Date: 15-03-2021
Physical Status of Civil Work
Sr No. Work Description Location Type UOM Scope Qty Work status Completed % Completion Balance Remarks
Himayat Nagar
Staff Quarter Type-3 (6 Unit) Brickwork in
Nos 6 30%
Progress
2 III
Type-3 (4 Unit) Column 2 lift
Nos 4 20%
casting in progress
4 Tower Wagon and Sliding 200 Mtr. Nos 2 Not Yet Started
7 OHE & PSI Depots OHE & PSI Depots Nos 1 Not Yet Started
Sr No. Work Description Location Type UOM Scope Qty Work status Completed % Completion Balance Remarks
Kinwat
Type-3 (4 Unit) Column Casting
4 40%
in Progress
11 Tower Wagon and Sliding 200 Mtr. Nos 2 Not Yet Started
13 OHE & PSI Depots OHE & PSI Depots Nos 1 Footing Casting in Progress 10%
17 Tower Wagon and Sliding 200 Mtr. Nos 2 Not Yet Started
Administrative Office
18 ADEE Office Nos 1 Not Yet Started
(ADEE/DEE/ADSTE/DSTE)
21 OHE & PSI Depots OHE & PSI Depots Nos 2 Not Yet Started