Commissioning Check Sheet For Air Distribution System
Commissioning Check Sheet For Air Distribution System
NO.:
SUBCONTRACTOR:
Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Clean all air intake areas, air conditioned areas.
2 Clean all AHUs, FCUs and fans.
3 Open all outlets.
4 Seal all unwanted openings in air path.
5 Check for free rotation of impeller.
6 Set overload protection correctly.
7 Check for tightness of electrical connections.
8 Ensure installation of filters in all units.
9 Clean filters.
10 Check belt tension and lubrication.
11 Start fans.
12 Balance air as per design.
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH
CONTRACT SPECIFICATIONS.