You are on page 1of 3

TASK RISK ASSESSMENT

ENGINEERING KINETICS (PVT) LTD


TASK TITLE: Naimat Phase-V Expansion Project Date: 27-11-2014
Activity: Lifting & Assembling through Crane TRA.No.007. EKL
Location: Naimat Phase-V Expansion Project (Green Field area)
Description: offloading of Containers (Camp/Site Office/Workshop)
RISK

Y/NALARP
EVALUATION RESIDUAL
S/No.

HAZARD (Refer to
ACTION TO BE TAKEN
HAZARD CONTROLS RISK
EFFECT Evaluation form)
S P R DESCRIBE ACTION MANPOWER S P R
SPA: Lifting &
Rigging
1. Personal 1. Skilled workforce 1. Ensure the workers involved in the
Supervisor,
Unskilled Workers injury, F 6 8 deployed. activity are trained, qualified and F 3 5 Yes
1. Safety
2. accident competent to carry out the work safely.
Watchman

1. Look out to be deployed for safe


1. Look outs deployment reverse movement.
2. Slow reverse 2. Look out should use reflective vest. SPA: Lifting &
movement. 3. Reverse alarm should be used during Rigging
Personal injury,
3. Reverse alarm reverse movement. Supervisor,
2. Damage to the G 6 7 G 2 3 Yes
Struck with crane functional. 4. Boom should be closed during any Safety
Equipment
4. Defensive driving movement of the crane. Watchman
certified operator 5. Follow the speed limits (10 Km/Hr) as Lookouts.
per UEPL standard.

1. Place crane on leveled/compacted


ground with fully extended outriggers. SPA: Lifting &
Crane collapse due Property 2. Provide wooden pads underneath the Rigging
1. Assess the ground
3. to poor ground damage, float pads of outriggers with area at least Supervisor, Yes
F 5 7 condition prior to lift. F 3 5
condition personal injury 3 times larger than that of float. Safety
4. If the poor ground conditions Watchman
encountered change the location.
1. Never stand between
the load and a barrier. 1. Position of the crane will be controlled
Personnel
2. Place Crane on leveled by supervisor. Certified
injury. /
& compacted ground 2. Follow controls for exclusion zone as Riggers.
Improper Crane damage to light
4. F 6 8 with fully extended out marked on lifting plan. Competent G 3 5 Y
setup pole, panel
riggers on wooden 3.Tool box to share movement Rigging & Lifting
skid, trees &
sleepers. arrangement with crane driver/ Supervisor.
cont. room
operator/lookout/ supervisor
1. Ensure all lifting gears should be third
1. Pre Use inspection of party certified.
SPA: Lifting &
Lifting Collapse, lifting accessories & 2. Inspect the equipment and accessories
Damaged lifting Rigging
Serious equipments. also Check prior to using any lifting
5. gears E 4 7 Supervisor, E 2 5 Yes
personal 2. Check the valid 3rd accessory
Safety
injury/Fatality party certification. 3. Trial lifts to be ensured.
Watchman
4. Ensure proper anchorage with the help
of eye bolt.
Slowly raise / lower the load , Lifting plan Safety
should be available at site Supervisor,
Physical Injury, Lifting plan, Weight of
6. Falling / Slipping G 6 7 Lifting gear certification, trial lift. Rigger, G 2 3
Load Hit with load should be known, Yes
2.Rigging study should be available at job Banks man,
Existing Piping. Trail Lift
site Supervisor
1. Area to be cordoned off with full time
Unnecessary Safety
1.Area cordon off supervision.
7. movement of Personal Injury G 6 7 Supervisor, G 2 3 Yes
2.No parallel activities 2. Stop other activities in that working
personnel Banks man
area.
1.Site/area/location
1. Rigger/signal/outlook man visit site
survey before moving
before moving equipment at site.
equipment at site i.e.
Equipment 2. HSE supervisor will ensure wind speed
Soil condition Rigging Sup,
stuck in muddy limit before starting lifting operation if
Weather 2.Wait till clear visibility (SPA)
8. area due to F 5 7 wind speed exceeds from 25 knots TRA F 3 5 Yes
conditions achieved (in case of wind Crane Opt, HSE
rain, High Wind should be revised.
storm) Sup
speed 3. No lifting if wind speed cross 30 knots
3. Observe plant wind
4. Wind speed Reading should be from
speed limit before any
radio room
lifting operations.
Harnesses are to be worn and lanyards Safety
Ensure all relevant PPE
attached at heights Supervisor,
Working at height Personnel equipment is used at all
9. F 5 7 Greater than 2m or where there is a risk Competent F 3 5 Y
(> 6.0 ft) Injury times.
of slipping & falling. Lifting
Supervisor
Cross reference this task
with all relevant PTW's,
Conduct a permit planning meeting with
Injuries, plans certificates one PI, SPA
SIMPOS E 7 10 stakeholders one day before job E 2 5 Yes
Fatalities day before job execution AA
execution
subject to SIMPOS
operation
GENERAL COMMENTS:
1. TBT will be conducted prior to job start.
2. Unauthorized entry of the person not allowed in work premises.
3. Proper PPE’s are must for all the crew.
4. Stand by vehicle must be present at the site in case of emergency.
5. Adequate cold drinking water readily is available at the site to prevent dehydration.
6. Housekeeping of the area should be done on prior basis before and after completion of job.
NAME OF TEAM MEMBERS Signature RISK ASSISMENT APPROVAL
I’m satisfied that the safeguard put in place will reduce the level of Risk to an acceptable level
Muhammad Asif (Project Manager) and the Task/Action is permitted to proceed.
Kawish Zafar (Rigging & Lifting Supervisor)
Reviewed by: ___FARUKH MALIK_________
Farhat Ali HITRA (HSE Engineer)
Date: ________________________ Time: ____________________
Authorizing
S = Severity; P = Probability, R = Risk
Signatory: _______________ DATE: ________________

You might also like