11 Mobile Crane Operation
11 Mobile Crane Operation
Method
task/operation being Task Carried assessment: Ongoing
Statement Action by
Sajimon KK assessed: out by? 15 January 09
by When?
Site
Ref No: Rev – 02 – RA – 2009 - Depa Cross reference to N.B. Residual risk:
SSOW/method Other on site The risk left
statement: (Highlight SSOW/Method statement control measures after all control
one below) Ref No: may be required measures have
Page No: due to weather been put in
YES NO M/S 001 conditions/other place – see
Risk Persons at risk reasons at time risk matrix at
severity of footer:
E C P Oth
(before task/operation:
Activity/ Significant ers
controls Control measures Work must not
Operation hazard
are in required: start until the
place) risks have
been assessed:
Fall of High Yes Yes Yes Prior to the Make sure mobile Project Site Engineer
11 Materials commencement crane is operated by Manager
of the activity competent person. Supervisor
Construction
Mobile Make sure mobile Manager Foreman
Crane crane is inspected
Operation and certified by third Site Manager Charge hand
Collapse High Yes Yes Yes party approved by
Dubai Municipality. Project Crane
Engineer Operators
Ensure rigger is
Humidity / Medium Yes Yes Yes highly trained and
Heat competent.
Ensure heavy
equipment operator
has the proper
license from the
traffic department.
Certified slingers to
be used for hooking
up.