Annex III
Table of Contents
Page
1. INTRODUCTION .............................................................................................................................7
2. SITE SUPERVISOR .........................................................................................................................7
2.1. Responsibilities of the site supervisor ...........................................................................................7
2.2. Accountability of the site supervisor .............................................................................................9
2.3.Limitations of the site supervisor .................................................................................................9
3. PREPARATION AT THE OFFICE .................................................................................................10
3.1. Documents....................................................................................................................................10
3.2. Equipment and Stationery ...........................................................................................................10
4. INVESTIGATION AND PREPARATION AT THE SITE ..............................................................10
5. SETTING OUT .................................................................................................................................11
5.1. Checking of a right angle ............................................................................................................11
5.2. Checking of Measurements .........................................................................................................11
5.3. Checking of Levels ......................................................................................................................12
6. EXCAVATION ..................................................................................................................................12
6.1. Acceptance of work ......................................................................................................................13
6.2. Measurement to be taken .............................................................................................................13
7. FOUNDATION ..................................................................................................................................13
7.1. Foundation in Stone Masonry .....................................................................................................13
7.2. Check List of Stone Masonry Foundation ...................................................................................14
7.3. Acceptance of Work .....................................................................................................................14
8. CONCRETE ......................................................................................................................................14
8.1. Cement .........................................................................................................................................14
8.2. Sand (Fine Aggregate) ................................................................................................................14
8.3. Coarse Aggregate .........................................................................................................................15
8.4. Water ...........................................................................................................................................15
8.5. Concrete Mix ...............................................................................................................................15
9. FORM WORK ..................................................................................................................................20
9.1. Vertical Supporting Forms ...........................................................................................................21
9.2. Horizontal Carrying Forms ..........................................................................................................21
Table of Contents
Page
10. STEEL REINFORCEMENT ............................................................................................................21
10.1. Bending of Reinforcement Bars..................................................................................................21
10.2. Planning and Splicing of Reinforcement Bars ..........................................................................21
10.3. Check List for Concrete Work ....................................................................................................22
11. BACKFILLING ................................................................................................................................23
11.1. Internal Backfilling ...................................................................................................................23
11.2. External Backfilling ...................................................................................................................23
11.3. Checklist for Backfilling ............................................................................................................23
12. HARDCORE .....................................................................................................................................23
13. MASS CONCRETE ..........................................................................................................................24
14. MORTAR ..........................................................................................................................................24
14.1. Lime ...........................................................................................................................................24
14.2. Cement .......................................................................................................................................24
14.3. Sand ...........................................................................................................................................24
14.4. Water ..........................................................................................................................................24
14.5. Cement Mortar ...........................................................................................................................25
14.6. Compo Mortar ............................................................................................................................25
14.7. Precautions in the use of Mortars ..............................................................................................25
15. WALLS ..............................................................................................................................................25
15.1. Walls of Hollow Concrete Blocks ...............................................................................................25
15.2. Bricks Delivered to the Site ........................................................................................................27
15.3. Wooden Walls ............................................................................................................................28
15.4. Check List for Hollow Concrete and Brick Walls ......................................................................28
15.5. Check List for Wooden Walls .....................................................................................................29
16. PLASTER AND POINTING ............................................................................................................29
16.1. Cement Plaster ...........................................................................................................................29
16.2. Compo Plaster ............................................................................................................................29
17. STRUCTURAL STEEL WORK .......................................................................................................29
17.1. Fabrication and Erection ............................................................................................................29
Table of Contents
Page
18. ROOFING AN DCLANDDING .......................................................................................................30
18.1. Galvanized Steel Sheet Roofing and Flashing ...........................................................................30
18.2. Steel Hook Bolts and Nuts .........................................................................................................30
18.3. Roof Fixing ................................................................................................................................30
18.4. Gutters and Downpipes ..............................................................................................................31
19. PAVIOR .............................................................................................................................................31
19.1. Cement tiles shall confirm with ES. CD3. 302 ...........................................................................31
19.2. Work Performance of Tiles Pavior ............................................................................................31
19.3. Wall Tiles ....................................................................................................................................31
19.4. P.V.C. Tiles ................................................................................................................................32
20. CARPENTRY AND JOINERY ........................................................................................................32
20.1. Standards ..................................................................................................................................32
20.2. Materials ...................................................................................................................................32
20.3. Joinery and Carpentry Wood ....................................................................................................32
20.4. Storage Protection and Treatment ............................................................................................33
20.5. Insect Damage ...........................................................................................................................33
20.6. Seasoning of Timber .................................................................................................................33
20.7. Surface Treatment ....................................................................................................................33
20.8. Pressure Impregnation .............................................................................................................33
20.9. Protected Joinery ......................................................................................................................33
20.10. Fabrication and Fixing ............................................................................................................33
20.11. Fabrication ...............................................................................................................................34
20.12. Fixing Joinery ..........................................................................................................................34
20.13. Bedding Joinery.........................................................................................................................34
20.14. Flush Doors ..............................................................................................................................34
20.15. Iron Monger ..............................................................................................................................35
20.16. Cleaning ...................................................................................................................................35
20.17. Position .....................................................................................................................................35
20.18. Check List .................................................................................................................................35
Table of Contents
Page
21. CEILING ...........................................................................................................................................35
22. PAINTING .........................................................................................................................................35
22.1. Work Performance for Painting ................................................................................................36
23. WATER AND SEWER SYSTEM ....................................................................................................36
24. WATER WELL ..................................................................................................................................36
25. WATER SUPPLY LINES ..................................................................................................................36
26. PLUMBER AND SANITARY INSTALLATIONS ..........................................................................37
27. SEWER SYSTEM .............................................................................................................................37
28. SEPTIC TANK AND SOAK AWAY PIT ........................................................................................38
28.1. Measurements to be Taken ........................................................................................................38
28.2. Check List for Water and Sewer System ....................................................................................38
29. ELECTRICAL INSTALLATION ....................................................................................................38
29.1. Internal Electrical Installation ..................................................................................................39
29.2. External Electrical Installation ..................................................................................................39
29.3. Measurements to be Taken ........................................................................................................39
29.4. Checklist for Electrical Installation ...........................................................................................40
30. SITE WORK ......................................................................................................................................40
30.1. Excavation .................................................................................................................................40
30.2. Backfilling and Terracing...........................................................................................................40
31. RETAINING WALLS .......................................................................................................................41
32. ROADS AND FOOT PATHS ............................................................................................................41
33. DRAIN CHANNELS AND CULVERTS ..........................................................................................41
34. FENCING AND GATE .....................................................................................................................42
35. VARIATION ORDERS ....................................................................................................................42
35.1. Programme Change ...................................................................................................................42
35.2. Alteration of Design ...................................................................................................................42
35.3. Excess or Reduction in Quantities .............................................................................................42
35.4. Unforeseen Items ........................................................................................................................42
36. INITIATION OF VARIATION ORDERS ........................................................................................42
37. PREPARATION OF PAYMENT CERTIFICATES .......................................................................42
Table of Contents
Page
S U MMARY .........................................................................................................................................44
FORM – 01 ACQUISTION OF DOCUMENTS ..................................................................................................... 47
FORM – 02 HANDING OVER THE WORK FOR THE CONSTRUCTION ....................................................... 48
FORM – 03 SOIL IDENTIFICATION AND ACCEPTANCE OF EXCAVATED FOUNDATION DEPTHS ....... 49
FORM – 04 CONTROL AND APPROVAL FORMS FOR DIFFERENT CONSTRUCTION STAGES ............... 50
1. INTRODUCTION
These Guidelines for site supervisors is issued in order to ensure a uniform system of supervision of
building construction projects at different sites. It is to be observed mainly when construction works
are carried out by contractors, but can in some ways even be used for construction works carried out
by direct labor and sub-contractors. In these Guidelines, the responsibilities, liabilities and limitations
of the site supervisor are briefly mentioned. The steps to be followed in checking building
construction works are expressed in general terms. Details of construction are specified in the
drawings, the technical specifications the general and special provisions of the contract. The site
supervisor’s duty is to ensure that the construction works are executed in accordance with the contract
requirements. Therefore, in the application of these Guidelines, the details specified in the contact
documents always precede the application and use of it.
2. SITE SUPERVISOR
A site supervisor is either a professional engineer, associate engineer, or engineering aide assigned on
site for supervision of building construction projects. Depending on the size and complexity of
building construction, the designer or the consultant will determine the level of professional
competence required for supervision on site.
The site supervisor shall be appointed before the contract for the construction is signed. The
concerned parties shall be informed in writing on the appointment of the supervisor and whenever he
is changed.
No person having any relationship or business connections with the executing contractors shall be
allowed to supervise the construction works.
2.1.2. Familiarizing him-self with and understanding fully the details in the contract documents
which include the technical specifications, the general provisions, the special provisions
and any other referenced standards.
2.1.3. Inspecting all works done and materials used to make sure that the contractor has
complied with the contract specifications.
2.1.4. Reviewing regularly construction progress schedule and alerting the contractor of possible
delays and consequences.
2.1.5. Arranging periodic and regular site meetings with the designer of the project, the
contractor and the client.
2.1.6. Consulting with the designer on schedule for testing materials and submitting to him detail
field observations on material characteristics with indications on tests required.
2.1.7. Considering and evaluating suggestions and recommendations which may be submitted by
the contractor or the client and reporting them with recommendations to the designer.
2.1.8. Maintaining orderly files of correspondences, minutes of site meetings, change orders,
measurement sheets, test results, and copies of payment certificates.
2.1.9. Keeping a site book and recording in it, for the duration of the project such as the
following and any other matter relevant to the works;
e) Names of the responsible technical staff for the construction of the project.
j) The date of receipt on site by the contractor of any part of designs or modifications
and the persons who delivered them.
n) Comments and clarifications on all matters affecting the execution of the works.
o) And all other matters related to the construction works that have caused delays and
extra expenses or that have helped for the efficient operations and satisfactory
completion of the project.
p) The designer also records in the site book any observations he made and
clarifications he gave on the construction works. Whenever the designer, the supplier
and the supervisor happen to be the same organization then the recording shall be
done by the supervisor appointed by it and the designer.
q) All recordings shall be in Amharic or English and shall be dated and signed.
2.1.10. Keeping a diary or logbook recording daily activates occurrences, etc. in accordance with
Form No. 008.
2.1.11. Taking regular measurements of executed works and preparing payment certificates
regularly as required in the contract.
2.1.12. Submitting construction monthly, quarterly and annual progress reports to Head Office.
2.1.13. Rejecting any work or materials that fail to conform to the contract specifications after the
same are thoroughly assessed, and informing the designer of such an action in advance.
2.1.14. Suspending that portion of work where in his opinion there is an imminent danger to the
safety of the workers, to the safety of the public and to the safety of the works, provided
however such suspension shall obtain the approval of the designer or the consultant.
2.1.15. Accepting works executed and materials delivered on site in conformity with the contract
drawings provisions and technical specifications.
2.1.16. Performing all other duties that may be delegated to him in writing by the designer or the
consultant.
2.1.17. Performing his duties with a professional standard of conduct, ethical behavior, integrity
and honesty.
2.2.6. Failure to fully carry out his duties as specified above and in accordance with contract
requirements.
2.3.5. Authorize the owner to occupy the building in whole or in part before provisional
acceptance formalities are completed.
Before starting work on a new site, the site supervisor shall have an office, documents, equipment and
stationery at the site.
3.1. Documents
4.1. Visual inspection should be made on site in order to obtain data on surface soils, surface water,
slopes, adjacent construction and accessibility to the site. The site should also be checked in
order to determine whether underground utilities may cross it. Available maps showing
underground structures and utilities should be checked to avoid breaking them during
construction. Pits should be dug to make visual inspection of soils in place and to obtain
undisturbed soil samples for laboratory testing whenever deemed necessary.
4.2. The site plan and the layout of buildings and sewer system shall be very carefully checked
especially concerning levels and soil condition.
4.3. If changes are necessary a written report shall immediately be submitted to the designer.
4.4. Area to be cleared off shall be decided upon and measurements taken. Trees within the
foundation shall be cut and rooted up. Permission must be obtained from the local authorities
before cutting trees outside the foundation areas.
4.5. Boarder-lines shall be checked and agreed with local municipality or other relevant offices and
corner stones placed.
4.6. Connection points for water and electricity shall be checked and agreed upon with local
municipality or other concerned offices.
5. SETTING OUT
It is necessary to check that the setting out is done correctly with proper measuring tape and leveling
instrument.
5.1. Checking of a right angle
a. “3:4:5 Method”
PEG-C
b. “Diagonal Method”
4m 5m PEG-A PEG-D
PEG-A PEG-B
3m
PEG-B PEG-C
First, put the corner peg A. Measure 3m from the
corner peg A along one wall and put in peg B. When the four corner pegs A, B, C and D are
Measure than 4m, from, the corner peg A along the placed, check that the distance between peg A
other wall and put in peg C. if the corner angle is and C is equal to the distance between peg B and
right, the distance between peg B and peg C shall be peg D.
5m.
5.2. Checking of Measurements
All measurements shall be taken horizontally. If the ground is sloping use the method shown
below.
First Stage
PEG-3
Check that the leveling instrument is accurate. Find and secure the elevation reference point in
accordance with the survey map. If no reference point exists establish one and fix the elevation
of this reference point going out from one corner of the border lines. The elevation is always
written on the survey map. Going out from the reference point, check that bottom of trenches
and floor levels are according to the elevation shown on the drawings.
Establishing points and preserving of reference points shall be done as shown below.
25
10 Protection of
Wood, Painted Red
5
10
35
Steel PEG embedded
in concrete
20
6. EXCAVATION
Check that the excavation for foundation is executed 20 cm wider than the thickness of the
foundation wall and to the exact depth. Required depth of excavation shall be determined by the
Designer unless the supervisor is delegated for such works.
If the ground is sloping the bottom of the trench shall be excavated according to one of the two
following methods
Dmin
Dmin
Dmin
Excavated materials and foundation depth shall be compared and checked against soil test
report. Excavated soil shall be properly identified in accordance with the specifications.
Remember: The contractor will be paid for excavated quantities in accordance with the
Technical specifications and method of measurement. Final foundation depth shall be checked
and approved by the designer using a proper form.
7. FOUNDATION
Foundation work must be checked very carefully. If the foundation drawings do not correspond with
the conditions on the site, a written report shall immediately be submitted to the designer.
7.1.1. Stone shall be of the type specified. It shall be hard, sound, and free from cracks, decay
and weathering and shall be freshly quarried from an approved quarry. Stone with round
surface shall not be used.
7.1.2. The stone when immersed in water for 24 hours shall not absorb water by more than 5%
of its dry weight when tested.
7.1.3. Stone masonry shall be laid with specified mortar, and with well filled joints. Check that
the stone masonry during execution is kept free from solid and other kind of dirt.
7.1.4. The length of stone shall not exceed three times its height.
Check:
a) Trench clearance
b) Stone quality
c) Mortar quality
Stone used should be compared with the design specification and should be identified among
the following two types of stone.
a) Basaltic stone
b) Hard trachetic stone
Executed works should be checked and accepted by the site supervisor using a proper form. In
case of doubt inform the designer.
8. CONCRETE
8.1. Cement
Cement shall be of specified type and quality and delivered to the site in the manufacturer’s
original sealed bags, fresh not older than six months.
The cement shall be stored in a dry and well ventilated store with a wooden floor which is
raised minimum 20 cm above the ground level.
The cement should be stacked separately and a card bearing date of arrival of the consignment
should be pinned to it.
This would help in using cement in the same order as it arrived, thereby avoiding dead storage.
Cement more than six months old (after production) should be tested to ascertain that it satisfies
the specified requirements.
8.2. Sand (Fine Aggregate)
Fine aggregate shall be clean river or pit sand of approved quality. It should consist of hard,
dense durable uncoated rock fragments. It should not contain harmful amounts of clay, silt, dust,
mica, organic matter, or other impurities to such an extent that either together or separately, they
render it impossible to attain the required properties of concrete when employing normal
proportions of the ingredients. The gradation of fine aggregate should meet the specification
requirements. If there are any doubts about the quality, samples should be sent for testing.
Remember: Before any sand is delivered to the site the quality shall be checked against the
following field tests.
8.2.1. Rub a little sand between the fingers. Stains left on fingers will indicate the presence of
clay impur ities.
8.2.2. Taste of sand shall provide a suitable check for the presence of salts.
8.2.3. Vigorously stir a sample of sand in a glass of water and allow it to rest. Amount of clay
or silt present in it would settle on sand.
8.2.4. Stir a sample in a three percent solution of caustic soda and keep the bottle corked for 24
hours. If the color of liquid turns brown, it indicates the presence of organic matter.
8.3.1. Coarse aggregate shall be crushed basaltic stone or gravel of approved quality.
8.3.2. It shall consist of hard, dense, durable, and uncoated rock fragments.
8.3.3. It shall not contain any clay, soft, thin elongated or laminated pieces and shall be free
from alkali and organic matter.
Remember: Before any coarse aggregate is delivered to the site, the quality shall be
checked and approved at the quarry by the Engineer/Supervisor.
8.4. Water
Water used for mixing concrete should be clean and free from injurious amounts of oils, acids,
alkalies, organic materials or other delitescent substances that significantly affect the hydration
reactions of Portland cement, thereby reducing the strength of the concrete.
If there are any doubts about the quality of the water a sample shall be sent to the designer or
consultant for testing.
In order to attain a condition where the four ingredients are uniformly distributed
through the mass, proper mixing involves effort and requires close inspection.
a) The mixer shall be thoroughly cleaned from hardened concrete and other kind of dirt
before use.
b) The mixer drum must be tight to avoid loss of mortar. The valves must not be
leaking mixing water.
c) The specified mixing time should be carefully adhered to.
d) The mixer must not be overloaded. Check the capacity of the mixer and do not allow
the contractor to mix bigger batches than specified.
e) The tilting type mixer is considered superior because it discharges more quickly,
with less segregation and is easier to keep clean.
f) In charging, the materials should enter the drum rapidly.
g) The blades in the drum must be kept clean. Worn out blades must be replaced.
h) The discharge mechanism must be so designed that segregation does not result in the
act of discharging.
i) Cement, fine and coarse aggregates shall be measured by weight or volume,
depending on what is specified.
The material shall be placed into the mixer in the following order.
a) Half the volume of water
b) Coarse aggregate
c) Fine aggregate
d) Cement
e) The rest of the water
Remember: The water-cement ratio shall always be kept constant.
The following standard mixes (Table 8.5.3a or 8.5.3b may be used in the absence of
approved design mix.
º º
ººººº
······
ººººº · 30 cm
·········
º º º ºº
ºººººººººº
Ø 20 cm
The slump test is made by measuring the number of centimeters (A) which concrete
subsides when a standard conical mold into which concrete subsides when a standard
conical mold into which it has been tamped is removed. The slump test is made on a
Concrete shall, if possible, be transported from the mixer to the point of deposit in
wheel barrows. Concrete older than half an hour shall not be allowed to be used in
the construction unless approved by the designer/supervisor. All placing of concrete
shall start from one end and continue in the same direction with-out any break, in
order to avoid unnecessary joints. Unless special arrangements are made, it is not
allowed to pour concrete from a height of more than 1.5m.
All concrete shall be vibrated with an adequate mechanical vibrator. The vibration
shall be carefully done, but the concrete shall not be over vibrated.
In general, the vibration shall continue until the surface of the concrete is fairly
smooth, where after the vibrator shall be removed slowly and carefully.
B/3
B/3 B
B/3
2-5 cm
Before the casting continues the joint shall be cleaned from foreign matter and
thoroughly watered.
When the casting is finished the concrete shall be kept damp for at least 7 days or as
specified, in order to prevent it from drying out too quickly. The longer the curing
period, the stronger the concrete will be.
For test cubes prepared on site, the forms shall be of wood or steel properly made
with shall be of wood or steel properly made with right angles and right dimensions:
15x15x15 cm.
If the concrete is going to be compacted by hand, the form shall first be filled up to
the half height and the concrete compacted with 20 stamps by a steel bar of 50 cm.
length and 20 mm. diameter. Thereafter, the form shall be completely filled and
compacted as described above, and the top surface shall be smoothed. If the concrete
is compacted by vibrator, the form shall be placed on the vibrator, which is lying on a
plank. Between the plank and the vibrator soft material like jute bag shall be placed.
It is forbidden to dip the vibrator into the concrete. Fill the form with concrete and
vibrate it. Stop the vibration when the top surface is smooth. The form can be filled
and vibrated as described above. The first two days after casting, the test cubes shall
be covered with wet paper or jute bags. After two days the form can be removed and
the cubes kept in water or wet-sand for another 3 days.
During the rest of the curing period, the cubes shall be kept in a proper store and
moistened at regular intervals, the cubes shall be sent to the laboratory in good time
before the testing date and shall be marked with the casting date and the project
address.
Test results shall be checked and evaluated by the designer. Results shall be recorded
and filed using form No.06. One copy each is kept by the supervisor and the
contractor.
9. FORM WORK
Strength with an adequate margin for unexpected loads is a basic requirement for the safety of
both the workmen and the structure itself. If addition to sufficient strength the form must be
sufficiently rigid under the construction loads to maintain the shape called for on the plans.
Tightness of form is essential to prevent loss of mortar with resulting honeycomb. Forms erected
for some time before concreting must be carefully checked to see that lumber shrinkage does not
open up originally tight forms.
The form or at least its lining, must be designed to produce the desired concrete surface texture to
carry out the architectural effect specified.
Forms must be designed so they may be stripped from the hardened concrete easily in order both
to protect the concrete and to reduce labor cost. For the safety of the workmen and the concrete
structure itself its assembly and bracing should be carefully inspected for strength by the
supervisor.
There are two different kinds of forms, vertical supporting and horizontal carrying.
Vertical supporting forms are in general used for walls, columns and tie beams. The form carries
the lateral pressure from the concrete during casting.
Horizontal carrying forms are in general used for suspended slabs and end beams. The forms carry
the load from the concrete until the concrete is strong enough to carry itself.
Forms can be either wooden or steel. Wooden forms for unexposed concrete surface are executed
of sawed boards with sharp edges and of the same thickness, wooden forms for exposed concrete
surface are generally of tongued and grooved boards of the same thickness and free from knots,
holes, cracks and splits.
The contractor/sub-contractor is responsible for the design and the stability of the form
work.
Before any casting of concrete starts, it is necessary to check that the form work has the right
dimensions, is straight, has the correct level is properly done and free from holes and dirt,
the top level of the form shall be at the same level as the top of the finished concrete.
Vertical forms can be removed much earlier than horizontal forms. The specifications must
be checked for the individual case.
The contractor is responsible for the design and stability of the form work.
Before any casting of concrete starts, it is necessary to check that the form work has the right
dimensions, is straight, is in the right level, properly done and free from holes and dirt.
All reinforcement bars shall be of the specified quality. If there are any doubts on the quality, the
Engineer/designer shall order the required tests.
Dimension, length and shape of the reinforcement bars shall be according to the drawings and
specifications.
according to the drawings and firmly bound together with soft annealed wire, diameter 1-2
mm. longitudinal splicing of reinforcement bars shall be done by over-lapping in the
places and manner shown in the drawings and described in the specifications.
Before the casting of concrete starts, all reinforcement bars shall be lifted up, placed and
fixed on precast concrete blocks, in order to get the right thickness of the covering
concrete.
The minimum thickness of concrete cover provided shall be checked against the
requirements of the drawings and specifications.
Mass concrete: the reinforcement bars shall be placed in the middle for mass concrete and
footings.
It is easier to use support of reinforcement as shown below, when the reinforcement shall
be placed in the right level.
Remember, that before any concrete is cast, the reinforcement shall be checked and approved
by the designer or by the supervisor if delegated, using the form No. 04.
Remember to order trial mixes and cube or cylinder tests of the concrete before any
concrete work starts in an area where the quality of the local materials have not been
properly determined.
The frequency of testing shall be agreed upon with the designer/supervisor at the start of
the work.
11. BACKFILLING
All materials used for backfilling shall be of approved quality and free from organic material, such
as pieces of wood, roots, bushes and black cotton soil.
All backfilling shall be well rammed and consolidated, using methods specified in the
specifications.
All internal backfilling shall be done with approved material, if possible with material
excavated on the site.
The backfilling shall be filled in layers not exceeding 20 cm. Each layer shall be well
rammed and consolidated with the addition of water if necessary.
Before the backfilling starts, check that the ground is cleared, free from grass, bushes and
pieces of wood.
All external backfilling around foundation walls and behind retaining walls shall be done
with approved selected material, if possible with material excavated on the site.
The backfilling shall be filled in layers, not exceeding 20cm. up to the ground level. Each
layer shall be well rammed and consolidated. If there are any pipes or electrical cables in
connection with the backfilling, the work shall be executed very carefully, so they do not
break or get damaged.
All trenches and places where backfilling shall be executed shall be clean from grass,
bushes and pieces of wood.
Where roads, foot-paths or parking places are constructed on backfilling the compaction
shall be very carefully done.
12. HARDCORE
Stone for hardcore, shall be of approved quality all stones in the hardcore shall be of
approximately equal size, well rammed and consolidated with the top surface tightened with
crushed stones or gravel and sand.
Remember that the stone quality shall be approved in the quarry. If there are any doubts about the
quality, the designer must be consulted.
All mass concrete shall be of specified thickness and quality with reinforcement if any, placed
according to the drawings and the specifications. Before the casting starts, it is necessary to check
that the hardcore is free from pieces of wood and soil and that the reinforcement is well fixed in its
correct position, all are in accordance with the plans and specifications. Just before casting
concrete, the surface of the hardcore is to be wetted.
All casting shall start from one side and continue without any long breaks in the same direction
until the whole slab is completed.
If there is any slope indicated on the drawing, it shall be executed in the mass concrete as well as
in the paving. If any kind of pavior, such as cement tiles, is prescribed, the finishing of the floor
surface shall be done at the same time when the casting of the mass concrete is done. The type of
surface shall be as prescribed in the drawings and the specifications.
Later application of cement screed shall be avoided. The mass-concrete shall be kept wet for at
least 7 days.
Remember to make test cubes or cylinders where specified and to check that installation in the
floor are done properly.
14. MORTAR
Alternatively, hydraulic lime may be used. Hydraulic lime shall be stored in the same
manner as described for cement.
14.2. Cement
Cement shall be Portland cement.
14.3. Sand
Sand for mortar shall be of quality as described for concrete works.
14.4. Water
Cement mortar normally consists of one part cement to three parts of sand (1:3), measured
by volume, but the specifications should be followed for each particular case.
Compo mortar normally consists of one part cement to two parts of lime to nine parts of
sand (1:2:9) measured by volume. Again the specifications should be followed.
All mortars prepared for masonry works shall be used as soon as possible with the time
limits given below.
Cement mortar shall be used within 30 minutes compo mortar shall be used within 2 hours
of the addition of cement. Partly set and dried mortar should not be re-tempered and used.
In case of masonry work with lime mortar, it is desirable that after a height of about 1.5
meters is reached the masonry work shall be allowed to set for at least two days before
starting further construction over it.
15. WALLS
Class “C” non load bearing units suitable for use as:
- Non-load bearing walls and partitions
- Non-load bearing internal panels in steel framed and reinforced concrete frame
buildings.
Hollow Concrete Blocks shall be free from laminations, cracks and other defects
that would impair the proper setting, strength or permanence of the construction.
They shall be well compacted, properly cured and shall have uniform colour and
texture.
The minimum compressive strength for each class of hollow concrete blocks shall
be as indicated here below, according to ES.C.D3/3D/1973.
When hollow blocks are to be manufactured on the site, the quality of cement and
sand shall be as described for concrete works.
Before any manufacturing in big scale starts, test samples shall be made, cured and
sent for testing.
For every 5 thousand blocks manufactured six samples shall be tested unless a
different frequency of testing is specified by the designer.
The blocks shall be kept moist, at least for seven days. This can be done by
covering the blocks with sand, wet sack cloth or other suitable means and frequent
sprinkling of water to keep the blocks wet during the whole period. The blocks
shall be properly dried before they are used for construction. This is necessary,
because concrete blocks are subject to shrinkage upon drying. The minimum time
for drying under shade shall not be less than 14 days.
Only blocks free from defects shall be used for construction and if damaged blocks
are found in the wall, they shall be replaced with good one at the expense of the
contractor.
The hollow blocks and the walls shall during the execution be kept free from soil
and other kind of dirt.
All joints, vertical as well as horizontal, shall be well filled with proper mortar and
partition walls filled with proper mortar and partition walls shall be bonded to
elevation walls.
It must be checked that the joints as well as the walls are in plumb and level.
Elevation Plan
If the wall is designated as load bearing by the designer, special care must be
taken for the execution of the work.
The thickness of the joints shall not exceed 15mm. Compo mortar shall be used
only above ground level.
They shall be stocked in regular tiers as they are unloaded, for minimum breakage
and defacement. The supply of bricks shall be so arranged that, as far as possible,
at least two days requirements of bricks are available at site at any time. Bricks
selected for use in different situations shall be stocked separately.
Bricks shall be soaked in water for a minimum period of one hour before use.
When bricks are soaked they shall be removed from the tank sufficiently in
advance so that at the time of laying, they are surface dry. Such soaked bricks shall
be stacked on a clean place where they are not spoiled by dirt, earth etc. all brick
works shall be laid in English bond, even and true to line, plumb, level and all
joints accurately kept. All joints vertical as well as horizontal shall be well filled
and the thickness of joints shall not exceed 10mm. Only bricks of the same
dimensions shall be used in the same dimensions shall be used in the same wall.
Partition walls shall be bonded to elevation walls as shown in the fig. below.
All kinds of wood used for construction shall be of the type and dimension required in the
specification and the drawings.
All woods shall be well seasoned, free from major knots, splits and bends.
All wood for construction shall be well protected against rain and stored free from the
ground.
Only wood free from defects shall be used for construction supporting members in the
structure and shall not be joined unless indicated on the drawings. Dimension, placing
and numbers of nails shall be according to the drawings.
15.6. Check List for Magnesium Oxide Board Walls & Ceilings
Plaster is divided in two major groups, cement plaster and compo plaster.
Cement plaster shall be used where water effect is expected such as in toilets, laundries and
external walls.
Compo plaster shall be used in all other cases, unless otherwise specified.
Before any plaster is applied, the wall shall be thoroughly cleaned form dirt and dust.
The wall shall, depending on the material, be kept wet for some time before any plaster is applied.
It is not enough to sprinkle water to the wall just before the plaster is applied. All plaster shall, if
possible, be mixed in a mechanical mixer of approved type.
Where pointing is prescribed, check that it is done in plumb and level, pointing shall be done with
cement mortar.
16.1. Cement Plaster
The quality of material shall be as described for concrete thickness and type of surface in
the specifications and drawings.
16.2. Compo Plaster
For quality of material see 14.1. For mixture, thickness and type of surface, reference to the
specifications and the drawings is important.
Unless specified in the contract specifications, welding shall comply with the requirements of
B.S.449 part 2.
Block bolts and nuts shall comply with B.S. 1976 mild steel electrodes shall comply with the
requirements of B.S.639.
Each weld shall be continuous, sound and without interruption and free of craters.
Immediately after welding slag should be taken away and the weld cleared with
metal brush. The ends of rectangular and square hollow section (RHS) shall be
sealed by welding to prevent ingress of moisture.
17.1.2. Assembly
17.1.3. Erection
During erection, the steel structure shall be securely bolted to plates, channels or
angle cleats. No direct bolting to sides of hollow steel section shall be allowed.
Holes for fixing of electrical fittings, partitions, etc. shall be correctly positioned.
Galvanized-steel sheet roofing and flashing shall comply with ES C. D7.001 and ES C.
D7. 026 for plain and corrugated sheets.
Steel hook bolts and nuts shall be zinc coated, the size and use of which shall be as per the
manufacturer’s instruction.
No person other than workmen fixing roofing shall have access to the area while roofing is
under construction. Fixing of roofing and flashing shall be fully water tight and performed
to the standard of best workmanship.
Galvanized steel sheet roofing and flashing shall be fixed to timber members using chiseler
diamond edge and convex head nails made of mild steel round wires. The steel sheets shall
be fixed to steel members using galvanized steel hook bolts and nuts the use and size of
which shall be as per manufacturers instruction.
Galvanized ribbed sheets shall be fixed to steel and wooden trusses and purlins using hood
bolts and nuts as above. Flashings, aprons, edge trims shall be performed to the required
shapes in galvanized steel sheets..
Fixing holes shall be drilled in crown of corrugations of roofing sheets. Holes shall be
5mm larger in diameter than bolts or screws and not less than 40 mm from edges of sheet.
Sheets shall be laid with and laps not less than 150 mm. Side laps shall be minimum one
and a half corrugations. Sheets shall be laid with upper laps away from prevailing wind.
Gutters and down pipes shall be formed with the specified guage galvanized mild steel flat
sheet from suitable lengths and to shapes shown on the drawings. Gutter hangers and down
pipe supports shall be 2.25 mm anti-rust-painted flat sheet spaced at 1m center maximum,
unless otherwise specified. Joints of gutter shall be overlapped 15cm and welded. The area
around the weld shall be treated with three coats of zinc paint.
19. PAVIOR
Before any paving starts, the mass concretes shall be completely free from standing water.
Unless specified in the contract, slurry of cement and water shall be brushed in the mass
concrete surface immediately before the bedding is laid. The bedding shall be cement
mortar, one part cement to four parts sand, and the slump shall be 2-5cm and over. The
thickness of the bedding shall be 2-3cm. and the tiles shall be gently knocked down into
the bedding so the mortar will be forced up in the joints approximately 5mm.
The joints, which shall be 2-4mm wide, shall be filled with cement mortar, when the
bedding is hard enough (after one day).
Expansion joints shall be executed as indicated on drawings. During the construction time,
for the first 14 days, the complete floor shall be kept wet and be well protected against
damage.
Wall tiles shall be soaked in clean water before laying and taken out just before use. Tiles
shall be bedded with straight joints in cement and sand (1:3) and grouted in white cement.
After completion it should be cleaned properly before approval.
P.V.C. tiles shall be laid on floor screeds with approved glue and in accordance with
manufacturer’s instruction.
Remember: Only tiles free from defects shall be used for the construction. Damaged tiles
found in the pavior shall be replaced with good ones at the contractor’s expense.
20.1. Standards
20.2. Materials
Timber for carpentry and joinery shall be as specified and of the best quality obtained from
an approved source. The timber shall be reasonably straight grained.
Timber shall be purchased immediately after taking over the site and is to be open stacked
for as long as possible before use. Timber as it arrives shall be inspected and any timber
not approved must be removed forthwith.
Timber and assembled wood work shall be protected from rain and sun and stored in such
a way as to prevent attack by termites, insects or decayed fungi.
Timber ready for use shall be free from live borer beetle or other insect attack. Measures
necessary to eradicate insect attact of timber which becomes evident, including the
replacement of timber attacked or suspected of being attacked, shall be approved.
Timber shall be seasoned to a moisture content of not more than 20% for carpentry and
12% for joinery.
Timber shall be treated after matching and before assembling by applying three coats of
approved preservatives to all new surface exposed by cutting.
Fixed joinery which is liable to become bruised or damaged in any way shall be
completely protected until the completion of the construction. Exposed and finished items
shall be removed and or loosened and protected, eg. by polythene bags, while decorations
are being carried out, and afterwards re-fixed.
Actual dimensions of scantlings for both carpentry and joinery shall not vary from the
specified dimensions and shall be uniform throughout. Boards shall hold up to the
specified thickness and timber shall be as long as possible and practicable in order to
eliminate joints. Carpentry work shall be left with sawn surface except where other
finishes are specified. Profile of sections shall not be modified form those shown on
drawings without approval. Where timber need to be extended into a wall, it shall be
thoroughly “brush treated” with approved wood preservative.
20.11. Fabrication
Joinery shall be accurately set out on boards to full size for the information and guidance
of the artisans before commencing the respective work, with all joints, iron work and other
works connected therewith fully delineated. Such setting out must be approved before
joinery is commenced.
Joinery shall be kept and framed together soon after the commencement of the building or
as in practicable, but is not be wedged up or glued until the building is ready for fixing
same. Any portion that warps, winds or develops shakes or other defects within twelve
months after completion of the construction shall be removed and new ones fixed in their
places together with all other related works which may be affected thereby.
Joints are to be made loose where shrinkage is liable to occur and glued where sealed
joints are required.
Glue for load-bearing joints and where conditions are dump must be resin type. Exposed
surface of joinery work shall be wrought and all areas “eased off” by planning and sand
papering to an approved finish.
Beads, fillets and small members shall be fixed with round or oval brades or nails well
punched in and stopped.
Large members shall be fixed with brass screws, the heads let in and pellated to match the
grain.
Grounds for external and internal works shall be in soft wood or tid wood. Holes for
plugging-in grounds must be completely filled with mortar after inserting the grounds.
Grounds for fixing joinery shall be spaced at 500 mm intervals.
20.13. Bedding Joinery
Door and window frames, sills, water bars etc. which are fixed to bricks, blocks or
concrete works by means of grounds, lungs, etc. shall be bedded solid in mastic and
pointed.
Cut ends, shearings and other wood-wastes from all parts of the building must be cleared
out and destroyed or removed as the construction progresses and at completion of the
construction.
Exposed items shall be finally washed with soap or detergent and left clean and sound. At
the time of final inspection of the work, all keys shall be available for verification of the
proper operation of locks.
20.17. Position
Unless otherwise specified, hinges shall be at 3 points, one at center and one each at 200
mm to the center of hinges above the bottom and below the top of the opening leaf.
Locks and handles: 1100 mm above finished floor, unless otherwise specified.
a) Right type of door is fixed in the right place and that the door swings in accordance
with the drawings.
b) Door frames and window frames are fixed straight and in plumb.
c) Hinges, locks, latches and handles are of approved type and properly fixed.
d) Window panels are of the right thickness and properly fixed.
21. CEILING
Material and dimensions shall be according to the specifications and the drawings. Before any
mounting starts, painting of pacts in connection with the ceiling, such as steel guides and walls,
shall be completed.
Check, that the ceiling is cleaned and well fixed when the work is completed.
22. PAINTING
Kind of paints to be used shall be according to the specifications or the designer’s instructions.
Applying of the paint shall be done according to the manufacturer’s instructions.
For painting, only skilled workmen shall be used. All surfaces to be painted shall be clean
form dust and dirt, absolutely dry and free from defects before the painting starts.
All brushes and tins used for the painting shall be clean and free from old paint.
When the painting is completed, the room shall be closed until the paint had dried in order
to prevent dust from sticking to the paint.
Remember: that all electrical appliances, iron and brass works shall be removed before the
painting starts and that they are properly re-fixed when the painting is completed.
The water and sewer system are often neglected by the contractors, therefore, much attention has
to be paid to this part of the construction.
All material delivered to the site shall be according to the specifications and drawings.
Delivered materials shall be checked before the installation starts and damaged materials shall be
rejected.
The water well shall be executed according to the specifications and the drawings and shall, if
possible, be dug during the dry season.
It is important to check very carefully the position of the well, in order to prevent it from being
infected by nearby situated septic tanks, soak away pits and dry latrine. If it is necessary to change
the position inform the designer.
When the digging is completed, a water sample shall be submitted to an approved testing institute
for test.
The masonry work must not be started before the test result is known.
Dimensions and types of pipes and tubes, valves and water tower shall be according to the
specifications and drawings.
All valves shall be buried in the ground at a minimum depth of 30 cm, unless otherwise specified.
All valves shall be placed according to the drawings. Before any backfilling starts, the line shall
be inspected and approved by the site supervisor.
Dimensions and types of pipes, tubes, valves and sanitary ware shall be according to the
specifications and the drawings.
All pipes and tubes to be installed in the floor shall be placed in position, fixed and all joints shall
be checked before the mass concrete is cast. The pipes and tubes shall either be placed in the
hardcore with minimum 10 cm covering layer of sand as shown in figure or in channels in the
floor as indicated on the drawing.
Sand Min 10 cm
All sanitary ware shall be properly fixed in its correct position. Connection between sanitary ware
and sewer system shall always be done with siphon of prescribed type.
All exposed pipes and tubes shall be well cleaned and painted as specified.
Dimensions and types of pipes and inspection pits shall be according to the specifications and the
drawings.
Excavation for sewer lines shall be executed with measurements according to the drawings.
The excavation shall be done in a straight line between the manholes. No pipes shall be laid before
the trench is inspected by the site supervisor.
Unless otherwise specified, the pipes shall be laid on a sand bed with a minimum thickness of 10
cm and in an absolutely straight line with an even slope of minimum 1:100. Covering soil layer
shall be minimum 50 cm.
A full circular section of daylight shall be possible to see when looking through the pipes from
one inspection pit to another.
The joining of concrete to pipes shall always be done with cement mortar and with the joint
completely filled all around.
Inspection pits shall be done according to the drawing. All pipes connected to the inspection pit
shall come approximately on the same level and channel shall be formed in concrete at the bottom
of the pit
When the inspection pits are completed and the pipes are laid, joined and inspected and approved
by the site supervisors, the backfilling can start.
The backfilling can be done with excavated material if it is of good quality and free from stones.
Top soil shall not be used for backfilling.
The backfilling shall be filled in layers not exceeding 20 cm. Each layer shall be well rammed and
consolidated with the addition of water if necessary.
Dimension and type of septic tank and soak away pit shall be according to the specifications and
the drawings.
It is necessary to check very carefully the position of the septic tank and the soak away pit in order
to prevent nearby situated water wells from being polluted. If it is necessary to change the position
inform the designer.
During the construction it must be checked that the level of the overflow pipes between the
different chambers and inlet and outlet pipes are according to the drawing.
All plastering, in and outside, shall be with cement plaster with thickness and mixture according to
specifications and the drawings.
The electrical installation shall be requested from EEPCO or its local representative and no final
payment for the electrical installation shall be passed until a certificate of approval is submitted to
the supervisor. Materials to be used for the installation shall strictly follow the specifications and
the drawings.
It is important to check that the electrical subcontractor has a valid certificate of competence
issued by EEPCO before he starts his work and that he keeps a competent foreman on the site
during the execution of the electrical installation.
It must be checked that the conduits are free from defects and that they are covering the
wires all the way.
It must be checked that all switches and outlets are placed according to the drawings and
that they are properly fixed. Connection of wires shall always be done in junction boxes.
It is necessary to check that all materials used outside, such as switches, junction boxes
and light points, are of specified type.
All external cables shall be placed in concrete or PVC pipes with a minimum dimension of
10 cm and at a minimum depth of 40 cm in the ground, unless otherwise specified.
The excavation shall be done in a straight line between the inspection pits. Inspection pits
shall be constructed every 30 mts at most, unless otherwise specified.
No pipes shall be laid before the trench has been inspected and approved by the site
supervisor.
The pipes shall be laid on a sand bed with a minimum thickness of 10cm.
The joining of the concrete pipes shall be done with cement mortar and with the joint
completely filled all around. Joining of PVC pipes shall be done according to the
manufacturer’s instruction. When the inspection pits are completed and the pipes are laid,
joined, inspected, and approved by the site supervisor, the backfilling can start.
The backfilling can be done with excavated material if it is of good quality and free from
boulders.
Top soil shall never be used as backfilling. The backfilling shall be filled in layers not
exceeding 20 cm. Each layer shall be well rammed and consolidated with the addition of
water if necessary. If vibrating machine is used the thickness of the layer can be 40 cm.
If junction boxes are used, they shall be placed in the inspection pits.
Check:
a) The material delivered to the site;
b) The trenches for cables;
c) The laying and the joining of the pipes;
d) The backfilling of the trenches; and
e) The fixing of all electrical fittings.
Site Clearance
The clearing shall only be done in areas where construction work is going to take place.
The clearing for the buildings shall be done up to 2m from the elevation walls on all sides.
Clearing for roads, footpaths and parking areas shall be done up to 1m from their boundaries.
Permission must be obtained from the designer for clearing outside the above limits.
Roots shall be taken out within the building area and under roads, foot path and parking areas.
All cut trees belong to the client and shall be piled up within the site at a place decided by the site
supervisor.
Roots, bushes and other debris shall be transported away from the site by the contractor.
30.1. Excavation
All top soil shall be excavated separately and piled up within the site at a place decided by
the site supervisor. Removal of top soil shall be done up to 2m outside the building
perimeter.
Excavated material not necessary for backfilling and terracing shall be transported to a
place within the compound or outside as decided by the site supervisor and in accordance
with the contract.
If excavated material is not suitable for backfilling and terracing, the contractor shall bring
material of good quality from outside. Backfilling and terracing shall never be done with
top soil.
31. RETAINING WALLS
Before the casting of concrete footing starts, it is desirable to check that the bottom of the trench is
free from loose soil, roots and pieces of wood.
The stone wall shall be executed with measurements according to the drawing and laid in cement
mortar (1:3) with well filled joints, necessary drainage openings (Weep holes) shall be provided.
All stones shall be of good and approved quality. The stone and the wall shall be kept free from
soil and other kind of dirt during the execution.
Remember: If the drawings indicate expansion joints, this shall be executed both in the footing
and the wall.
Excavation for roads and footpaths shall be executed at least to the bottom level of the hardcore of
the building.
Backfilling for roads and footpaths shall be done with non expansive selected material. If possible,
material excavated on the site shall be used.
The backfilling shall be done in layers not exceeding 20cm. Each layer shall be well rammed and
consolidated with the addition of water if necessary. If vibrating machine is used, the thickness of
the layer can be 40cm. Before the backfilling starts, it is necessary to check that the ground is free
from top soil, grass, bushes, roots and pieces of wood. Stone for hardcore shall be of approved
quality. All stones in the hardcore shall be of approximately equal size, well rammed and
consolidated and the top tightened with crushed stones or gravel.
The thickness of the hardcore shall not be less than specified. The hardcore as well as the top
surface shall be executed with a minimum slop of 1:100 towards the sides.
The top surface shall be executed with material according to the specifications and the drawings.
The flow of surface water shall be studied and the drawings indicating the position of the drain
channels/pipes shall, if necessary be changed by the designer so that they comply with the actual
condition on the site. The drain channels/pipes shall be executed with measurements according to
the drawing and with a minimum slope of 1:200, unless otherwise specified in the sanitary
drawing.
Stone channels shall be executed on a bed of hard-core or well compacted gravel and with joints
and pointing in cement mortar (1:3). Channels of half concrete pipes shall be placed on a well
compacted layer of fine aggregate with a minimum thickness of 10 cm.
The half concrete pipes shall be laid in and joined with cement mortar (1:3).
Soil channels/pipes and culverts shall be constructed in accordance with the plans and
specifications.
Type of fence and gate and area to be fenced shall be as specified in the specifications and the
drawings. Foundation for fence poles shall be done according to the drawings and specifications.
Variation orders occur during construction works for a number of reasons, among which the
following can be listed as the main ones.
Involving:
a) Addition in works or
b) Reduction in works
36.1. Variations for items No. 35.1. and No. 35.2 shall be initiated by the Client and Supervisor
of the project.
36.2. Items No. 35.3 and No. 35.4 shall be initiated by the site supervisor and/or mainly by the
contractor.
36.3. Initiated variation orders shall be submitted for checking and approval by the supervisor or
the Client using the official forms.
36.4. All variation orders shall be checked and approved by the Consultant and Client in
accordance with the procedures set out in the General Conditions of Contract.
37.2. Payment certificates should be prepared by the contractor in sufficient copies as needed.
a) The supervisor
b) Consultant, if there is a contract provision for such supervision.
c) The contractor
d) The Client
a) Arithmetic error
b) Contract prices
c) Contract quantities
d) Contract time
e) Actual measurement sheets
f) Variation orders
g) Supplementary agreements
h) Validity of performance bond
i) Progress reports.
37.5. Since most of the current contract agreements are based on measurements, quantities may
vary, subject to additions or deduction from contract amount as provided in the current
contracts.
37.6. Excess in quantities shall be paid for under a separate title together with variation orders.
On the other hand, deduction for reduction in quality shall be made on the normal payment
certificates.
37.7. Tender discount or rebate is applicable to the main agreement as well as to the variation
orders, unless otherwise specified.
S U M M A R Y
The site supervisor is responsible for the control of works in order to ensure that the project is executed in
accordance with plans and specifications. In general terms, the items of work to be checked are the
following:
a) Earth work
b) Layouts
c) Excavations
d) Foundations
e) Structures
f) Non technological installations, indoors and outdoors.
g) Layout of equipment
h) Erection, installation and connection of service technical networks, indoors and outdoors.
i) Erection, installation and connection of technological networks.
j) Insulation and protection
k) And others, such as windows, doors, flooring, ceiling and roofing works with all their details as
specified in the plans and specifications.
a) Earth Work
The compaction shall be checked by means of field and laboratory tests as specified in the contract
specifications.
The layout of the platform, its levels and the grade of slopes shall be checked means of topographic
survey.
b) Layouts
c) Foundations
Check:
Alignment
Dimensions
Foundation bed level and relative moisture
d) Structures
Check:
Check:
Check:
f) Installations
Check;
g) Layout of equipment
Check;
The correct location, alignment and leveling of the equipment in the assigned areas according to the
coordinates indicated in the contract drawings.
h) Insulations
Check:
The site supervisor shall ensure that the terms and conditions contained in the contract for the
execution of the work are dully fulfilled, controlling.
The site supervisor shall pay special attention to the works being done that will remain covered
underground. Proper inspection shall be made for compliance of each work with the specifications.
The site supervisor shall record in the site book all incidences affecting the work during the period of
execution.
The site supervisor shall participate and collaborate on the report on the final technical and
economical evaluation of the investment, furnishing detail information with regard to:
The site supervisor shall participate in the inspection for provisional acceptance of the project.
FORM – 01
SITE : ___________________________________________________
EMPLOYER : ___________________________________________________
CONTRACTOR: ___________________________________________________
SUPERVISOR : ___________________________________________________
This is to acknowledge that I have received the following set of documents concerning the
project.
_________________________________ ________________________________
DATE: ______________________________
FORM – 02
YBEL INDUSTRIAL PLC
HANDING OVER THE WORK FOR THE CONSTRUCTION
PROJECT : ____________________________________________________
EMPLOYER : ____________________________________________________
CONTRACTOR : ____________________________________________________
SUPERVISOR : ______________________________________________
The contractor hereby acknowledges the taking over of the work with all its explanation clearly
defined in the specification and drawings.
The contractor also acknowledges that the completion date of the said work counts as from the
date mentioned above within the terms and conditions of the contract.
In witness thereof this document has been signed by all present in six copies one of which for
the investor, one for the supervisor, one for the contractor
___________________________________ _______________________________
___________________________________ _______________________________
For WVE For the Contractor
Witness: ____________________
____________________
____________________
FORM – 03
YBEL INDUSTRIAL PLC
PROJECT : _____________________________________________________
SITE : _____________________________________________________
EMPLOYER : ____________________________________________________
CONTRACTOR : _____________________________________________________
SUPERVISOR : _______________________________________________
FORM – 04
PROJECT : ___________________________________________________
SITE : ___________________________________________________
EMPLOYER : ____________________________________________________
CONTRACTOR : ___________________________________________________
SUPERVISOR : ______________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
2. ______________________________________________
3. ______________________________________________
4. ______________________________________________
NB. All the construction stages listed in the construction schedule should be checked and approved
by using this form.
Date ________________________
FORM – 05
PROJECT : ___________________________________________________
SITE : ___________________________________________________
EMPLOYER : ____________________________________________________
CONTRACTOR : ___________________________________________________
SUPERVISOR : ___________________________________________________
REQUIRED TEST
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
APPROVED BY : ___________________________________________________
DATE: __________________________
FORM – 06
PROJECT : ___________________________________________________
SITE : ___________________________________________________
EMPLOYER : ____________________________________________________
CONTRACTOR : ___________________________________________________
SUPERVISOR : ___________________________________________________
APPROVED BY : _____________________________________________
FORM – 07
YBEL INDUSTRIAL PLC
(2) Project ________________________ (3) Week From _____________ to _______ 198 __________
(4) Contractor ____________________ (5) Employer ____________________________________
(6) Consultant ___________________ (7) Contract amount Birr ___________________________
(8) Contract time ____________ days (9) Time Elapsed _______________ (10) Amount Earned
(11) Commencement date ___________________________________________
(12) Amount Earned Birr ____________________________________________
(13) Completion date _______________________________________________
(14) Major items of work in progress, remarks (15) Wheat her fine __________
Rainy
Fair
(17) Time Elapsed ___________
(18) Amt. Earned%____________
(19) Amt. Executed% _________
(20) Personnel _______________
Engineers ___________________
Technicians _________________
Foremen ____________________
Time Keepers ________________
Guards ____________________
Electricians _________________
Bar Benders _________________
Chisellers ___________________
Masons ____________________
Carpenters __________________
(16) Materials on site (21) Major Equipment Plumbers ___________________
Plasters _____________________
Painters ____________________
Metal Workers ______________
Laborers __________________
Others ______________________
Total _______________________
________________________________
____________________________ ______________________________
Supervisor
Project
Employer
Contractor
Consultant
Construction Supervisor
Item No. Description of Percentage of Executed Work Percentage of
Work Total
Total ____________________________
Date _____________________________
FORM – 08
YBEL INDUSTRIAL PLC
SITE DIARY
Project : _____________________________________________________________
Site : _____________________________________________________________
Employer : ______________________________________________________________
Contractor : _____________________________________________________________
Consultant : _____________________________________________________________
Site Supervisor : ____________________________________________________________
DATE _________________
8. Remarks: ________________________________________________________________
________________________________________________________________________
________________________________________________________________________
Drawing :________________________
Received: _______________________
Missing: ________________________
FORM - 09
Employer _______________________________________________________________________
Contractor ______________________________________________________________________
Date _______________
I, We _________________________________________________________________________
______________________________________________________________________________
________________________________
Consultant or designer or Supervisor
____________________ _____________________
Contractor Site Supervisor
CC: Client
FORM - 10
YBEL INDUSTRIAL PLC
RESUME OF FACTS AND ACKNOWLEDGEMENTS
DATA
Project ___________________________________________________________________________
Employer _________________________________________________________________________
__________________________ _________________________________
__________________________ _________________________________
__________________________ _________________________________
__________________________ _________________________________
__________________________ _________________________________
1. ___________________________
The Consultant or the Designer or Supervisor
and Approved by
2. ___________________________
The Employer
N.B. This sheet should be prepared in six copies and should be attached next to the cover format of
the variation order.
FORM - 11
YBEL INDUSTRIAL PLC
RESUME OF FACTS AND ACKNOWLEDGEMENTS
DATA
Project ___________________________________________________________________________
Employer _________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_____________________
Employer (Name)
_________________________________
Supervisor (Name)
_________________________________
Contractor (Name)
These quantities are checked against original take off sheets, and the mistakes are accepted as valid
by the designer.
_________________________________________________________________________________
Name
Date: _____________________
N.B. This sheet should be prepared in six copies and should be attached next to the cover format of
the variation order.
FORM – 12-A
YBEL INDUSTRIAL PLC
Previous Payment
No Date Amount ( Birr ) DEDUCTIONS Amount ( Birr )
1. Previous Payment
2. Rebate
3. Retention
4. Penalty
5. Advance Payment
6. Others
Total
Net sum due to the
contractor
VAT 15%
Total
Total
I/we certify that the contractor is now entitled to the sum of Birr __________________________
_______________________________________________________________________________
__________________________ __________________________
Verified by Approved by