Professional Documents
Culture Documents
Date 1-31-13
SECTION 2
2.0 Drawings
2.1 General
Page 1 of 5
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 2 Drawings 1-31-2013.docx
2.1.14
2.1.15 Sensors
All sensors must be specified on the controls drawings. These sensors must be shown in the mechanical
drawings to verify clearances.
2.2.2
2.2.3
2.2.4
2.2.5
2.3 Dimensions
2.3.1
2.3.2
2.3.3
2.3.4
2.3.5
2.4.1
Page 2 of 5
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 2 Drawings 1-31-2013.docx
2.5 Detail Identification Format
2.5.1
2.5.2
2.5.3
This Installation drawing must include a plan view and an elevation view. Additional elevation views,
layers and/or sections must be provided as required.
System/equipment installation layout CAD drawings (ie. Both plan & elevation views) must comply with
Manufacturing Facility CAD Requirements (MFCR) or as amended. Deviations from this standard must be
submitted in writing and must be approved by the Chrysler Group LLC Platform Facility Manager. Visit the
MFCR web site to get the latest revision.
A unique layer must be provided in the plan view to record Controls Design information. This layer will
depict the zones of control for WD's, all stops (Emergency and Cycle), and PLC's. Additional controls-
specific information may be recorded in this layer as determined beneficial. This layer must be developed
as the data is defined and kept current through the course of the project.
A unique layer must be provided to record safety requirements and direction determined during Safety
Reviews. This layer will be a location to record important elements necessary to satisfy safety
Page 3 of 5
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 2 Drawings 1-31-2013.docx
requirements and provide a visual representation to supplement Safety Review minutes. This layer must
be developed as the data is defined and kept current through the course of the project.
Completed Installation Drawings must be submitted to Chrysler Group LLC Launch Technician for
approval three (3) weeks prior to shipment of the tooling to the unit plant(s). A Chrysler Group LLC
Launch Technician's signature is required for approval of all Installation Drawings.
2.6.3
2.6.4
2.6.6
The following are the requirements for CAD drawings for AME BIW:
2.7.1.1
All CAD designs must be in CATIA.
The following are the requirements for CAD drawings for AME TCF:
2.7.2.1
Any tooling detail that touches the vehicle must be modeled in CATIA.
2.7.2.2
Any tooling detail that does not touch the vehicle may be modeled in CATIA. It may also be
Page 4 of 5
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 2 Drawings 1-31-2013.docx
modeled in other programs (such as Autocad) if there is a compelling reason ( i.e. much cheaper to
design in another medium for a given supplier).
Equipment integrator(s) must upload all CATIA data into VPM following AME process group requirements
of tool number, file location within VPM and timing. It is the responsibility of AME process group to verify
that all electronic files have been received.
2.8.1
2.8.2
REVISION HISTORY
Revision
Date Number* NAME Description (include pages affected)
1-31-2013 13.01 M. Wesley No updates in this revision
Page 5 of 5
Revision Date: 01/31/2013 Revision: 13.01
File name: DnD Sec 2 Drawings 1-31-2013.docx