No. Activity Remarks
Not Yet In Progress Closed
Scaffolding
area for right side,
1 Install scaffold area for Painting at section 2 OLJ X
2nd elevetaion depend tides
Grouting
Demoulding
1 Pile 14 X Finished
2 Pile 20 X Finished
3 Pile 21 X 70% Progress, pin retrieved
Painting
Walkway OLJ (section 1) X
Walkway OLJ (section 3)
85% Progress
1 Piles 8" Walkway (8ea)
(Remaining for Top Coat piles)
Under grating X
Which depend tides X
90% Progress
2 All structures under grating (Beam WF & L) X (Remaining for top coat after piles
walkway)
Status
No. HSE Issue Remarks
Not Yet In Progress Closed
I-Care : 3
PTW : 3
LSR : 1