DETAILED ESTIMATE PLAN SHOWING THE PROPOSED CONSTRUCTION OF A R.C.

C TERRACED ROOF
RESIDENTIAL GROUND FLOOR AND FIRST FLOOR BUILDING IN SURVEY NO:25/1-B, PLOT NO : 10 "RATNA
GARDENS" AT SARKAR KOLLAPATTY-VILLAGE & PANCHAYAT SALEM-TALUK,SALEM-DISTRICT.

NAME OF THE APPLICANT: Smt M.GANDHIMATHI W/O R.MURUGAN


MEASUREMENT
SI.NO NAME OF WORK NOS QUANTITY UNIT
LENGTH(ft) BREATH(ft) DEAPTH(ft)
1 Site Cleaning & leveling

2 Earth work open excavation for foundation.


Footing 1 x 15 5.00 5.50 6.00 2475.00
2475.00 Cft

3 Sand filling with river sand as per standard specifications.


1 x 15 5.00 5.00 0.25 93.75
93.75 Cft

4 P.C.C 1:4:8 concrete using 20 mm stone jelly as per standard specifications.


1 x 15 5.00 5.00 0.50 187.50
187.50 Cft

5 Pre construction anti termite treatment by approved agency as per their specification.
1 x 1 28.25 45.75 - 1292.44
1292.44 Sft

6 Earth filling in Basement and consolidation etc.,


Hall 1 x 1 16.00 16.00 3.00 768.00
Bed 1 x 1 10.00 10.50 3.00 315.00
Kitchen 1 x 1 10.00 10.00 3.00 300.00
Dinning 1 x 1 16.00 8.00 3.00 384.00
Store 1 x 1 4.50 8.00 3.00 108.00
Toilet 1 x 1 5.00 8.00 3.00 120.00
Pooja 1 x 1 4.50 5.00 3.00 67.50
Bed 1 x 1 16.00 10.00 3.00 480.00
Stair 1 x 1 10.00 8.00 3.00 240.00
Portico 1 x 1 16.00 8.00 3.00 384.00
3166.50 Cft

7 P.C.C 1:4:8 concrete using 40 mm stone jelly as per standard specifications.


Hall 1 x 1 16.00 16.00 0.50 128.00
Bed 1 x 1 10.00 10.50 0.50 52.50
Kitchen 1 x 1 10.00 10.00 0.50 50.00
Dinning 1 x 1 16.00 8.00 0.50 64.00
Store 1 x 1 4.50 8.00 0.50 18.00
Toilet 1 x 1 5.00 8.00 0.50 20.00
Pooja 1 x 1 4.50 5.00 0.50 11.25
Bed 1 x 1 16.00 10.00 0.50 80.00
Stair 1 x 1 10.00 8.00 0.50 40.00
Portico 1 x 1 16.00 8.00 0.50 64.00
527.75 Cft

8 R.C.C M25 Grade of concrete using 20mm stone jelly the rate includes the cost of centering and shuttering
Plinth beam (Ground floor)
Allaround 1 x 2 28.25 0.75 1.00 42.38
Allaround 1 x 2 45.75 0.75 1.00 68.63
Cross wall 1 x 2 28.25 0.75 1.00 42.38
Cross wall 1 x 1 10.00 0.75 1.00 7.50
Cross wall 1 x 2 8.00 0.75 1.00 12.00
Cross wall 1 x 1 4.50 0.75 1.00 3.38
Cross wall 1 x 1 10.00 0.75 1.00 7.50
Lintel beam (Ground floor)
Allaround 1 x 2 28.25 0.75 0.75 31.78
MEASUREMENT
SI.NO NAME OF WORK NOS QUANTITY UNIT
LENGTH(ft) BREATH(ft) DEAPTH(ft)
Allaround 1 x 2 45.75 0.75 0.75 51.47
Cross wall 1 x 2 28.25 0.75 0.75 31.78
Cross wall 1 x 1 10.00 0.75 0.75 5.63
Cross wall 1 x 2 8.00 0.75 0.75 9.00
Cross wall 1 x 1 4.50 0.75 0.75 2.53
Lintel beam (FIrst floor)
Allaround 1 x 2 28.25 0.75 0.75 31.78
Allaround 1 x 2 45.75 0.75 0.75 51.47
Cross wall 1 x 2 28.25 0.75 0.75 31.78
Cross wall 1 x 1 10.00 0.75 0.75 5.63
Cross wall 1 x 2 8.00 0.75 0.75 9.00
Cross wall 1 x 1 4.50 0.75 0.75 2.53
Cross wall 1 x 1 10.00 0.75 0.75 5.63
Roof beam (Ground floor)
Allaround 1 x 2 28.25 0.75 1.00 42.38
Allaround 1 x 2 45.75 0.75 1.00 68.63
Cross wall 1 x 2 28.25 0.75 1.00 42.38
Cross wall 1 x 1 10.00 0.75 1.00 7.50
Cross wall 1 x 2 8.00 0.75 1.00 12.00
Cross wall 1 x 1 4.50 0.75 1.00 3.38
Roof beam (First floor)
Allaround 1 x 2 28.25 0.75 1.00 42.38
Allaround 1 x 2 45.75 0.75 1.00 68.63
Cross wall 1 x 2 28.25 0.75 1.00 42.38
Cross wall 1 x 1 10.00 0.75 1.00 7.50
Cross wall 1 x 2 8.00 0.75 1.00 12.00
Cross wall 1 x 1 4.50 0.75 1.00 3.38
Sunshade
W 1 x 7 4.50 2.00 0.25 15.75
Stairacase(Waist Slab) 1 x 1 22.25 3.00 0.42 28.04
Roof Slab (Ground floor) 1 x 1 28.25 45.75 0.50 646.22
Roof Slab (First floor) 1 x 1 28.25 45.75 0.50 646.22
2142.47 Cft

9 Supplying,cutting and tying inposition of steel rods for all reinforcement works.
1 x 1 5.00 1.00 - 5.00 Tone

Providing and laying masonry work with I class moulded brick with CM 1:6 including scaffolding, curing racking out
10
of the joints etc. as per specifications.
Ground Floor
Outer Wall 1 x 1 148.00 0.75 11.50 1276.50
Cross wall 1 x 2 28.25 0.75 11.50 487.31
Cross wall 1 x 1 10.00 0.75 11.50 86.25
Cross wall 1 x 2 8.00 0.75 11.50 138.00
Cross wall 1 x 1 4.50 0.75 11.50 38.81
Cross wall 1 x 1 10.00 0.38 11.50 43.13
staircase 1 x 21 3.00 0.83 0.50 26.15
First Floor
Outer Wall 1 x 1 148.00 0.75 11.50 1276.50
Cross wall 1 x 2 28.25 0.75 11.50 487.31
Cross wall 1 x 1 10.00 0.75 11.50 86.25
Cross wall 1 x 2 8.00 0.75 11.50 138.00
Cross wall 1 x 1 4.50 0.75 11.50 38.81
Cross wall 1 x 1 10.00 0.38 11.50 43.13
Parapet wall 1 x 1 26.00 0.75 3.00 58.50
staircase 1 x 21 3.00 0.83 0.50 26.15
Decdution MD 1 x 2 3.50 0.75 7.00 -36.75
D 1 x 8 3.25 0.75 7.00 -136.50
D1 1 x 2 2.50 0.75 7.00 -26.25
PD 1 x 2 2.50 0.75 7.00 -26.25
MEASUREMENT
SI.NO NAME OF WORK NOS QUANTITY UNIT
LENGTH(ft) BREATH(ft) DEAPTH(ft)
W 1 x 12 3.00 0.75 4.00 -108.00
V 1 x 2 3.00 0.75 2.00 -9.00
AO 1 x 2 4.00 0.75 7.00 -42.00
3866.04 Cft

Plastering the RCC exposed surfaces with CM 1:3 including the cost of hacking surface etc.,complete.In all floors.
11
Ground Floor Outer wall 1 x 1 148.00 - 12.00 1776.00
Hall 1 x 1 16.00 - 16.00 256.00
Bed 1 x 1 10.00 - 10.50 105.00
Kitchen 1 x 1 10.00 - 10.00 100.00
Dinning 1 x 1 16.00 - 8.00 128.00
Store 1 x 1 4.50 - 8.00 36.00
Toilet 1 x 1 5.00 - 8.00 40.00
Pooja 1 x 1 4.50 - 5.00 22.50
Bed 1 x 1 16.00 - 10.00 160.00
Stair 1 x 1 10.00 - 8.00 80.00
Portico 1 x 1 16.00 - 8.00 128.00
First Floor Outer wall 1 x 1 102.50 - 12.00 1230.00
Hall 1 x 1 16.00 - 16.00 256.00
Bed 1 x 1 10.00 - 10.50 105.00
Kitchen 1 x 1 10.00 - 10.00 100.00
Dinning 1 x 1 16.00 - 8.00 128.00
Store 1 x 1 4.50 - 8.00 36.00
Toilet 1 x 1 5.00 - 8.00 40.00
Pooja 1 x 1 4.50 - 5.00 22.50
Bed 1 x 1 16.00 - 10.00 160.00
Stair 1 x 1 10.00 - 8.00 80.00
Portico 1 x 1 16.00 - 8.00 128.00
Parapet wall 1 x 1 26.00 - 3.00 78.00
Decdution MD 1 x 2 3.50 - 7.00 -49.00
D 1 x 8 3.25 - 7.00 -182.00
D1 1 x 2 2.50 - 7.00 -35.00
PD 1 x 2 2.50 - 7.00 -35.00
W 1 x 12 3.00 - 4.00 -144.00
V 1 x 2 3.00 2.00 -12.00
AO 1 x 2 4.00 7.00 -56.00
Ceilling Plastring
Ground Floor
Hall 1 x 1 16.00 16.00 - 256.00
Bed 1 x 1 10.00 10.50 - 105.00
Kitchen 1 x 1 10.00 10.00 - 100.00
Dinning 1 x 1 16.00 8.00 - 128.00
Store 1 x 1 4.50 8.00 - 36.00
Toilet 1 x 1 5.00 8.00 - 40.00
Pooja 1 x 1 4.50 5.00 - 22.50
Bed 1 x 1 16.00 10.00 - 160.00
Stair 1 x 1 10.00 8.00 - 80.00
Portico 1 x 1 16.00 8.00 - 128.00
First Floor
Hall 1 x 1 16.00 16.00 - 256.00
Bed 1 x 1 10.00 10.50 - 105.00
Kitchen 1 x 1 10.00 10.00 - 100.00
Dinning 1 x 1 16.00 8.00 128.00
Store 1 x 1 4.50 8.00 36.00
Toilet 1 x 1 5.00 8.00 - 40.00
Pooja 1 x 1 4.50 5.00 - 22.50
Bed 1 x 1 16.00 10.00 - 160.00
Stair 1 x 1 10.00 8.00 - 80.00
Balcony 1 x 1 16.00 8.00 - 128.00
MEASUREMENT
SI.NO NAME OF WORK NOS QUANTITY UNIT
LENGTH(ft) BREATH(ft) DEAPTH(ft)
6793.00 Sft

12 Painting over one coat of water thinnable cement primer of


approved brand.
Ground Floor Outer wall 1 x 1 148.00 - 12.00 1776.00
Hall 1 x 1 16.00 - 16.00 256.00
Bed 1 x 1 10.00 - 10.50 105.00
Kitchen 1 x 1 10.00 - 10.00 100.00
Dinning 1 x 1 16.00 - 8.00 128.00
Store 1 x 1 4.50 - 8.00 36.00
Toilet 1 x 1 5.00 - 8.00 40.00
Pooja 1 x 1 4.50 - 5.00 22.50
Bed 1 x 1 16.00 - 10.00 160.00
Stair 1 x 1 10.00 - 8.00 80.00
Portico 1 x 1 16.00 - 8.00 128.00
First Floor Outer wall 1 x 1 148.00 - 12.00 1776.00
Hall 1 x 1 16.00 - 16.00 256.00
Bed 1 x 1 10.00 - 10.50 105.00
Kitchen 1 x 1 10.00 - 10.00 100.00
Dinning 1 x 1 16.00 - 8.00 128.00
Store 1 x 1 4.50 - 8.00 36.00
Toilet 1 x 1 5.00 - 8.00 40.00
Pooja 1 x 1 4.50 - 5.00 22.50
Bed 1 x 1 16.00 - 10.00 160.00
Stair 1 x 1 10.00 - 8.00 80.00
Portico 1 x 1 16.00 - 8.00 128.00
Parapet wall 1 x 1 26.00 - 6.75 175.50
Decdution MD 1 x 2 3.50 7.00 -49.00
D 1 x 8 3.25 - 7.00 -182.00
D1 1 x 2 2.50 - 7.00 -35.00
PD 1 x 2 2.50 - 7.00 -35.00
W 1 x 12 3.00 - 4.00 -144.00
V 1 x 2 3.00 2.00 -12.00
AO 1 x 2 4.00 7.00 -56.00
Ceilling
Ground Floor
Hall 1 x 1 16.00 16.00 - 256.00
Bed 1 x 1 10.00 10.50 - 105.00
Kitchen 1 x 1 10.00 10.00 - 100.00
Dinning 1 x 1 16.00 8.00 - 128.00
Store 1 x 1 4.50 8.00 - 36.00
Toilet 1 x 1 5.00 8.00 - 40.00
Pooja 1 x 1 4.50 5.00 - 22.50
Bed 1 x 1 16.00 10.00 - 160.00
Stair 1 x 1 10.00 8.00 - 80.00
Portico 1 x 1 16.00 8.00 - 128.00
First Floor
Ground Floor - 0.00
Hall 1 x 1 16.00 16.00 - 256.00
Bed 1 x 1 10.00 10.50 - 105.00
Kitchen 1 x 1 10.00 10.00 - 100.00
Dinning 1 x 1 16.00 8.00 - 128.00
Store 1 x 1 4.50 8.00 - 36.00
Toilet 1 x 1 5.00 8.00 - 40.00
Pooja 1 x 1 4.50 5.00 - 22.50
Bed 1 x 1 16.00 10.00 - 160.00
Stair 1 x 1 10.00 8.00 - 80.00
Balcony 1 x 1 16.00 8.00 - 128.00
7436.50 Sft
13 Supplying & Fixing Cement mortar using Marble Flooring fininshing 10 mm thick etc,.
Ground Floor
MEASUREMENT
SI.NO NAME OF WORK NOS QUANTITY UNIT
LENGTH(ft) BREATH(ft) DEAPTH(ft)
Hall 1 x 1 16.00 16.00 - 256.00
Bed 1 x 1 10.00 10.50 - 105.00
Kitchen 1 x 1 10.00 10.00 - 100.00
Dinning 1 x 1 16.00 8.00 - 128.00
Store 1 x 1 4.50 8.00 - 36.00
Toilet 1 x 1 5.00 8.00 - 40.00
Pooja 1 x 1 4.50 5.00 - 22.50
Bed 1 x 1 16.00 10.00 - 160.00
Stair 1 x 1 10.00 8.00 - 80.00
Portico 1 x 1 16.00 8.00 - 128.00
First Floor -
Hall 1 x 1 16.00 16.00 - 256.00
Bed 1 x 1 10.00 10.50 - 105.00
Kitchen 1 x 1 10.00 10.00 - 100.00
Dinning 1 x 1 16.00 8.00 - 128.00
Store 1 x 1 4.50 8.00 - 36.00
Toilet 1 x 1 5.00 8.00 - 40.00
Pooja 1 x 1 4.50 5.00 - 22.50
Bed 1 x 1 16.00 10.00 - 160.00
Stair 1 x 1 10.00 8.00 - 80.00
Portico 1 x 1 16.00 8.00 - 128.00
2111.00 Sft
Tiles Work
Ground floor
Toilet(GF & FF) 1 x 2 5.00 8.00 - 80.00
Bath & toilet 1 x 1 4.00 6.00 - 24.00
Wall Tiles Work
Toilet(GF&FF) 1 x 2 26.00 - 7.00 364.00
468.00 Sft

14 Joinery details
MD 1 x 2 3.50 - 7.00 49.00
D 1 x 8 3.00 - 7.00 168.00
D1 1 x 2 2.50 - 7.00 35.00
PD 1 x 2 2.50 - 7.00 35.00
W 1 x 12 3.00 - 4.00 144.00
V 1 x 2 3.00 - 2.00 12.00
443.00 Sft
15 Painting two coats for new wood works such as doors windows etc .
MD 1 x 2 3.50 - 7.00 49.00
D 1 x 8 3.00 - 7.00 168.00
D1 1 x 2 2.50 - 7.00 35.00
PD 1 x 2 2.50 - 7.00 35.00
W 1 x 12 3.00 - 4.00 144.00
V 1 x 2 3.00 - 2.00 12.00
443.00 Sft

16 Weathering course concrete with brick jelly 20 mm with pressed Tiles


1 x 1 28.25 45.75 - 1292.44
1292.44 Sft

17 Electrical Work & Plumbing Work L.S

18 Septic tank & Sump L.S

ENGINEER
ABSTRACT ESTIMATE PLAN SHOWING THE PROPOSED CONSTRUCTION OF A R.C.C TERRACED ROOF
RESIDENTIAL GROUND FLOOR AND FIRST FLOOR BUILDING IN SURVEY NO:25/1-B, PLOT NO : 10 "RATNA
GARDENS" AT KOLLAPATTY-VILLAGE & PANCHAYAT SALEM-TALUK,SALEM-DISTRICT.

NAME OF THE APPLICANT: Smt M.GANDHIMATHI W/O R.MURUGAN


ESTIMATE AMOUNT : RS.1400000.00
SI.NO NAME OF WORK QUANTITY RATE UNIT AMOUNT

1 Site Cleaning & leveling 5,000.00

2 Earth work open excavation for foundation. 2475.00 40.00 Cft 99,000.00

3 Sand filling with river sand as per standard specifications. 93.75 50.00 Cft 4,688.00

4 P.C.C 1:4:8 concrete using 20 mm stone jelly as per standard specifications. 187.50 200.00 Cft 37,500.00

Pre construction anti termite treatment by approved agency as per their


5 1292.44 10.00 Sft
specification. 12,924.00

6 Earth filling in Basement and consolidation etc., 3166.50 15.00 Cft 47,498.00

7 P.C.C 1:4:8 concrete using 40 mm stone jelly as per standard specifications. 527.75 30.00 Cft 15,833.00

R.C.C M25 Grade of concrete using 20mm stone jelly the rate includes the
8 2142.47 40.00 Cft
cost of centering and shuttering 85,699.00

Supplying,cutting and tying inposition of steel rods for all reinforcement


9 5.00 3500.00 Tone
works. 17,500.00

Providing and laying masonry work with I class moulded brick with CM 1:6
10 including scaffolding, curing racking out of the joints etc. as per 3866.04 100.00 Cft
specifications. 386,604.00

Plastering the RCC exposed surfaces with CM 1:3 including the cost of
11 6793.00 15.00 Sft
hacking surface etc.,complete.In all floors. 101,895.00

Painting over one coat of water thinnable cement primer of


12 approved brand. 7436.50 10.00 Sft
74,365.00

Supplying & Fixing Cement mortar using Marble Flooring fininshing 10 mm


13 2111.00 10.00 Sft
thick etc,. 21,110.00
Tiles Work 468.00 10.00 Sft 4,680.00

14 Joinery details
Wooden work(Sal Wood) 443.00 200.00 Sft 88,600.00

15 Painting two coats for new wood works such as doors windows etc . 443.00 180.00 Sft 79,740.00
Weathering course concrete with brick jelly 20 mm with pressed Tiles
16 1292.44 30.00 Sft
38,773.00

17 Electrical Work & Plumbing Work L.S 150,000.00

18 Septic tank & Sump L.S 80,000.00


Total 1351409.00
Say 1400000.00
RUPEES FOURTEEN LAKHS ONLY

ENGINEER
ABSTRACT ESTIMATE PLAN SHOWING THE PROPOSED CONSTRUCTION OF R.C.C TERRACED ROOF RESIDENTIAL
GROUND FLOOR AND FIRST FLOOR BUILDING,AT " RATHNA GARDENS " IN SURVEY NO:24/1G,24/1H, AT, SARKKAR
KOLLAPATTY VILLAGE & PANCHAYAT, SALEM WEST-TALUK,SALEM -DISTRICT.
NAME OF THE APPLICANT: Smt M.GANDHIMATHI W/O R.MURUGAN
TOTAL AREA : 1292.45 SQ.FT ESTIMATE AMOUNT : RS.1800000.00
SI.NO NAME OF WORK QUANTITY RATE UNIT AMOUNT

1 Site Cleaning & leveling 5,000.00

2 Earth work open excavation for foundation. 2475.00 8.00 Cft 19,800.00

3 Sand filling with river sand as per standard specifications. 93.75 16.00 Cft 1,500.00

4 P.C.C 1:4:8 concrete using 20 mm stone jelly as per standard specifications. 187.50 20.00 Cft 3,750.00

Pre construction anti termite treatment by approved agency as per their


5 1292.44 20.00 Sft
specification. 25,849.00

6 Earth filling in Basement and consolidation etc., 3166.50 15.00 Cft 47,498.00

7 P.C.C 1:4:8 concrete using 40 mm stone jelly as per standard specifications. 527.75 26.00 Cft 13,722.00

R.C.C M25 Grade of concrete using 20mm stone jelly the rate includes the
8 2142.47 65.00 Cft
cost of centering and shuttering 139,261.00

Supplying,cutting and tying inposition of steel rods for all reinforcement


9 5.00 2500.00 Tone
works. 12,500.00

Providing and laying masonry work with I class moulded brick with CM 1:6
10 including scaffolding, curing racking out of the joints etc. as per 3866.04 140.00 Cft
specifications. 541,246.00

Plastering the RCC exposed surfaces with CM 1:3 including the cost of
11 6793.00 24.00 Sft
hacking surface etc.,complete.In all floors. 163,032.00

Painting over one coat of water thinnable cement primer of


12 approved brand. 7436.50 36.00 Sft
267,714.00

Supplying & Fixing Cement mortar using Marble Flooring fininshing 10 mm


13 2111.00 35.00 Sft
thick etc,. 73,885.00
Tiles Work 468.00 80.00 Sft 37,440.00

14 Joinery details
Wooden work(Sal Wood) 443.00 65.00 Sft 28,795.00

15 Painting two coats for new wood works such as doors windows etc . 443.00 70.00 Sft 31,010.00
Weathering course concrete with brick jelly 20 mm with pressed Tiles
16 1292.44 100.00 Sft
129,244.00

17 Electrical Work & Plumbing Work L.S 180,000.00

18 Septic tank & Sump L.S 80,000.00


Total 1801246.00
Say 1800000.00
RUPEES EIGHTEEN LAKHS ONLY

ENGINEER