Professional Documents
Culture Documents
Place / Date:
2.A new complete rectifier bridge was installed. Before installation it was megged with
500V and had over 550MOhm. It was again megged after installation then with the whole
transformer and cable connection and I had the same values. The rectifier was tested with
the Inverter disabled and correct voltage on the DC-link was confirmed. Inverter was then
enabled and Tunnel thruster no2 was started. Step by step the load was increased until
95% Load. No alarms no faults.
3.Because of the state of the cabinet all components was cleaned, and all connections
checked for damage. I changed the Bender-Unit and the 24V power supplies for both
internal signals and external signals. Both SCI cards are also changed.
Customer Service, Siemens, Industry Solutions Division:
Site Telephone 24/7 e-mail
Norway +47 815 365 24 (24 hrs ) INDUSTRY: systemservice.no@siemens.com
MARINE: marineservice.no@siemens.com
Emergency switchboard:
New Cirquit breaker should be ordered and old one sent in for testing.
Report:
Time of Departure from Siemens: 01 March 2014 H1630
Time of arrival at site: 03 March 2014 H1100 Local time
Time of Departure from site: 07 March 2014 H1400 Local time
Time of arrival at Siemens : 11 March 2014 H1900