggregate volume in the
hopper using the on-board camera and known measuring
points
29
CONSTRUCTION PROCEDURE
Construction Monitoring:
For a 900 mm diameter stone column, the theoretical
volume of 50mm down aggregate
The excavator bucket volume will be 1.0cu.m and the
telescopic loader bucket volume will be 0.7 cu.m.
Once a bucket full of aggregate is added inside the hopper
with the help of excavator/loader, and by the actual depth
installed, the operator will withdraw the tooling
approximately 900 mm prior to the next bucket of aggregate
being added
The Engineer will note the torque required to feed the
quantity of aggregate in stages over the length of column.
Upon completion of the installation of the first column, the
total number of buckets consumed is noted, and total
volume of aggregate placed for the column is recorded by
Engineer.
30
CONSTRUCTION PROCEDURE
Construction Monitoring:
The torque required to feed the aggregate is also
recorded and the process is repeated
It is expected that by the time 5 test columns are
completed, we will be able to select the required
torque to install columns of the required 900 mm
diameter to meet the design requirements
The ongoing installation is continuously
monitored with the total volume of aggregate
placed per column being recorded and the required
torque used, thus allowing the parameters to be
adjusted as ground conditions changes to ensure
the design requirements are met
Equipment experts will visit regular intervals to
monitor the quality of the stone column
installation.
31
CONSTRUCTION PROCEDURE
32
CONSTRUCTION PROCEDURE
33
CONFIRMATORY LOAD TESTS
Load tests on Stone Columns
Acceptance Criteria
As per IS 15284_Part-1 :
34
CONFIRMATORY LOAD TESTS
Load tests on Stone Columns
The load was applied by operating a hydraulic jack
against a suitable kentledge
The load was applied in intervals of 10% of safe load
(design load)
Settlements were recorded for each load increment
with the help of 4 dial gauges. Settlements were
recorded at every 1, 4, 9, 16, 30 and 60 minutes for
each interval
Next loading increment was applied if the rate of
settlement was less than 0.05 mm or less in first 15
minutes.
The design test load was maintained for a period 24
hours
Each unloading is done in 5 to 6 stages is maintained
till the rebound attained a rate of 1.00 mm in first 15
min
Load-settlement curve was plotted for each test 35
CONFIRMATORY LOAD TESTS
Single column load test- 320kN. Group-Three column load test- 960kN.
Test Load - 320 * 1.50 = 480kN Test Load - 960 * 1.50 = 1440 kN.
Load Settlement Curve for Single Column Load Test Load Settlement Curve for Three Column Load Test
37
CONFIRMATORY LOAD TESTS
Mr. Anurag Sachan – MD ,DFCCIL Mr. NRK Raju – Head Engineering , TPL
Mr. Vivek Gautam – COO , TPL Mr. Ravi Kumar – MD , SARITHA INFRA
39
MD DFCCIL Site Visit
40
Site Photographs
41
GROUND IMPROVEMENT WORKS IN DFCCIL PROJECT -
A CASE STUDY
GROUND IMPROVEMENT
PRELOADING + PVD
42
GROUND IMPROVEMENT – PVD + PRELOADING
Pre-loading height and Time period decided based on the allowable settlements
43
GROUND IMPROVEMENT – PVD + PRELOADING
Design summary of Ground Improvement:
Type of PVD – TechDrain : 100mmx 4mm
Thickness of Clay layer : 8m to 12 m
Grid Pattern : Triangular
Spacing of PVD : 0.9m
Preloading – Depending on Embankment height (6 to 10m)
Time duration – Fixed based on preloading and allowable settlements (3 to 4
months)
44
GROUND IMPROVEMENT – PVD + PRELOADING
PVD
The Installation Rigdrain stitchers, can be
machine, called
either static or vibratory. The static
machines install the drain by pushing the
mandrel evenly into the ground, whereas
the vibratory machines drive the mandrel
with vibratory movement. Vibratory
machines are necessary particularly when
hard ground is to be penetrated. The
installation work of PVDs will be carried by
Saritha Infra.
45
GROUND IMPROVEMENT – PVD + PRELOADING
46
GROUND IMPROVEMENT – PVD + PRELOADING
PVD Installation Procedure
STEP 1: STEP 2:
Remove any debris Place SQ1/Rock dust/Gravelly soil 0.3m
to 0.5m to have proper working platform
movement of equipment for installation
of PVD
47
GROUND IMPROVEMENT – PVD + PRELOADING
PVD Installation Procedure
STEP 3: STEP 4:
PVD Installation Preloading Stage-1
48
GROUND IMPROVEMENT – PVD + PRELOADING
PVD Installation Procedure
STEP 5: STEP 6:
Preloading Stage-2 Final Stage
49
GROUND IMPROVEMENT – PVD + PRELOADING
Field Monitoring Devices:
Casagrande Type Piezometers – 4 Nos each at 5000 sqm area
Settlement Recorders – Plate Type 10 Nos each at 2000 sqm area