TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.

TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for entrance steps and ramp with PT Rev. Date NA
Slab Pages 1 of 10

METHOD STATEMENT FOR ENTRANCE STEPS AND RAMP


WITH PT SLAB

PROJECT : (Replace with the project’s name, at location , city name)

CLIENT : (Replace with the client’s name)

MASTER DEVELOPER : (Replace with the master developer’s name)

PMC : (Replace with the PMC’s name)

LEAD CONSULTANT : (Replace with the lead consultant’s name)

SUB-CONSULTANT : (Replace with the sub-consultant’s name)

MAIN CONTRACTOR : (Replace with the main contractor’s name)

SUB-CONTRACTOR : (Replace with the sub-contractor’s name)

TABLE OF CONTENTS
1. REVISION RECORD...............................................................................................................................3
2. PURPOSE...............................................................................................................................................4
3. SCOPE OF WORKS...............................................................................................................................4
4. REFERENCES........................................................................................................................................4
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for entrance steps and ramp with PT Rev. Date NA
Slab Pages 2 of 10

5. DEFINITIONS / ABBREVIATIONS..........................................................................................................4
5.1. Definition.............................................................................................................................................4
5.2. Abbreviations......................................................................................................................................4
6. RESPONSIBILITIES................................................................................................................................4
6.1. Project Manager.................................................................................................................................4
6.2. Construction Manager........................................................................................................................5
6.3. Project Engineer.................................................................................................................................5
6.4. QA/QC Engineer / Inspector...............................................................................................................5
6.5. Surveyor.............................................................................................................................................5
6.6. HSE Engineer/Officer.........................................................................................................................5
6.7. Foremen/ Works Supervisor...............................................................................................................6
7. EQUIPMENTS/ TOOLS / MANPOWER..................................................................................................6
7.1. Equipments / Tools.............................................................................................................................6
7.2. List of Manpower................................................................................................................................6
7.3. List of Materials...................................................................................................................................6
8. PROCEDURE..........................................................................................................................................6
8.1. Filling & Compaction...........................................................................................................................7
8.2. Blinding...............................................................................................................................................7
8.3. Curing&Waterproofing........................................................................................................................7
8.4. Block Work & Curing...........................................................................................................................7
8.5. Waterproofing.....................................................................................................................................7
8.6. Fixing of the Slab Formwork...............................................................................................................8
8.7. Pouring of Concrete............................................................................................................................9
8.8. Curing.................................................................................................................................................9
9. HEALTH, SAFETY AND ENVIRONMENT............................................................................................10
10. ATTACHMENTS....................................................................................................................................10
10.1. Inspection Chck List..........................................................................................................................10
10.1.1. Earthworks...................................................................................................................................10
10.1.2. Concrete......................................................................................................................................10
10.1.3. Masonry.......................................................................................................................................10
10.2. Inspection Test Plan.........................................................................................................................10
10.3. Risk Assessment..............................................................................................................................10
10.4. Technical Data sheet (TDS).............................................................................................................10
10.5. Material Safety Data Sheet (MSDS).................................................................................................10
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for entrance steps and ramp with PT Rev. Date NA
Slab Pages 3 of 10

1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All previous revisions
are hereby superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions
0 First issue

Signature field
Revision
Revision
Number
Date
Prepared by Checked by

Reviewed
By Construction Technical QA/QC MEP Co-
Manager Manager Engineer HSE Officer ordinator Sub-contractor

Approved
By Project
Manager

2. PURPOSE
1. The purpose of this Method Statement is to define the procedure for sequence of works for removing the top
250mm of the casted beam without cutting any existing rebar’s installed followed by cleaning, fixing slab steel and
recasting with the post tension beam/slab.
3. SCOPE OF WORKS
1. This method statement applies to the casting of PT Slabs in Buildings 6C & 6D, Basement Level 1.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for entrance steps and ramp with PT Rev. Date NA
Slab Pages 4 of 10

4. REFERENCES
1. Drawings: ST6C-23B12, ST6C-23B13, ST6D-24B16, ST6D-23B16, ST6D-24B15, ST6D-23B15, ST6C-24B12,
ST6C-24B13, ST-6C-8003, ST6C-8101
2. Technical Specifications: 03300: RCC Works
5. DEFINITIONS / ABBREVIATIONS
5.1.Definition
1. Client -(Replace with clients name)
2. Developer -(Replace with developers name)
3. Consultant -(Replace with consultants name)
4. PMC -(Replace with PMC name)
5. Contractor -(Replace with contractors name)
5.2.Abbreviations
1. Engineer- Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MET - Method Statement
8. MIR - Material Inspection Request
9. MSDS - Material Safety Data Sheet
10. PPE -Personal Protective Equipment
11. PQP -Project Quality Plan
12. PTW -Permit To Work ( Working at Height or enclosed spaces)
13. RA -Hazard Identification and Risk Assessment
14. RFIA - Request for Inspection and Approval
15. TBM - Temporary Bench Mark
6. RESPONSIBILITIES
6.1.Project Manager
1. Ensuring that the project works in his zone are carried out in accordance with Company policies and in accordance
with the requirements of this Quality plan.
2. Ensuring the full compliance of subcontractors with Company Quality policies and with the requirements of this
Quality plan.
3. To ensure that all the equipment required to execute the works according to the construction programme are
available, in good condition, and provide any additional equipment that might be required.
4. To co-ordinate with the Construction Manager, Project Engineer, Safety Engineer, Foreman and Surveyor for a
safe and proper execution of the works.
5. To guide specific attention to all safety measures in co-ordination with the safety officer/engineer.
6.2.Construction Manager
1. Ensure area is ready and safe to start the works.
2. Set up required equipment and plant through discussion with the Project Manager and Project Engineer/Works
Supervisor.
3. Ensure the works are carried out according to the specification, quality and approved shop drawings.
4. Liaise and co-ordinate with the Project Manager for the agreed sequence of works with respect to the construction
programme.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for entrance steps and ramp with PT Rev. Date NA
Slab Pages 5 of 10

5. Allocation of required manpower through co-ordination with the Project Manager.


6. Provide the risk assessments for the works in hand.
7. Provide sufficient and safe access for operatives, trucks and pumps.
8. Take precautionary measures with regards to protecting works from hot weather, wind, rain and sun.
6.3.Project Engineer
1. The engineer shall carry out his duties in a manner that shall be co-ordinated by the project manager on a daily
basis, and shall ensure proper distribution of the workforce and equipment at required locations.
2. To be aware of test frequencies related to the formation level.
3. To control disposal of waste excavated material according to the instructions received from the Project Manager.
4. To co-ordinate with the Safety Officer to maintain safe working and proper housekeeping of the site. To comply
with the safety measures and ensure that all Safety Officer Teams are aware of the same to prevent accident and
loss.
5. To monitor and check all activities and ensure that works shall be carried out according to specifications, quality
and approved drawings.
6. To inform the QC Inspector of the areas ready for inspection.
6.4.QA/QC Engineer / Inspector
1. Ensuring that Consultant/Client inspection requests are implemented.
2. Compilation of all necessary quality control checklists
3. Assisting Consultants during the Inspections.
4. Coordinating with the third party lab regarding tests and results.
5. The control of work performance by means of checking the work before consultants’ inspection and issuing RFIs &
punch lists as necessary.
6. Completion of documentation to verify the work performed.
7. Controlling all inspection activities on-site in line with ITPs.
8. Ensuring that all test equipment including surveying equipment is calibrated and is suitable for use on-site.
6.5.Surveyor
1. To establish benchmarks from agreed reference points, provide required setting out and level markings and follow
up with regular checks.
2. Co-ordinate with the Project Engineer / Foreman and ensure the approved shop drawings/construction drawings
shall be implemented properly.
3. Maintain survey details and reports, periodically check the progressing works and advise the project manager of
any deviation from the drawings.
6.6.HSE Engineer/Officer
1. To ensure implementation of all safety measures related to the nature of works being carried out, and in
accordance with the Project Safety Plan.
2. To ensure that all the persons involved in the works are aware of their responsibilities, and that they have enough
understanding of the safety procedures.
3. The safety officer in co-ordination with the Project Manager shall ensure that all the implemented safety measures
are effective enough to maintain safe working on the site.
4. To maintain continuous inspections of the site activities, advise and train persons on a daily basis to prevent
accidents and personnel injury.
5. To give special concern to housekeeping, and ensure that the site is maintained clean and tidy.
6. To ensure all the relevant safety sign boards for different works are in place.
6.7.Foremen/ Works Supervisor
1. Ensure the works are progressed in the sequence as agreed with the Project Manager.
2. Liaise with the Project / Construction Manager for the allocation of the work force, ensuring adequate manpower is
available.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for entrance steps and ramp with PT Rev. Date NA
Slab Pages 6 of 10

3. Liaise with the site manager to ensure all the required plant / materials are available to construct the works.
4. Full time supervision shall be required to ensure the works are carried out in accordance to specifications, quality
and approved drawings.
7. EQUIPMENTS/ TOOLS / MANPOWER
7.1.Equipment’s / Tools
1. Truck Load Mixer (Concrete supplier)
2. Concrete Pumps
3. Vibrators
4. Hand Tools
5. Grinder
6. Hilti Breaker
7. Hammer & Chisel
8. Wire Brush
9. Air Compressor
7.2.List of Manpower
1. Project Manager
2. Construction Manager
3. Project Engineer
4. QA/QC Inspector
5. Safety Officer
6. Foremen / Work Supervisors
7. Equipment Operators
8. Skilled and unskilled labourers
7.3.List of Materials
1. Formwork
2. Concrete
3. Steel Reinforcement
Note: Quantity of manpower, materials and equipments shall be submitted on the daily progress report.
8. PROCEDURE
Please note that depending on the site conditions either cutting or filling shall be done to form the transition between the
slab levels.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for entrance steps and ramp with PT Rev. Date NA
Slab Pages 7 of 10

8.1.Filling & Compaction


The Slopes shall be formed below the PT Slab as a series of steps as shown below in Figure 1. The width and height of
these steps shall depend on the formwork design drawings.

Each step shall be filled in layers of a maximum depth of 200mm. Each layer shall be tested to 95% of compaction. Once
the layers have been built up to the required level and ITR shall be raised to confirm the alignment and the levels.
Anti-termite Treatment
below the SOG blinding, anti-termite treatment shall be done a few hours before the placement of the blinding concrete.
Care shall be taken to protect the treated soil using polythene sheets.
8.2.Blinding
1. On the polythene sheets level pads shall be made and offered for inspection to the Consultant along with the
complete preparation of concrete placement. Once the approval from the Consultant has been obtained the
concrete shall be placed.
8.3.Curing Waterproofing
2. Once the blinding has obtained its initial setting curing shall start and shall proceed for a day and then after
removing the surface moisture, the approved waterproofing system shall be applied to the blinding.
8.4.Block Work & Curing
1. The area for fixing block works shall be cleaned to remove any sand or debris.
2. 100 x 200 x 400mm size solid blocks shall be used. All blocks shall be fixed after soaking with water.
3. One layer of blocks shall be fixed as a layout and to be approved by the consultant.
4. Once layout approval is obtained the subsequent layers of blocks shall be laid to plumb taking care to align the
vertical joints of alternate courses.
5. Mortar shall be 1 part of cement, 3 parts of black sand.
6. Mortar joints shall be made uniform of thickness between 10mm and 15mm. Full bed and head joints shall be
provided.
7. Flush joints shall be formed for surfaces that will take waterproofing.
8.5.Waterproofing
1. When blocks are dry and ready to receive the water proofing bitumen paint, the Site Engineer shall be notified for
the application paint.
2. Application shall be in accordance with all requirements of work specification and the procedure of the
manufacturer.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for entrance steps and ramp with PT Rev. Date NA
Slab Pages 8 of 10

3. When the waterproofing is dry, backfilling shall commence as described in Section 7.1

DETAIL A

DETAIL B
8.6.Fixing of the Slab Formwork
1. Once the Formation level is ready the formwork for the Post Tension Slab shall be started. The formwork shop
drawings shall be submitted and approval received prior to starting the works. All Safety precautions shall be
followed during the assembly process. Inspections shall be carried out and checklists followed. (See Section 8)
2. Fixing Reinforcement
3. Once the formwork is inspected and approved by the Consultant the placement of the reinforcement for the Post
Tension slab and beams shall commence.
4. The slab / band beam reinforcement consists of a 12mm dia. L-bar and a 12mm Dia
U-bar.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for entrance steps and ramp with PT Rev. Date NA
Slab Pages 9 of 10

The L-bar shall be drilled and grouted, as shown above, using Fosroc Lokfix as per the attached data sheets.

As shown above, the placement of the U-bar shall be done with the slab reinforcement.
5. When the adjacent slab steel is ready to be tied, the beam steel shall be rechecked using the latest shop drawing
and any missing or loose bars shall be tied securely. The Slab reinforcement bars shall be fixed in accordance to
the approved shop drawings and project specifications. The quantity, bar splices, spacing, rebar sizes and bending
shall be verified. The fixing work shall be checked to ensure that all rebars were fixed properly in the proper
location.
6. Side form spacers used shall be concrete block spacers and their sizes shall vary as per concrete cover
requirement of steel. Sufficient bottom concrete spacers should be provided to maintain the concrete cover of
reinforcing bars. The rebars shall be tied manually using tie wires. Enough chair bars shall be provided to maintain
the correct distance between the top and bottom bars. The spacers shall be of sufficient strength to take the live
and loads during the installation and the casting phases.
7. Steel reinforcement shall be fixed for the pile head and the on-grade slab to be cast monolithically.
8. All MEP installations shall begin once the first layer of the reinforcement steel is in place. Requests shall be raised
to check the sizes, locations and levels of Electrical works and Mechanical works embedded items.
9. An air compressor shall be employed to clean the area and remove all the accumulated debris.
8.7.Pouring of Concrete
1. Upon receiving the ready mix concrete the regular sampling and testing procedures shall be followed.
2. Prior to pouring the approved bonding agent concrete or water-cement slurry shall be poured on the beam to act as
a bonding agent. Pouring/ Depositing of concrete shall be done by Contractor’s competent site personnel’s and
workers in accordance to the approved shop drawings and project specifications. Any concrete in the work which
has partly hardened or which has been contaminated with foreign objects shall not be used.
3. When pouring of concrete using concrete pump. Do not exceed 1.5m for vertical drop of concrete to prevent
segregation of concrete. Apply vibrators systematically, sufficient duration and intensity to compact the concrete
thoroughly. Avoid over vibration to prevent the concrete segregation. Maintain one spare vibrators for every three
vibrators used for in case of breakdown. Use ready mix concrete through-out and as per approved supplier and
mixed design by the Consultant.
8.8.Curing
1. Curing and protection of concrete shall comply with the guidelines given in the project specifications. Concrete
protection and curing shall be done in such a manner as to prevent the evaporation of moisture from the concrete
and injury of the surface. Immediately after the concrete has set, curing shall commence. As soon as the concrete
has stiffened sufficiently after not more than 24hrs, the surface shall be covered by absorptive mats of fabric and
kept continuously wet for 7 days. Any curing compound materials used for concrete curing is subject for approval of
the consultant.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for entrance steps and ramp with PT Rev. Date NA
Slab Pages 10 of 10

9. HEALTH, SAFETY AND ENVIRONMENT


10. ATTACHMENTS
10.1. Inspection Check List
10.1.1.Earthworks
1. QA/QC C2-02 Survey Work
2. QA/QC C2-05 Excavation
3. QA/QC C2-06 Backfilling & compaction
10.1.2.Concrete
4. QA/QC C3-01 Blinding
5. QA/QC C3-02 Scaffoldings/ Formworks
6. QA/QC C3-03 Rebar check during fixing
7. QA/QC C3-04 Rebar’s check prior to fixing
8. QA/QC C3-05 MGI Pre-concreting
10.1.3.Masonry
9. QA/QC C4-01 Masonry
10. QA/QC C4-01 MGI Masonry
10.2. Inspection Test Plan
11. ITP 2 Survey
12. ITP 4 Steel Reinforcement
13. ITP 5 Concrete Placement
14. ITP 6 Civil Works Concrete – Finishing & Curing
15. ITP 7 Civil Works Concrete – Concrete & Masonry Works
16. ITP 14 Formworks
17. ITP 24 Concrete Removal
10.3. Risk Assessment
10.4. Technical Data sheet (TDS)
10.5. Material Safety Data Sheet (MSDS)