Professional Documents
Culture Documents
TABLE OF CONTENTS
SECTION -1 : EXCAVATION
SECTION -2 : CONCRETING
SECTION -3 : BRICK LAYING AND STONE MASONRY
SECTION -4 : PAVING
SECTION -5 : TERRAZZO AND MARBLE FINISHES OR WORK
SECTION -6 : PLASTERING AND POINTING
SECTION -7 : ROOFING AND WATER-PROOFING
SECTION -8 : RAIN WATER DRAINAGE
SECTION -9 : CARPENTRY, JOINERY AND GLAZING
SECTION -10 : STEEL AND METAL WORK
SECTION -11 : PAINTING AND DECORATING
SECTION – W-1 : EXCAVATION AND BACKFILLING FOR WATER
SUPLY & SEWERAGE SYSTEMS (EXTERNAL)
SECTION – W-2 : WATER SUPPLY AND SANITARY PLUMBING
SYSTEMS, FIXTURES & SEWERAGE
SECTION – E-1 : ELECTRICAL SPECIFICATION
(INTERNAL & EXTERNAL)
Note: All the specification, material and testing will be followed as per MES
Schedule of rate 2014 for schedule items
1
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION – 1
EXCAVATION
1.1 SCOPE:
The scope of the Specification of this Section covers earthwork and special fills
for buildings and structures including Road Structures and Structures for external
Water Supply & Sewerage; trenches for internal utility lines; site leveling;
clearing and grubbing.
The Contractor is presumed to have visited the Site before tendering and have
satisfied himself as to the nature of the soil at site to be excavated, space available
for storage of excavated material to be re-used, and other site and sub-soil
conditions that may affect his work.
Any ancient carvings, relics of antiquity, coins or other curios and treasure trove
etc., which may be discovered or excavated during the progress of the work, are
to remain the property of the Client or the Government as per Law and are to be
handed over to them.
Clearing and grubbing shall consist of removal of top soil & removal of trees,
stumps, roots, grass, etc. Holes left by stumps and roots shall be back-filled with
suitable material and compacted to the satisfaction of the Client. The cleared and
grubbed area shall be dressed, watered and compacted to the satisfaction of the
Client. The excavated material shall be stock-piled into suitable and unsuitable
materials. The suitable material shall be used for backing and the unsuitable and
surplus material shall be disposed of as per Clause 1.7.
1.5 EXCAVATION:
1.5.1 General:
2
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
1.5.3.2 The Contractor shall secure and maintain excavation and keep them
dry and free from water, snow or mud arising from whatever cause.
He shall provide and maintain at site power driven pumps, etc. for
this purpose at his own expense. The water shall be disposed of to
the satisfaction of the local authorities and the Client. Excavated
material shall be kept at a sufficient distance from the trench to
prevent it from falling back and for allowing placing and removing
shoring and form-work. Dewatering of sub-soil water shall be paid
as a separate item.
1.5.3.3 The Contractor shall provide and install all shoring material,
sheeting, timbering, etc. for maintaining excavations and to ensure
safety of the workmen and shall be responsible for any damage or
injury to adjacent permanent work, paving or structure and services.
Shoring and sheeting left in place as per instructions of the Client
shall not form part of excavation item.
1.5.3.4 The Contractor shall dress and compact, as given in Clause 1.6.1
the bottom of all excavations and the ground under concrete beds,
pavings, etc. to the satisfaction of the Client.
1.5.3.5 Before any work is commenced over the excavated areas by the
Contractor, these shall be inspected by the Client and approved by
them. Any work carried out without such inspection or approved
may be rejected and ordered to be removed.
3
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
1.5.3.7 Contractor shall not excavate below the desired levels or beyond
specified dimensions unless so expressly required by Client. Any
unauthorized excessive excavations shall be filled back by the
Contractor suitably using lean cement concrete 1:4:8 as directed by
the Client entirely at Contractor’s expense. Excavation below sub-
soil water level and above sub-soil water level shall be paid under
separate items.
1.6 FILLING:
The selected excavated materials obtained under Clauses 1.5.2 and 1.5.3
shall first be placed and then the materials brought from outside the site
shall be used.
The Contractor shall provide selected granular fill, spread in layers not
exceeding 7” (200-mm) thickness to required lines, levels and grades
including watering and compacting by mechanical means to densities as
mentioned in 1.6.1 above.
4
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Materials: shall be sound, hard, durable stone metal, gravel, sand or other
acceptable granular material of particles of such a size as will wholly pass
a 2” square sieve, and not more than 10% by weight shall pass the No. 200
mesh sieve.
The selected material obtained in Clause 1.4, 1.5.2 and 1.5.3 shall be filled
as specified in Clause 1.6.1 above.
The suitable excavated material having been placed in the proper section of the
work as specified, the surplus materials shall be used in other portions of the
permanent site work required for the project under Contract. Suitable material
that cannot be placed readily in the permanent work and excess suitable material
shall be separately stock-piled at approved locations. Waste material shall be
removed from the site by the Contractor and be disposed of outside the boundary
or as approved by the Client. In case the excess suitable material is declared
surplus by the Client, the same shall be disposed of like waste material.
Dewatering of sub-soil water from excavation of pipe trenches and excavation for
other structures shall be arranged by adequate process of well-pointing, bailing
and/or pumping.
Well pointing shall consist of bore holes, provided with necessary strainers, blind
pipes and pumping machinery, and these shall be of suitable size and depth and
shall be located on both sides of the pipe trench and along the periphery of
foundations to a sufficient depth to keep the excavations clear of sub-soil water
during the process of construction.
All water pumped and drained from the work shall be disposed of in a manner
satisfactory to the Client. The Contractor shall build all drains and do ditching
required in this connection and shall also take necessary precautions against
flooding, at no extra cost to the Client. The Contractor shall be responsible for
5
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
litigations and damages if the water pumped and drained from the work is let in a
private land or property without the consent of the proprietor, and further shall
pay the necessary compensation to the claimants without any obligation to the
Client.
The Client may order, in writing, any or all shoring and sheet piling to be left in
place for purpose of preventing injury to the structures, other property or persons,
whether such sheeting was shown on drawings or placed at direction, or
otherwise. If left in place, such sheeting shall be cut off at the elevation ordered,
in any case at least 18” below the final ground surface. The sheeting remaining in
place as ordered by the Client shall be driven tight and shall be paid for as
separate item.
1.10.1 Material:
Sides and bottoms of all trenches for footings and foundations and
appurtenances; sides and bottoms of trenches for pipelines and
drains within the structures and appurtenances and three feet
outside the structures; sides of all structures and appurtenances to
be buried in earth or fills; bottoms of all floors and under plinth
protection. In case no plinth protection is required to be provided,
a strip three feet wide shall be treated and buried in earth.
1.10.3 Application:
1.10.4 Precautions:
The termite proofers are poisonous. The parts of the bodies of the
persons and eatables should not come in contact with the chemical
whether it is in pure or diluted form, and it should not be inhaled.
6
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The empty containers must be moved from the site and disposed of
safely.
1.11 MEASUREMENTS:
1.11.1 All quantities shall be net, no allowance being made for the work done
beyond the dimensions shown, unless ordered otherwise by the Client.
1.11.2 Clearing and Grubbing shall be measured by the superficial area.
1.11.5 Fill (with materials other than excavated material) shall be measured by
volume.
1.11.6 De-watering of sub-soil water shall be a job item for the entire work.
1.11.7 Shoring and Sheeting Left in Place shall be measured by the actual board
measure of one inch thick board.
1.12.1 The rates and prices shall be full and comprehensive compensation for
everything furnished and done for the accepted work completed as per these
specifications and in all respects. The clauses referenced against the various
payment items shall be deemed to be the principal clauses only, related to that
item.
7
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
104 Earthwork for Site Leveling, as per Clauses 1.5, 1.5.1, 1.5.2
including filling as per Clause 1.6.3 and disposal of material as per
Clause 1.7. Only the quantity of excavation shall be measured for
payment.
8
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION-2
CONCRETING
2.1 SCOPE:
The specification in this section covers mass Concrete, in-situ Reinforced Cement
Concrete specified by nominal proportions, quality-controlled cement concrete of
specified strength, cement concrete under floors and foundations specified by
nominal proportions of mix as well as Pre-cast concrete work of specified mix or
strength.
BS-4449 for Hot rolled plain bar and high yield deformed bar.
BS-4482 for Hard drawn mild steel wire.
BS-4461 for Cold worked steel bar.
BS-4483 for Steel mesh fabric.
BS-4466 for Bending Dimensions and Scheduling of Bars for Reinforcement of
Concrete.
BS-2640 for gas welding.
BS-5135 for metal arc welding.
BS-12 for Ordinary Portland cement.
BS-12 for Rapid hardening Portland cement.
BS-146 for Portland blast furnace cement.
BS-4027 for Sulphate resisting Portland cement.
BS-12 for White or Colored Portland cement.
BS-1370 for Low heat Portland cement.
BS-4246 for Low heat Portland blast furnace cement.
BS-4248 for Super sulphated cement.
BS-1088 for Plywood for formwork (for fair face concrete work).
BS-882 for concrete aggregates.
BS-1200 for fine aggregate for mortars.
BS-1881 for testing of concrete.
BS-812 for testing of aggregate for chlorides.
BS-1377 for testing of aggregate for sulphates.
ASTM C-289 for testing non-reactivity of the coarse aggregate.
BS-3148 for water.
ASTM C-260 for air entraining agents.
BS-5075 for workability agents.
9
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
2.4 MATERIALS:
2.4.1 Cement for concrete and mortar shall be the best Portland cement
of quality conforming to the current British Standard
Specifications for the type of cement specified to be used, and shall
be obtained from a firm approved by the Client. Cement shall be
stored in damp-proof shed and shall be used in the order of its
delivery. Any cement which has deteriorated or has become
contaminated shall not be used and shall be removed immediately
from the site by the Contractor at his own expense. The cement
used for all fair-faced concrete or floors shall be that necessary to
obtain a light shade concrete as approved by the Client. Unless
designated otherwise the cement to be used under this contract
shall be Ordinary (grey) Portland cement conforming to BS-12.
2.4.2 Water: Only clean fresh water free from impurities and deleterious
matter and without excessive salt content shall be used. Where the
water is not obtained from the public supply the Contractor shall
submit at his own expense any analysis, from an approved analyst,
of the water he intends to use in construction, for approval of the
Client.
2.4.3 Sand (Fine Aggregate): The sand shall be clean and gritty from
Chenab and composed of hard siliceous grains and other materials
as approved by the Client. It shall be free from clay, dust, salt, silt
or any organic, alkali or bituminous matter. The materials shall be
well graded and shall all pass through BS Test Sieve measuring
3/16” square, and for reinforced concrete the maximum quantities
of clay, silt and fine dust shall not be more than 3% by weight
when using the test in BS-812 (1967), Clause-13. Sands with more
than 5% fines or clay shall be washed.
10
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The coarse aggregate shall be well graded from the maximum size
specified and shall all be retained on sieve with mesh measuring
3/16” square. For use in reinforced concrete the maximum size of
coarse aggregate shall be as per Table given in Clause 2.8.
11
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The Client shall have the right to require the Contractor at any time to draw
samples of all materials used in reinforced concrete, including steel, from
stockpiles at site or any other location and require the Contractor to test them
himself or get them tested at Contractor’s cost from an approved laboratory. The
Client shall have the right to reject any unsuitable materials which shall be
removed from the site immediately. All testing and sampling shall be done as per
BS., or alternatively the following shall be followed, as may be applicable.
Amount of material
Passing the No. 200 sieve AASHTO T-11.
No aggregate for testing during the production of concrete shall be sampled at the
discharge gates of the bins feeding the weight hopper. The Contractor, at his expense,
12
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
shall provide safe and suitable facilities for obtaining the samples. No concreting work
on the project will be permitted to be done until the Client certify in writing that they give
their approval, following the performance of the necessary tests, to the use of all the
materials involved in making the concrete.
The liquid-tightness test of the liquid retaining structures shall be carried out by filling
and emptying (after test) the structure with the same liquid which the structure is meant
to retain, except that the liquid (other than water, in case of water retaining structures)
shall be provided free of cost to the Contractor. The accepted BOQ rates include costs
for all samples/specimens (concrete cubes/cylinders included), checks, tests, facilities for
workmanship, materials and products, required to be performed at works, field or
approved labs; and replacement/rectification of defective materials/works as required by
the Client.
The stone aggregate shall consist of good, hard, tough broken stone, gravel or
shingle of gauge specified and from an approved source. It shall be free from dirt,
clay, leaves or any organic matter, soft or decayed stone. 1.5” size aggregate shall
be screened to pass wholly through a screen of 1.5” x 1.5” and be all retained on
3/16” x 3/16” square mesh and shall be well graded in between so that not more
than 60% and not less than 30% shall be retained on a screen of 3/4” x 3/4”
square mesh.
13
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Concrete shall be laid when the mix is quite fresh, gently and uniformly in layers
not exceeding 6” (150-mm) in thickness. Each layer shall be thoroughly rammed
and the concrete of the succeeding layer shall be immediately deposited over it.
All the layers forming the required depth of concrete shall be deposited and
consolidated within half an hour of the mixing of concrete and not disturbed after
the initial set has taken place. The concrete shall be consolidated with iron
rammers until a little of the mortar just enough to cover the surface comes up to
the surface.
The concrete shall be cured by keeping it wet for at least 10 days. Masonry work
or reinforcement work may be started over it at least two days after laying, but
ensuring that curing of new masonry shall be thorough enough to provide curing
to the concrete as well. The back filling of the foundation shall be done after
masonry work has started and the earth filled back shall be kept damp to provide
curing for the concrete.
14
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Test Cubes: The Contractor shall, at his own expense, supply test
cubes and 6” iron moulds, as required for the Preliminary Test
Procedure and Works Tests.
15
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
i) Two sets of 6 cast iron 6” cube moulds with two 4-lbs. 15”
long tamping rods with ramming face one inch square.
16
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Should the test results fail to comply with the requirements (a)
above and should any individual test show less than 85% of the
specified 28 days strength, the Contractor shall make corrective
changes to the Consultant’s approval in the material mix
proportions before placing additional concrete. In addition, such
corrective changes shall be made when the compressive strength of
concrete tested after 7 days indicates that the concrete will not
attain the required compressive strength at 28 days.
2.7.4 The placing of concrete shall not begin until trial batches of the mix
design to be used have been produced by the Contractor and tested. The
trial mix proportions shall be such that the average strength of consecutive
test cylinders shall be 20% higher than the specified 28 days strength and
no individual test cylinder shall be below the specified strength.
17
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
=====================================================
% by weight passing
--------------------------------------------------------------------
B.S. Nominal size of graded Aggregate
Sieve --------------------------------------------------------------------
1.5” to 3/16” 3/4” to 3/16” 1/2” to 3/16”
=====================================================
2.8.4 Slump Test: The consistence of the concrete shall be measured by slump
cone test in accordance with the current British Code of Practice of
Concrete in Buildings and the test of the Slump shall be repeated
whenever the materials are changed and whenever required by the Client.
18
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
All units of precast concrete shall be made to sizes, shapes, qualities and
reinforced as shown on the drawings and shall have additional reinforcement if
required for handling or erection. However, the Contractor shall prepare and
submit shop drawings giving all details of jointing, inserts, anchors, lifting
devices, openings and the method of casting, handling and fixing, for approval of
the Client. The cast units shall be left in the moulds until thoroughly set and
19
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
cured sufficiently to achieve desired strength and shall not be built-in before four
weeks of casting. Contractor must get prior approval of the system and method
proposed for steam-curing or any other scheme from Client. All exposed eye-
bolts, anchors, supporting angles, dowels, etc., shall be of heavily dipped
galvanized steel and shall be cast integrally with the units at exact locations. No
separate payments shall be made for such inserts, anchors, shop drawings, dowels
lifting devices, surface finishes, hoisting of unit or fixing them in their final
positions. The lifting devices shall be safe for at least 100% additional Impact
load and made of materials sufficiently ductile to ensure visible deformation
before fracture.
2.11 FORM-WORK:
Formwork shall be erected true to line and to the shapes required in the work.
The maximum tolerance in columns and walls shall be 1/8” in 10’ height in
concrete checked after stripping the forms. It shall carry without deformation, the
loads due to wet concrete and any constructional incidental load, and when the
concrete is vibrated the shuttering shall withstand the effects of vibration without
deflection, bulging, distortion or loosening of its parts. The Contractor shall be
responsible for the sufficiency of all shuttering, centering and moulds.
The formwork shall overlap the previous concreting to minimize lipping which
shall not exceed 1/8” at any point and shall be completely eliminated in case of
fair-faced concrete. Formwork shall be provided on both faces of concrete when
the slope to horizontal of either face exceeds 30 degrees. The soffits of suspended
spans of beams and cantilevers shall be suitably pre-cambered upward to
eliminate sagging, on removal of shuttering, below the required level as approved
by the Client.
20
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Wire or similar ties shall not be left in concrete having a face exposed to the
weather; any metal part to be left buried shall be 1” away from the surface.
Through bolts shall be permitted provided that they are greased to allow for easy
withdrawal and the holes subsequently made good.
The shuttering shall be designed so that the soffits of slabs and sides of beams,
columns and walls may be removed first without vibration or shock, leaving the
shuttering to the soffits of beams and their supports in position. Wedges or other
suitable means shall be provided to allow accurate adjustment of the shuttering
and to allow it to be removed without jarring the concrete.
Provision shall be made in the formwork for any openings, perforations, sinkings
and of the inclusion of built-in parts as required.
All shuttering shall be thoroughly cleaned of old concrete and immediately before
concreting it shall be thoroughly washed out with water, holes being provided in
the shuttering to permit the escape with the water of sawdust, shavings or other
rubbish.
All joints shall be sufficiently tight to prevent the leakage of grout, and if
necessary the board shall be planned and thickened in order that the surface
against the concrete shall not be broken at bonds between the joints.
All formwork shall be removed without undue vibration or shock and without
damage to concrete. The Contractor shall be responsible for the safe removal of
the shuttering but, in general, formwork shall not be removed earlier than 2 days
for walls, columns and sides of beams; 10 days for slabs, and 21 days for beam
soffits, or as extended by the Client. Any work showing signs of damage through
premature removal of shuttering shall be entirely reconstructed at no additional
cost to the Client. Should it be felt necessary for structural safety, temporary
shoring and propping shall be maintained to the satisfaction of the Client.
2.12 REINFORCEMENT:
2.12.1 Reinforcement shall be accurately cut and bent to shapes and dimensions
and shall be placed where indicated on Drawings and Specifications.
Straight parts of bars shall be truly straight and bends shall be true to
shape and dimensions shown on the drawings and in accordance with BS-
4466. Steel shall not be bent or straightened in a manner injurious to the
21
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
bars. The internal radii of bends shall be not less than twice the diameter
of the bar, except that stirrups and column binders shall be bent to the size
shown within a tolerance of ±1/8”. Bars shall be bent cold.
Reinforcing steel shall be thoroughly cleaned of dirt, oil, paint, loose rust,
mill scale or any coating that would reduce or destroy the bond before any
concreting is done. Steel bars reduced in section shall not be used.
Reinforcing steel shall not be bent or straightened in a manner injurious to
the steel. The Contractor shall provide sufficient spacers, saddles, chairs
and other supports of approved type to the satisfaction of the Client for
maintaining the top reinforcement firmly in position during concreting.
The bottom reinforcement of beams and slabs and columns reinforcement
shall be supported by sufficient precast concrete blocks with embedded
binding wire and thickness to allow the appropriate concrete cover to the
reinforcement. All reinforcement shall be securely fastened together and
fixed in place by binding wire in such a manner that it will not be
dislodged during concreting. The binding wire shall be 16 gauge G.I.
tying wire, or black annealed wire. The schedules shall be prepared in
accordance with BS-4466 – Binding Dimensions and Scheduling of Bars
for Reinforcement of Concrete.
2.12.2 The thickness of concrete cover over reinforcing bars shall conform to BS
CP-144, unless otherwise shown on drawings, and shall be not less than
the diameter of the round bar (or 1.5 times the size of square bar), nor less
than the following:-
22
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
2.12.5 The Contractor shall prepare and furnish shop drawings and details for
manufacture and installation of equipment, material/fitments or structural
components wherever asked for by the Client to know and approve
Contractor’s proposed way of executing the work.
2.13.1 Mixing: All concrete shall be machine mixed except that in emergencies,
the mixing may be by hand as directed by the Client. Mixers shall be
equipped with an accurate water measuring and controlling device and
capable of producing homogeneous concrete mixtures of uniform colour
and discharging it without segregation.
The equipment at the mixing plant shall be so constructed that all the
materials including water entering the drum can be accurately
proportioned and controlled. The entire batch shall be discharged before
recharging. The volume of the mixed material per batch shall not exceed
the manufacturer’s rated capacity of the mixer. Each batch shall remain in
the mixer for a mixing period of not less than 2 minutes which shall be
measured from the time when all the solid material is in the mixing drum.
All the mixing water shall be introduced before 1/4th of the mixing period
elapses.
23
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The Contractor shall submit pour slip on approved format at least 48 hours
earlier of concreting for getting the permission of the Client.
24
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
initial setting of the cement has taken place and within 20 minutes of the
addition of water in the mix. When placed from a height of more than 3’,
chutes etc. shall be employed as approved by the Client to ensure that no
segregation takes place. The concrete shall be efficiently tamped, and
compacted during the operation of placing. It shall be thoroughly worked
around reinforcement steel, work and embedded fixtures and into the
corners of the forms so that no voids or honey combing occur and no
reinforcement or embedded fixtures are displaced. Excessive tamping and
vibration shall be avoided to prevent segregation.
Forms for columns or walls and thin sections of considerable height shall
be provided with openings and other devices that will prevent segregation
and accumulation of hardened concrete on the forms or reinforcement
above the level of concrete.
The workmen carrying concrete to the site and all other workmen moving
about before the concrete is laid shall move only on boards placed for the
purpose and no person shall be allowed to walk on the steel reinforcement
itself.
Prior to the laying of concrete on walls, bearing plates and at other points
as may be directed by the Client, the surface will be brought to a true,
hard, smooth level using a cement sand mortar in the ratio of 1-part of
cement to 3-parts of sand. Two layers of building paper weighing 8-
lbs./100 Sft. per layer will then be laid flat to separate the concrete from
the surface on which is to be laid. This work of plaster and building paper
shall be paid for separately.
25
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
2.13.5 Construction Joints: The concrete shall be placed so that the number of
Construction Joints shall be as few as possible; construction joints shall be
made on horizontal and vertical planes only unless otherwise shown on the
drawings, and only at places approved by the Client. Concrete shall be
carried continuously upto construction joints, and such sequence of
pouring shall be carried out as has been approved by the Client.
On the soil face of all joints and where shown on drawings 1” x 1”, or as
shown on drawings, joint sealer shall be applied hot, which shall be paid
for separately.
In case of continuous retaining walls more than 30’ long, concreting shall
be carried out such that vertical gaps of about 2’ width with vertical
26
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
joggled ends at both sides are left out at about 30’ distances to be filled in
after 14 days of concreting adjacent sections.
2.14.1 Concrete after it is placed and during the early stages of hardening shall be
protected from the harmful effects of sunshine, rain, wind, cold, running
water and shock. It shall be suitably covered for protection from frost,
flowing water or rain and to avoid loss of moisture. Concrete shall be
prevented from drying out for at least ten days or as directed by the Client.
Curing shall be started as soon as free water has disappeared from the
surface of the concrete after placing and finishing generally after 24 hours.
Curing of formed under-surfaces of beams, slabs, etc. shall be
accomplished by moist curing with forms in place for the full curing
period, or if forms are removed prior to the end of the curing period, by
other approved means.
2.14.2 Moist Curing: Concrete surfaces shall be covered with burlap, or other
approved fabric mats, kept continually wet.
2.14.3 Water-proof Paper Curing: Surfaces shall be covered with water proof
paper lapped 4” at edges and ends, and sealed with mastic or pressure
sensitive tape not less than 1.5” wide. Paper shall be weighted to prevent
displacement and tears or repaired by patching.
27
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
All concrete shall be cast to conform to sizes, levels, and slopes and shall be
thickened for supporting walls and sunk for trenches, pipes and ducts, etc.
including leaving out holes, pockets, recesses, chases, drip courses and the like as
shown on the drawings and as directed.
Following loading test shall be carried out by the Contractor if the Client are dis-
satisfied with a part or whole of the structures, to determine its acceptability.
The testing shall be carried out in accordance with BS:CP-114 and as directed by
the Client. The test need not be performed until the expiry of 56 days of effective
hardening of the concrete. In such test, the structure would be subjected to a
superimposed load used for design, and this load should be maintained for a
period of 24 hours before removal. If within 24 hours of the removal of the load,
the structure does not show a recovery of at least 75% of the maximum deflection
shown during the 24 hours under load, the test loading would be repeated. The
structure would be considered to have failed to pass the test if the recover after the
second test is not at least 75% of the maximum deflection shown during the
second test.
If during the test or upon removal of the load the structure shows signs of
weakness, undue deflection or faulty construction, it would be reconstructed or
strengthened as necessary at Contractor’s cost.
28
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
If test result shows that, in the opinion of the Client, the work meets the
specification, the actual cost of the test as certified by the Client shall be borne by
the Client.
Concrete shall be suitably cast, formwork lined with marine quality plywood as
approved, and vibrated to achieve smooth, uniform, plane surface “fair-faced”
finish, conforming to “D” type finish, per BS:CP-110, free from voids and defects
unless otherwise given in BOQ or where plaster is shown on drawings or required
by the Client. All finishes to concrete or precast portions shall conform to
approved samples of finish prepared before commencing work.
The Contractor shall start placing and pouring of concrete only after all the
attachments, fastenings, sleeves, hooks, hold-fasts, dove-tail slots, dowels, inserts
and bolts, etc. are in place. Providing and installing all the embedded items shall
be paid for separately unless given otherwise in BOQ. In case nature of work
requires embedded items as shown in BOQ or drawings, the Contractor shall
include in his rate the cost of provision of holes/recesses, etc.
2.21 MEASUREMENTS:
The rates shall be comprehensive and full compensation for everything furnished
and done to complete the items in all respects as per Specifications of this section
and as described below:
29
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
- The rates of cement concrete plain (PCC) 1:2:4 and richer than 1:2:4 shall
be with 3/4” down graded crushed stone as coarse aggregate from
Approved quarries and sand and fine aggregate from the approved source
30
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION-3
BRICK LAYING AND STONE MASONRY
3.1 CONFORMITY TO STANDARDS:
3.2 MATERIALS:
3.2.1 Brick shall be of first class quality, good, hard, well burnt clay, uniform in
shape and color, and shall measure 9”x4-3/8”x2-11/16” so that every four
courses laid shall measure a foot in height. The brick shall be free from
defects, cracks, chips, stones, nodules of lime or kinker or other blemishes.
The brick would not absorb more than 1/6th of its weight, when soaked in
water for one hour. The minimum compressive strength of the bricks shall
be 1250 psi, with an average for five bricks not less than 1500 psi when
tested flat in accordance with BS-1257 “Method of Testing Clay Building
Bricks”. Bricks of only one kiln shall be used throughout the work, unless
otherwise approved by the Client.
3.2.2 Stone for masonry shall be obtained from approved section of an approved
quarry. It shall be hard, tough, durable of uniform colour and free from
faults and cleavage and of a kind proven satisfactory by previous use for
specified purpose. Stone shall be dressed to exact sizes and shapes with
exposed faces chisel dressed. Stone shall be minimum 5” in thickness, 12”
in width and 18” in length. All visible edges shall be free from chippings
and bed surface of face stones perfectly normal to visible face for at least
3”. At least 50% of the total volume of masonry shall be of stone having a
volume not less than 1 cft. each. Dry stones shall not absorb more than
5% water of their weight when immersed in water for hours.
3.2.3 Cast Stones or concrete grill work blocks shall conform to BS-1217
(1945) as applicable and made from nominal 1:2:4 cement concrete as
specified in section “Concreting”. It shall be of true shapes, size and
shade as shown on drawings or as instructed at site.
3.2.4 Light Weight Concrete Block shall be made from cement concrete by
using additive for producing a density of 75-lbs./cft. The additive for
producing light weight concrete shall be used according to the
31
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
3.2.6 Wall Ties: Metal wall ties shall conform to the requirements of BS-243
“Metal Wall Ties” where applicable. All wall ties shall be galvanized.
Wall ties may be embedded or fastened to rawal plugs or “Fisher 6-mm
Nylon Plugs” or inserted in dove-tail slots or as approved.
3.3 SAMPLES:
The samples of all the material for masonry work shall be approved by the Client,
and same type of material shall be used during the work. If the Client desire to
get the material tested, this will be got done by the Contractor from a laboratory
approved by the Client at Contractor’s expense.
Brick shall always be laid in English bond, unless otherwise specified, with frogs
upwards. Bricks shall be laid with bed and vertical joints properly filled with
specified mortar, raked out ½” deep for plastering/pointing and for unexposed
foundation or plinths flush pointed with the same mortar used for laying. Brick
work must be truly plumb and must be checked by plumb-bobs and straight edges
frequently. Work shall be kept clean of mortar droppings or splashes before
setting hard. Where required, shaped or chamfered surfaces shall be cut and
chiselled finely such that when placed in position they do not require leveling up
with extra mortar. Where work has to be left, the wall shall be left in slope and in
no case the difference of height between various walls shall be more than 5’ at
any section of the building.
32
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
All brick work shall be bonded where it abuts other brickwork. Where brick walls
or partitions intersect or abut, it shall be necessary to interlock the masonry of the
two walls in such a way or use wall ties so as not to leave a straight vertical joint
between the two walls. Where brickwork abuts concrete, wall ties engaging in 3”
long galvanized dove-tail slots cast in concrete members shall be provided at
every fourth-course, or fixed to approved Nylon plugs in drilled holes in concrete
member as approved. In cavity wall construction, wall ties shall be placed 5’
apart horizontally and 12” vertically and staggered. Top of walls on which
slabs/beams will rest shall be finished with a smooth level bed of 1:3 cement sand
mortar and covered with two layers of building paper weighing 8-lbs./%sft. or
polythene sheet (2-layers) with overlaps.
Built-in anchor bolts, inserts, pipe supports, hangers, pipe sleeves, dowels, ties
and all items shown on the drawings or specified are required to be built into the
masonry as the work progresses. Frames and other built-in works shall be
maintained in their proper position and bracing shall not be removed until they are
securely held by the masonry. The spaces around all built-in items shall be filled
with masonry, where shown on drawings. Contractor shall leave openings in
masonry for air-conditioning ducts and grills, plumbing pipes, electric conduits,
etc. The masonry shall be kept properly cured for at least 10 days where cement
mortar is used. Where according to plans and sections the masonry would require
cut bricks to be used, the same shall be done by the Contractor at no extra cost to
obtain correct thickness according to drawings.
Vertical joints in alternate courses must be directly one over the other and
horizontal joints shall be truly level. The thickness of joints must be kept uniform
3/8” to 1/2” unless otherwise specified, throughout the work.
Stone masonry work shall be carried out using approved stones that result in
uniform colored and textured surfaces with truly horizontal and vertical joints in
coursed masonry work. Through bond stones shall be marked and uniformly
spaced in masonry work. Stones shall be soaked for 2 hours prior to laying.
Every stone shall be laid in the work on its natural quarry bed or in such a manner
that stresses borne by it come normal to such bed. Each stone shall be set with
both bed and vertical joints filled with mortar, and thoroughly bedded in.
Unless otherwise specified stones shall be laid in 1:4 cement sand mortar. Entire
masonry in any structure shall be carried up to a uniform level, and where breaks
are unavoidable joints shall be made in gradual steps. Cross-walls shall be fully
bonded to main walls. Exposed surfaces shall be finished as specified; when not
specified, joints shall be struck 1/2” deep simultaneously with masonry work, and
face of work shall be kept clean. Contractor shall suitably protect the work from
33
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
rain and frost during construction and cure it by moistening for 10 days after
laying.
Masonry with light-weight block shall conform to all relevant requirements of the
clause for brick masonry work’s specifications. Concrete blocks should be
thoroughly dry before they are used and care shall be taken to protect them from
rain and dampness. Each lot shall be inspected by the Client before use, and if the
blocks are not thoroughly matured and dry, the same shall not be used until
approved. The blocks should be laid on a full bed of mortar and the joint well
flushed up. The top of the walls shall be protected by suitable means from rain
and frost. The blocks should have a rough textured face and the joints should be
raked out to a depth of about 1/2” as the work proceeds.
The blocks shall be manufactured from cement, coarse aggregate 3/4” to 3/16”
grading and sand or from “all in aggregate” which shall be such that not more
than 5% shall exceed the maximum size of 3/4” and not more than 60% shall
pass a BS 1/2” sieve and retained on 3/16” sieve. The block density (block
weight divided by gross volume) shall not be less than 94-lbs./cft. and
compressive strength shall not be less than 500psi for non load bearing walls and
1500psi for load bearing walls.
The sizes of the blocks may be 12”x6”x4”, 12”x6”x6” or 12”x6”x9”. The blocks
shall be kept on pallets until cured for 2 days.
34
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
3.9 MEASUREMENT:
All types of masonry work shall be measured by volume, except masonry walls,
veneering and cladding upto 4.5” thick which may be measured by superficial
area.
All openings and built-in members of other materials like beams, lintels, bed
plates, etc. shall be deducted unless the superficial area of openings and above
items is one sq.ft. or less. Wall thickness shall be those shown on drawings and
not those actually achieved at site.
The rates shall be comprehensive and inclusive of full compensation for every
thing required to be furnished (including mortar) and done to complete the BOQ
item in all respects as per specifications of this Section. The rates of masonry pay
items shall not cover the following, unless otherwise specifically required in
BOQ, which shall be measured and paid for under separate pay items in BOQ:
a) Reinforcement and all types of inserts like anchors, ties, sleeves, hoop
iron, etc.
b) Specially made sills, cornices, drip courses and filling material in cavity
walls.
35
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION - 4
PAVING
Except as otherwise specified, paving and flooring work shall conform to British
Standard CP-304, “In-Situ Flooring” as applicable to the work shown on the
drawings and described in the Bill of Quantities.
4.2 MATERIALS:
Sand shall conform to BS-1199 (1955) “Building Sands from Natural Sources”.
Surface Hardener: Concrete flooring, where called for in the Bill of Quantities,
shall include a non-metallic surface hardener of approved make, utilized as per
printed instructions of manufacturer and as approved by the Client.
4.3 SAMPLES:
The materials required under this section shall be used after approval of the Client
and same type of materials shall be used throughout the work. If the Client
require to get the material tested, this shall be got done by the Contractor at his
own cost from a laboratory approved by the Client.
36
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The flooring shall be divided into panels not exceeding 16 sft. or as shown on the
drawings or Bill of Quantities, or as directed by the Client. The symmetrical
panels shall be formed by wood or iron screeds of 1.5” width or glass or metal
dividers and of a depth equal to the thickness of the floor concrete. The top of
these screeds should be at the exact required level of the finished floor. Alternate
panels shall be laid on alternate days. If wood or iron screeds are used, sides of
the panels laid first shall be coated with bitumen of S.I.B. quality and two layers
of approved kraft paper provided in the joints before laying the adjacent panels.
The surface shall be tested with a straight edge to detect high and low spots which
shall be eliminated. The Contractor must keep a straight edge not less than 8’
long with parallel sides as well as 10” spirit level available near the work for
testing the floor being laid throughout the time the work is in progress. In no case
shall hammering of any type be allowed on a finished surface. The concrete after
laying shall be tamped to force the coarse aggregate away from the surface, and
while the concrete is still green but sufficiently hard to bear a man’s weight, it
shall be wood floated to a true even plane with no coarse aggregate visible, by
applying sufficient pressure on the wood floats to bring moisture to the surface.
After the surface moisture has disappeared, surface shall be steel trowelled to a
smooth, even and impervious finish free from trowel marks. After the cement has
set enough to ring the trowel, surface shall be given a second steel trowelling to a
final finish. The use of additional mortar or neat cement for giving a smooth
finish shall not be allowed. Concrete shall be left undisturbed for 24 hours after
laying. During the process of laying as well as for a period of 14 days after laying
it shall be protected by suitable covering from the weather and extremes of
temperatures and kept wet for that period. Expansion joints shall be filled with a
mixture of 90-lbs. approved asphalt per cft. of sand.
37
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
II. Two Coats of Bituseal at 1.5 gallon per 100 Sft per coat.
III. Aluminium foil (Building Paper) sheet.
Vertical DPC shall conform to the specifications “Plastering and Pointing” and
consist of the following unless otherwise given in BOQ:
a) 3/4” (19 mm) thick, 1:3 cement sand plaster, finished hard and smooth.
b) One layer of Special Industrial Bitumen, applied hot, having neat uniform,
un-interrupted surface, free from bubbles, pin holes, etc. @ 35-lbs./%sft.
The composition shall be of two layers, the “Undercoat” and the “Topping”.
Flooring shall be laid in panels, expansion joints shall be provided as given in
Section 4.4.
The ratio for the undercoat shall be 1-part of cement, 2-parts of sand and 4-parts
of crushed stone aggregate by volume. The ratio for the topping shall be of 1-part
of cement & 2-parts of crushed stone aggregate and no sand shall be added. The
water/cement ratio shall be kept a minimum for workability but not more than
0.40. First the undercoat shall be laid within the screeds/dividers leaving required
space for the topping. Within one hour of laying of undercoat the topping shall be
laid monolithic, and levelled and beaten with long wood straight edges, taking
care that all small voids and needle holes are filled with the mix while levelling
the top. When the cement mortar in the topping has taken its initial set (and not
before) the surface shall be lightly trowelled with steel floats. No scratches, holes
or unevenness shall be left out in trowelling. The addition of cement to the top
surface to obtain an easy polish is absolutely forbidden. After sufficient
hardening, the surface shall be finished smooth and cured for 14 days.
Where in-situ cove moulding in concrete is called for in the drawings or Bills of
Quantities the same shall be formed where the border of the floor finish meets the
wall and carried up the wall to form a skirting of the same composition as the
topping. The skirting and the cove are to be formed at the same time as the border
and shall be of such dimensions as are shown on the drawings or directed by the
Client. Floor and skirting/cove moulding shall be rubbed/ground smooth where
un-even or rough.
38
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
When called for in the BOQ or directed by the Client, the wearing surface of
concrete pavements shall be rendered nonskid by suitable means approved by the
Client. Completed work shall be cured for 14 days.
Expansion joints 3/4” thick shall be filled to entire depth of pavement with
Asphalt-Sand mix @ 90-lbs. of Asphalt per cft. of sand.
Description: Under this item the Contractor shall lay brick pavement at locations
indicated on the plans or where directed by the Client and in accordance with the
plans and specifications.
Materials: Brick shall conform to all the requirements specified in Section “Brick
Layer & Stone Masonry”.
Construction: The Contractor shall prepare the subgrade to provide smooth and
firm foundation compacted to a minimum of 95% of standard AASHTO
maximum dry density, finished accurately to lines, grades and dimensions shown
on drawings or as directed by the Client. Over-excavated portion shall be made
good by mortar or lean concrete (1:4:8).
The subgrade shall be sprinkled with water thoroughly without being muddy. The
laying shall be in plain, diagonal, herring-bone or other pattern as ordered by the
Client, where laid in plain courses it shall be bonded to break joints half the length
of the brick.
The joints shall not be less than 1/4” or more than 3/8” thick and shall be filled
with mortar for the full depth of the joint. The surface obtained shall be in
accordance with the lines and grades shown in the plans, and all excess mortar
removed from the finished surface.
39
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
4.9 MEASUREMENTS:
All work under this Section shall be measured by the superficial areas unless
given otherwise in BOQ.
Unless metallic or any other type of panel dividers are called for in BOQ, the rates
for PCC floors and pavements shall be for laying the same in alternate panels with
treatment and fillers for joints as specified. Rates for RCC pavements/roads shall
also be inclusive of steel reinforcement and expansion joint fillers as specified.
40
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION-5
TERRAZZO AND MARBLE FINISHES
OR WORK
5.1 CONFORMITY TO STANDARDS:
5.2 MATERIALS:
Cement, Sand, Aggregate for Concrete and Water shall conform to specifications
of the Section “Paving”.
Marble Chips shall be crushed marble and best quality white or colored, sound
and hard local marble chips approved by the Client, and of the required sizes.
Marble for Wall Facing and Floors shall be best quality polished local marble of
uniform texture free from all defects, obtained from Mullaghori or equal
approved, as required in BOQ and approved by the Client.
Onyx: The onyx shall be of approved color and shade obtained from Quetta or
equal approved, sound and free from all defects.
Glazed Wall Tiles shall conform to BS-1281 “Glazed Ceramics Wall Tiles” of
approved size and color.
Angle Clips for precast toilet partitions shall be chromium plated steel clips as
shown on drawings.
Bolts of precast toilet partitions shall be 5/16” brass bolts chrome-plated with
acorn heads, fitting to wall anchors.
41
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Pipe for Toilet Partition shall be galvanized iron conforming to BS-1387. Angle
for stair nozing shall be cold rolled aluminum angles of the size required.
5.3 SAMPLES:
All materials used for Terrazzo and marble work as well as samples of terrazzo
floor and marble work shall be submitted to the Client and their approval
obtained, and same type of material will be used throughout the work. If the
Client require the material to be tested, this shall be got done by the Contractor at
his own cost from a laboratory approved by the Client.
A layer of cement and marble chipping mixture should be well trowelled into the
surface of the base concrete before filling to the top level of the screeds. The
layer should be well compacted and all voids shall be filled in. A layer of neat
cement of the specified color shall then be well-trowelled into the surface leaving
a plain smooth surface.
Floor shall be laid in panels of about 4’x4’ or of size as directed by the Client.
Dividing strips of brass, aluminum, glass or terrazzo as specified shall be
provided and fixed to exact levels making an allowance for grinding. Brass or
Aluminum strips shall not be less than 0.064” thick and of width equal to the total
thickness of cement concrete base and Terrazzo topping. In case of terrazzo strip,
a groove 3/4” wide and of thickness of the finished floors shall be left between the
panels of terrazzo, which shall be filled with terrazzo of the same specifications as
for floor mixed with approved color. The Contractor shall produce perfectly
straight and sharp lines for this in filling between the panels. Three days after
laying, the top layer must be evenly and smoothly machine-ground with
42
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
carborundum blocks of coarse, medium and fine grades so as to ensure that all
marble chippings are evenly exposed all over the surface. If marble chips are not
evenly exposed, the Contractor shall remove the wearing surface and relay at his
own cost. The surface after grinding shall be left undisturbed and cured for 2 to 3
weeks, after which it shall be cleaned of dirt and dust by rubbing gently with
pumice stone or washing soda in sufficient water. Three days after the surface
has been cleaned it shall be rubbed hard with 1:10 solution of oxalic acid using
felt. The surface shall then be cleaned and washed with plenty of water. After the
surface has dried a final gloss shall be given by chemical polishing the surface
using approved Polish to the satisfaction of the Client.
The marble chips and cement shall conform to specifications for floor. Mixing
shall be done in the same manner and proportion. The plastered surface over
which the terrazzo topping is to be applied shall be well roughened and watered,
cement mortar of specified ratio shall then be plastered over this well roughened
surface to required thickness. Before the base course has set, the layer of terrazzo
mixture (of the specifications for Flooring) shall be well trowelled into the surface
of the base to a thickness which after grinding shall result in the finished thickness
as required. A layer of neat cement of the specified color shall then be well
trowelled into the surface leaving a plain smooth surface. After 24 hours the
Contractor shall start finishing as for floors specified above. Terrazzo skirting
shall be provided around all terrazzo floors unless shown otherwise. Skirting and
dado shall be straight. They shall be with 1/4” radius cove at floor unless
otherwise shown. Grinding, finishing and polishing shall be done as per terrazzo
floors.
The stair risers and treads shall be finished according to exact sizes including the
terrazzo topping making allowance for grinding of terrazzo. The nozing shall be
flush with the terrazzo toppings and shall be protected by aluminum angles if
specified or shown on drawings. The angles shall be firmly secured by means of
counter-sunk brass screws and cast together with the step. Terrazzo shall be
ground finished and polished as per terrazzo floors.
Partitions for toilets shall be precast RCC slabs finished with 1/4” thick finished
and polished terrazzo on both faces. The finished thickness of these walls shall be
2”. RCC slab shall conform to specification for “Concreting” and terrazzo to
Section 5.5. Fixing of these partitions to floor, walls, etc. shall be as directed by
the Client and as shown on drawings.
43
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Where required floors shall be constructed of Terrazzo Tiles laid on a mortar bed.
Unless otherwise specified tiles shall be 12”x12”x 1.1/8” thick hydraulically
pressed terrazzo tiles with min. 1/2” thick wearing layer with cement to chips
ratio not less than 1:2 by weight and coloring matter (if any) not exceeding 10%
by weight of cement used in the mix. Tiles shall be factory pressed with a
pressure of not less than 2000 psi and factory ground. These shall be of a color
pattern and chip size as approved by the Client using Portland cement or white
cement as specified. Tiles shall be laid true to lines and perfectly even on a
mortar bed using 1:3 cement sand by volume of 1/2” average thickness over
1.1/2” thick 1:2:4 concrete floor screeds unless specified otherwise.
When laying has been completed all joints will be grouted with factory supplied
pigmented cement mortar to match the basic cement matrix of the tiles. Top of
floor shall then be left undisturbed and cured for 2 weeks, surface thoroughly
cleaned, and ground and polished to a full gloss as for in-situ terrazzo.
Acid proof tiles shall be of specified sizes and design, whether glazed or un-
glazed and whether plain or non-skid and of (M/s. EMCO or M/s. International
Ceramic Industries, Islamabad, make or approved equal). Acid-proof cement (NF-
10 of M/s. EMCO or approved equal) shall be applied to back and sides of joints.
The work shall be laid and cured as per written instructions of the manufacturer.
Finished work shall conform to required lines, grades, etc.
If both acid-proof cement and epoxy mortar are specified to be used, acid-proof
cement shall be used as above leaving the half depth of the tiles joints unfilled
which shall be filled with epoxy mortar. Acid-proof tiles and mortar/epoxy work
shall be laid over concrete 1:2:4 and/or cement sand mortar base as may be
specified. If specified, specially moulded “Cove” tiles shall be used as skirtings.
For marble facing to walls, selected marbles of specified thickness and sizes not
less than 2’x1’ or as may be specified shall be used. Slabs shall be fixed to
masonry or concrete with brass or other approved clips two at top and two at
bottom of each slab. The surface over which the marble slabs are required to be
fixed shall be cleaned of all dirt and dust. Marble slabs shall be laid over a 1:2
44
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
cement mortar plaster layer truly in plumb with copper clamps as specified, each
slab laid on 5 dabs of 4”x4” each in 1:2 cement sand mortar and grouted with
white/colored cement as specified. For marble floors selected marble of approved
color and quality and specified thickness and size shall be embedded over 1/2”
thick 1:2 cement mortar laid uniform and finished truly level with square edges.
Marble Slabs on Kitchen, Vanity Counter top and Stair Steps to use as specified
in BOQ. The cured marble floor and wall facings shall be finished and polished to
full gloss.
Partitions shall be set true and level. Where partitions abut masonry walls, these
shall be secured as shown on drawings. At other joints 3 angle clips shall be
provided at each inter-section. Where slabs bear on floor they shall be secured
with brass dowels not less than 2 per slab.
The wall which is to receive glazed tiling shall be thoroughly soaked with water.
Then 1:1 cement sand rendering shall be applied and left slightly rough. The tiles
well soaked in water shall be bedded in 1:1 cement sand mortar, the mortar being
buttered on the back of the tile to give a bed 1/4” thick after which the tile shall be
pressed and tapped home in correct position.
The grouting shall be done with white or tinted cement as required. Any fixture
required to be fixed in the glazed wall tiling shall be done with tiles cut to exact
size with proper tools. Where whole tiles can be used, pieces shall not be
permitted.
5.13 MEASUREMENT:
The rates shall be full compensation for every thing required to be furnished like
materials, labor, T&P scaffolds, etc. and the work done like roughening and
cleaning/washing of the existing surfaces, batching, mixing, dividing and laying
in panels including the panel dividing strips (if and as mentioned in BOQ
drawings) leveling, compacting, jointing, curing, grinding, washing, cleaning,
45
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
In Case of BOQ Items for Tiles Work: (terrazzo tiles, glazed ceramic tiles, acid
proof tiles/slabs, etc.) the following shall be as specified in BOQ/shown on
drawings:
46
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION-6
PLASTERING AND POINTING
6.1 CONFORMITY TO STANDARD:
Except as otherwise specified, all plaster work shall be carried out in conformity
with B.S. CP-211 “Internal Plastering” and CP-221 “External Renderings and
Finishes” as applicable to work shown on drawings and/or required in BOQ.
6.2 MATERIALS:
Sand shall be of medium coarse grain obtained from local approved quarries
subject to the approval of the Client, and shall conform to BS-1199 “Building
Sand from Natural Sources”.
6.3 SAMPLES:
All materials for plastering and pointing shall be used after approval of the Client
and same type of material will be used throughout the work in progress. If the
Client require the material to be tested, this shall be got done by the Contractor at
his own cost from a laboratory approved by the Client before work is commenced.
The surface to be plastered shall be properly cleaned and watered for 24 hours and
before application of plaster. Concrete surfaces shall be properly roughened by
wire brushes while the concrete is still green or by hacking if the surface has
hardened so that 40% of the concrete surface is roughened. Masonry joints shall
be raked to 1/2” depth.
Cement and sand shall be thoroughly mixed in a dry state and with gauged water
for sufficient workability. Any mortar which has not been used within 30 minutes
of the addition of water shall be rejected. All tools should be examined and
thoroughly cleaned before plastering is begun. All corners and arises shall be
rounded or squared as required while plastering. The plaster shall be laid and
47
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
finished to a true and plumb surface free from blow holes, trowel marks and other
defects and tested frequently with plumb-bob and straight edge not less than 10’
in length. All horizontal lines and surfaces shall be tested with a level and all
jambs and corners with a plumb-bob as the work proceeds. All mouldings and
decorations shall be worked true to template and shall be neat, clean, level and
parallel, or truly plumb as the case may be. Plaster shall be applied to specified
thickness in mortar of specified mix ratio and required consistency.
All putlog holes shall be filled up in advance of the plastering as the scaffolding is
being taken down. The plaster shall be kept wet for 10 days and protected from
ambient temperatures and weather. Plaster stops and beads shall be of galvanized
metal or as approved and shall be fixed where shown on the drawings.
For struck pointing the mortar shall be filled in the joints flush with masonry with
a pointing trowel and then pressed with proper pointing tools to form weathered
and struck horizontal joints and triangular or V-notched vertical joints. For flush
pointing, after pressing mortar in the joints, these shall be filled up with mortar
and finished level with edges. After pointing, the face of the work shall be
cleared of all surplus mortar. No washing shall be done till the pointing has set.
All defects shall be treated at Contractor’s expense. All work shall be kept wet
for 10 days and protected from extreme temperatures and weather.
48
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
6.6 MEASUREMENT:
All the work under this section shall be measured by actual area plastered
including returns and soffits. Deduction shall be made for the openings of any
size from the two sides. Unit of measurement shall be %Sft. or as given in BOQ.
The accepted BOQ rates for the BOQ items shall be full compensation for every
thing furnished and done for the completed items, at any height, depth or level, as
per these specifications, drawings and instructions of the Client.
i) In case of plaster work rates, the thickness and mix ratio shall be as given
in BOQ items. Finish shall be smooth or to suit the type of painting/lime
washing/distempering, as directed by the Client or rough finish in case of
under-coat/base plaster. Drip courses made in plaster shall not be
measured for direct payment but shall be included in the plaster rate. The
plaster rates, unless otherwise given in BOQ do not include costs for
providing, using or installing surface hardeners, water proofing agents or
any other type of additive, metallic beads, corner guards and plaster stops.
ii) In case of pointing, the type and mix ratio shall be as given in BOQ item
or on drawing. The rate shall not include cost of providing and using any
pigment, unless otherwise given in BOQ items.
49
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION-7
ROOFING AND WATER-PROOFING
7.1 CONFORMITY TO STANDARDS:
All roofing work shall conform to relevant standards as applicable to the work
specified. Except where otherwise specified, the work of water-proofing shall
comply with the requirements of British Standard CP-144. “Roof Coverings, Part-
I, ‘Built-up-Bitumen Felts’ and Part-2 ‘Mastic Asphalt’ “ as applicable to the
work specified.
7.2 MATERIALS:
Bitumen shall conform to BS-1310 having a softening point lower than 160 deg.F
and shall be Special Industrial Bitumen (S.I.B.) grade 10/20, PB3 or PB4.
Bitumen Felt shall conform to BS-747:1968, fine sand surfaced Bitumen Felt
type IB, fiber based “Sealock”, “Master” or equal.
Gravel shall be 1/4” to 3/8” size and shall be washed free of dust, soil or foreign
matter, and 100% passing through a 1/2” screen and dried.
G.I. Corrugated and Plain Sheets shall conform to relevant standards and shall be
of 22-SWG thickness.
50
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Steel Bolts, Nuts, Washers, Screws shall conform to the requirements of BS-916
“Black Bolts, Screws & Nuts” and BS-1083 “Precision hexagon bolts, screws,
nuts and plain washers” as applicable & BS-1494 “Fixing Accessories for
Building Purposes”.
Wood Screw: All fixing accessories for sheet roofing, J-hook bolts, Limpet
patent dome washers, anchoring bolts and nuts for connecting sheets to each
other, etc. shall be hot dipped galvanized as per BS-720 Part-I “Hot Dip
Galvanized Coating”.
7.3 SAMPLES:
The Contractor shall get samples of all the materials used for the items under this
section approved by the Client, and same type of material shall be used
throughout the work. Any material required by the Client to be tested, shall be
got tested by the Contractor at his own cost from a laboratory approved by the
Client.
51
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
layers shall be staggered by 11” so that in every three layers each lapped
joint is covered by two continuous layers.
e) Protective Coating: Unless specific concrete or tile paving is called for
above the water-proofing membrane, the final mop coat of bitumen while
hot shall be provided with a blinding layer of washed dry peagravel or
coarse sand as specified at 4-Cft./%Sft.
Roofing sheets shall rest on horizontal purlins so as to come under the ends and to
give at least one or two lines of intermediate support. Each sheet shall be laid
with 6” minimum lap at the end and a side lap of 2 corrugations. Each sheet must
be fastened at the corners and every third corrugation along the ends, and evenly
at the sides at intervals of not more than 2’. Holes for fastenings shall be drilled
and not punched and shall be located always at ridges. Sheets are to join each
other with J-hook bolts of 1/4” dia through 5/16” dia holes. Each bolt shall have a
galvanized limpet dome washer at the top and a bitumen washer over the hole.
Ridges and hips shall be covered by special ridge and hip section or with plain
G.I. sheeting 22-SWG laid in length with end and side laps of at least 9”, fastened
as specified.
Sheets shall be fastened down just above the eaves by continuous lengths of
1.5”x1/2” flat iron bolted down at not more than 5’ intervals by 1/2” dia bolts
with 3”x3”x1/8” washer at the lower end and embedded 12” into the wall.
Unless otherwise given in BOQ the work will consist of a coat of Primer per
Clause 7.4 (b) on clean dry surface, two coats of Special Industrial Bitumen or
approved equal applied at 17-lbs./%Sft. Each coat having a neat surface free of
pin holes, bubbles, blemishes etc. a layer of polythene sheet of 500 gauge (5-mill
52
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
= 0.005” thick) having 3” overlaps at joints, compacted earth, one inch thick mud
plaster, a layer of first class burnt clay tiles 1.5” thick grouted in 1:3 cement sand
mortar. Materials shall conform to the relevant specifications of this and other
sections. Completed work shall be cured for 10 days.
7.8 MEASUREMENTS:
All quantities shall be measured net, without any allowance for overlaps, turn ups,
etc. Roofing and Water proofing shall be measured by superficial area, except that
foam concrete insulation shall be measured by volume. Slopping roofs shall be
measured along the slope.
The rates shall be full compensation for every thing required to be furnished (like
labor, T&P, scaffolds, materials) and done (like heating, transporting, laying, etc.)
for the work item complete in place in all respects, conforming to these
specifications.
Rate shall cover work as per Clause 7.4 but the number of felt layers, numbers of
piles of the felt, weight of felt per roll of 72’x3’ and whether the top flood coat
shall be covered with sand, pan gravel or polythene sheet 0.005” indicated gauge,
shall be as given in BOQ/drawing.
Rate shall cover work per Clause 7.5, excluding the monolithic plaster layer at top
which shall be paid for under a separate item under this Section or Section
“Plastering and Pointing”. Density and average thickness of foam concrete shall
be as indicated in BOQ.
Pay Item for Water Proofing and Mud & Tile Roofing:
Rate shall be for work as per Clause 7.7 and the average thickness of compacted
earth shall be 3”, unless given otherwise.
The rate shall cover work as per Clause 7.6 including its fixing arrangement
(except the support system like rafters and purlins) like J or hook bolts, limpet and
bitumen washers including their galvanizing/painting as per specifications
Section-10, laps, hips, ridge and gutter pieces, etc. complete system as per actual
requirements.
53
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION – 8
RAIN WATER DRAINAGE
8.1 CONFORMITY TO STANDARD SPECIFICATIONS:
All work in this section shall conform to the applicable requirements of BS CP-
301 (1950) and CP-303 (1952) and to the directions of the Client and these
specifications.
8.2 MATERIALS:
Cast Iron Rainwater Pipes & Fittings: for use above ground shall conform to
BS-416 (1967) as applicable and for drainage work below ground to BS-437 as
applicable.
Cast iron pipes and fittings 6” dia and 4” dia shall be of medium grade and the
pipes shall weigh not less than 73-lbs and 48 lbs per 6’ length respectively. These
shall be perfectly straight and of uniform diameters and thickness. The pipes and
fittings shall be coated inside and outside with bitumen hard enough not to flow at
a temperature of 145 deg. F. The exposed work’s external surface shall be
painted with an approved paint 3 coat work.
The hangers, supports and anchors shall be of approved design and shall be so
arranged as to allow the pipes to lift in case of settlement of the building. These
shall be painted with bitumastic enamel paint or the paint of the same quality as
for the pipes supported by these hangers.
Galvanized Iron Pipes and Fittings: The pipes shall conform to BS-1367
medium grade and its galvanizing shall conform to BS-729 as applicable. All G.I.
pipe fittings of galvanized iron pipes shall conform to British Standard
Specifications and their galvanizing shall conform to BS-729 as applicable.
Jointing and Packing Material: Lead shall be sound, free from inclusions and
shall be of the best quality available in the market. The packing shall be of pure
jute, hemp or hempen spun yarn.
54
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
8.3 SAMPLES:
Samples of all materials, fittings, fixtures etc. shall be got approved before use by
the Client. Approved substitutes shall be accepted in place of the specific types or
brands.
8.4 LAYING AND JOINTING OF C.I. PIPES:
Each pipe shall be carefully examined before being laid and defective or damaged
pipes shall not be used and shall be removed from the site. The pipes before
being laid shall be brushed to remove any soil or stones that may have
accumulated on the inside of the sockets and outside of spigot being carefully
cleaned and shall be plugged as necessary during construction. Any section of the
pipe found to be defective even after fixing shall be replaced with sound pipe
without additional expense to the Client. Fittings at bends in the pipe line shall be
firmly anchored in order to prevent the fittings from being blown off the lines
when under pressure. Joints for Cast Iron rain water pipes and fittings shall be
made with lead, jute and hemp spun yarn. Run lead joints shall be applied to
perfectly dry pipes. Under wet conditions, depths and methods as per BS Code of
Practice –310 (1950). The packing material shall be well packed into the annular
space so as to prevent the entrance of lead into the pipe. The lead shall be caulked
to form a tight joint without over-straining the bell. Painting shall be done per
Clause 8.2 and Specification Section-10.
All screwed joints both internal and external shall be carefully examined. The
threads of the joints shall be perfect for the full depth of the joint and any burrs at
the ends shall be removed. In case there is any flow in the thread, the thread shall
be tightly drawn over the sockets and dies of the correct size to suit the threads
shall be used. The screwed ends of pipes or specials to be jointed shall be very
slightly tapered to ensure water tightness. The jointing work shall be so arranged
that the two ends of the pipes or specials jointed shall be at equal distance from
the middle of the socket and shall have a space of not more than ¼” between
them. Country cotton yarn smeared with genuine white lead shall be wound in
the grooves of the outside threads of the pipes from end to end of the joint. The
strand of cotton yarn shall be very thin and of best quality. No piece of cotton
yarn shall project outside the ends of the joint or inside the pipe. While lead paste
shall be thin and made up by boiling genuine and moist white lead in linseed oil.
Painting shall be done per Clause 8.2 and Specification Section –10.
55
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
All piping shall be tested by the Contractor and approved by Client before
acceptance, by either of the following methods:
a) Water Test: The entire rain water drainage system shall have all
necessary openings plugged to permit the entire system to be filled with
water to the level of the highest stack. The system shall hold this water for
30 minutes without showing any drop.
b) Air Test: Air at a pressure of not less than 5-lbs/sq.in shall be applied
with a force pump and the system should maintain the pressure for at least
15 minutes without leakage. A mercury-column gauge shall be used in
performing the air test.
Open drains shall be constructed where required on the site of works for rain
water drainage as per drawings and true to level and slopes. Materials and
construction shall comply with clauses of specifications under section
“Concreting” and other relevant sections.
Rates for all items under this Section shall cover the cost of furnishing all
materials, labor and appliances at site and performing all operations in connection
with laying, fixing, jointing, testing and painting in accordance with the bills of
quantities and as specified. All pipe work shall be measured in running feet/meter
of finished length. Wastage or length consumed in joints shall not be measured
for separate payment. However, for measurement of completed length of G.I. &
C.I. pipe line, the length consumed in specials and fittings shall be measured and
paid for along with the pipeline. All types of specials for fixing cast iron or A.C.
pipes are included in the rates of pipes and no separate payment for specials will
be made.
56
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION – 9
CARPENTRY, JOINERY AND GLAZING
9.1 CONFORMITY TO STANDARDS:
Except as otherwise specified, work under this section shall conform to relevant
British Standards as applicable to work.
9.2 MATERIALS:
Panelling Boards: Where called for in the BOQ or shown on the drawings,
paneling boards shall be factory-pressed boards of required thickness with Teak
or Sheesham veneer on the exposed face and commercial ply on the back, with
high density particle board in – between, as specified and approved by the Client.
Edges and ends of boards where visible shall be provided with a veneer of
matching grain and quality.
Formica: It shall be of required shade and pattern and of best quality as approved
by the Client.
Flush Doors: shall conform to BS-459 “Flush Wood Doors” and Code of
Practice CP-151 Part-I “Flush Wood Doors”.
57
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Glue: shall conform to the applicable requirement of BS-745 “Animal Glue for
wood” or BS-1204 “Synthetic Resin (Phenolic and Amine Plastic) Adhesives for
construction work in Wood”.
Putty shall be an elastic glazing compound suitable for interior and exterior
glazing and shall conform to the requirements of BS-544 “Linseed oil putty for
use in wooden frames”. The putty for metal frames shall be of a type specially
prepared for use with metal frames conforming to the applicable requirements of
the BS or of a make approved by the Client.
All glass used shall be even, free from specks, bubbles, tints, distortion and flaws
of every kind. Unless otherwise specified in the Bills of Quantities, the glass shall
conform to weights per Sft for various sizes as below:
Weight of glass as required for the largest panel in any unit of door or window,
etc. shall be employed in all panels irrespective of their size.
9.3 SAMPLES:
Samples of material used for the work under this section shall be submitted for
approval by the Client and same type of material shall be used throughout the
58
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
work. If the Client require the material to be tested, this shall be got done by the
Contractor at his own cost from a Laboratory approved by the Client. Any
material rejected by the Client shall be removed from the site immediately.
9.4 WORKMANSHIP:
9.4.1 General: Wood work shall be neatly and truly finished to exact
dimensions and details as shown on the drawings. All joints shall be
simple tenon and mortise joints unless otherwise specified or directed by
the Client, and shall fit truly and fully. Holes of correct size shall be
drilled before inserting screws. Driving in or starting in screws with
hammer shall not be allowed. All screws shall be dipped in oil before
being inserted in correct size holes which shall be drilled for the purpose.
All portions of timber, built into or against masonry or concrete or used as
sub-frame for railing or paneling, shall be treated with wood preservative
as specified.
If after the wood work has been erected, any undue shrinkage, distortion
or bad workmanship is discovered the Contractor shall forthwith replace
or amend the same without any extra charge, to the satisfaction of the
Client.
9.4.2 Frames for Doors, Windows etc.: Door and window frames shall
conform to the applicable requirements of BS-1567 “Wood Door Frames
and Linings”. The door frames shall be of best quality Deodar wood or of
the timber specified and shall be fabricated to exact size and dimensions as
shown in the drawings. The vertical members of frames shall be
embedded in floors at least 2” deep for which extra length no extra
payment shall be made. Frames shall have rebate to receive the leaves as
shown on the drawings. The frames shall be suitably secured to the
brickwork or concrete by holdfasts or expansion bolts as shown on the
drawings or as approved by the Client. Stop shall be of best quality timber
of the same specification as that for frames.
59
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
with 5-ply 6mm thick plywood of specified finish on each side. Door leaf
shall have an inner frame and well seasoned edge strips of quality and
design shown on drawings on all four edges of leaf. Face veneers shall be
free of saps, streaks, knots and irregularities and shall be suitable for
taking required finish. Veneer construction shall provide for equal stress
on both sides to ensure absence of warp. Flush doors shall be screwed to
the frames by means of hinges which shall be counter sunk in the wooden
frames.
9.4.5 Wiregauzed Doors and Windows: They shall be of size and design as
shown in drawings or indicated in BOQ. Wire gauze shall be fixed to the
frame of the leaf after being stretched from out to out of rebate and fixed
taut. The screw shall not be less than 1.25” in length nor spaced farther
than 9”. All exposed arises of the fillet shall be finished with a small neat
mould.
9.4.6 Glazing: All glazing work shall be carried out in conformity with BS:CP-
152. Glass will be fixed after first coat of paint or polish has been applied.
Glass shall be fixed with best quality putty, wood or steel moulding as
required. Glass shall be protected against damage. After inspection, any
labels and paint spots shall be removed from the glass and glass shall be
washed clean. Damaged or broken glass shall be removed and replaced by
the Contractor at his own expense.
9.4.7 Paneling: it shall be of well seasoned best quality required wood. Unless
otherwise indicated in BOQ or drawings, the planks shall be ¾” thick.
Deodar wood battens shall be screwed to hard wood plugs fixed in slab or
wall creosoted before fixing as specified. Deodar wood panels shall be
screwed to the Deodar wood under-frame as shown on the drawings.
Deodar wood beading shall be provided wherever indicated on the
drawings. Panels shall be so fixed that a uniform surface with equal gaps
or joints results in a pleasing appearance.
9.4.8 Wood Handrails: shall be of best quality well seasoned wood. Handrails
shall be accurately shaped to detail and made in as long sections as
possible. Joints shall be fastened with concealed handrail bolts. All
changes in direction shall be smooth, even, carved out of one solid piece.
Handrails shall be secured to metal railing with ¼” x 2” screws at 12”
centers.
9.4.9 Sub-frames for wall paneling, wood floors & cat-walks: They shall be
of best quality Deodar wood, of sizes as shown on drawings and securely
fixed in position using hard wood plugs, bolts etc. using enough number of
nails, screws etc. as specified and directed by the Client. The timber
60
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
9.5 PAINTING:
9.6 MEASUREMENTS:
Fixed wire-gauze and wire-gauze leaves shall not be measured for separate
payment.
61
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The rate and prices shall be full compensation for every thing furnished and done
for the work item installed/fixed complete in all respects, and as per these
specifications, drawings, instructions of the Client and Conditions of Contract. It
should be specifically noted that the rates are also inclusive of the following:
62
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION – 10
STEEL AND METAL WORK
10.1 CONFORMITY TO STANDARDS:
Unless otherwise specified all work carried out under this section shall conform to
British Standard-449 “The use of Structural Steel in Building” CP-113 and other
BS as applicable to the work. Aluminum work shall conform to BS-1476/HE-9
and ASTM-6063.
10.2 MATERIALS:
Steel Channels, Angle Iron, Rolled I Beams, Plates & Bars shall conform to
the applicable requirements of BS-15 “Mild Steel for General Structural
purposes”.
Steel Plates shall conform to the requirements of BS-1449 “Steel Plates Sheets
and Strips”.
Galvanizing: All fixing accessories for windows and doors where specified and
nuts, bolts, screws, hinges, stay pegs, Iron beadings, breadings, brackets, stays,
rests, etc. shall be hot-dipped galvanized as per BS-729 Part-I, “Hot dipped
Galvanized Coatings”.
Steel Bolts, Nuts, Washers: Bolts per BS-4190 to be strength grade 4.8 if Cold
Forged or 4.6 if Hot Forged and the Chemical composition shall be selected by
the manufacturer (except that the maximum Sulphur and Phosphorous content
shall not exceed 0.006 percent) to give the Mechanical properties.
Also if the steel is produced by an oxygen process, the Nitrogen content shall not
exceed 0.008%. The principal mechanical properties required for these grades of
steel are as follows:-
63
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Washers shall conform to BS-4320 and only Black Washers, unless otherwise
specified, made of mild steel shall be used. The bolts shall be supplied
subdivided by type and diameter, oil-protected on the threaded parts to prevent
oxidation and damage from impacts.
The Client reserves the right to inspect periodically the Contractor’s shop and take
samples in order to verify the mechanical resistance of the materials.
10.3 SAMPLES:
Samples of the materials used for the work under this section shall be submitted
and approval of the Client obtained and same type of material shall be used
throughout the work. If the Client require the material to be tested, this shall be
got done by the Contractor at his own cost from a Laboratory approved by the
Client.
64
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
All sections shall be hot rolled low carbon steel one piece sections with flanges
rolled integrally as per BS-990, flanges forming the weathering contacts as both
inside and outside points of closure. Composite steel sections made by welding
channels, angles and plates shall be accepted in lieu of one piece section only
when specifically called for or when shown on drawings. Such sections shall be
continuously welded in a staggered manner. Corners of frames shall be mitred,
solid welded and shall be finished flush and smooth on surfaces that will be
exposed after installation. All members shall be in one length without splices,
and shall be straightened so that they shall not be more than 1/16” from a straight
plane in either direction for the full length of members. Doors, windows shall be
installed plumb, level, in alignment and properly braced to prevent distortion.
These shall be erected in position using proper holdfasts or counter sunk bolts and
screws as shown on drawings and approved by the Client.
Hinges for windows shall be of steel or malleable iron with non-ferrous bushings
or washers. Two hinges and one locking handle in smooth finished solid bronze
per window shall be furnished but for window exceeding 5’ in height three hinges
and two point locking devices with steel connecting rods shall be furnished. Ten
inches long solid Bronze or moulded heavy gauge galvanized iron peg stay, one
for each openable panel, shall be provided. Pegstays and locking devices shall be
manufactured as per standard design approved by the Client and shall be secured
to windows with corrosion resisting bolts and screws. Metal glazing bead if
specified or shown on the drawings shall be galvanized and of minimum 18-SWG
thickness.
10.5 GLAZING:
Wire gauze shall be as specified in section “Carpentry, Joinery & Glazing”. Wire
gauze shall be stretched taut and fixed to the members with nuts and bolts or
screws with M.S. flat beading/moulding over it, as shown in drawings.
65
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Rolling shutters shall be of solid-front made of 22-gauge G.I. sheet strips. G.I.
sheet strips shall be 2.5” wide and shall be machine moulded. Covers & slits shall
be of approved make and design. Shutters shall be secured to structure by means
of holdfasts, bolts and nuts. The rolled top portion shall be encased in 1/8” thick
sheet casing. When installed, the shutters shall be capable of smooth and easy
operation and shall be provided with approved type of handles and eyes for
padlocks etc. They will be painted as per Section “Painting & Decorating”.
10.8 RAILING:
Iron railing shall be well formed to the shape, size and material shown on the
drawings with sharp lines, curves, angles and smooth surfaces. Balustrades shall
be formed with all turns and easings and shall be secured to the top rail at
intervals of 12” on centres or as directed. Balusters shall be set parallel to each
other, and the balusters and posts shall be anchored into stairs, curbs and slabs, etc
as directed. The space between the railing balusters or posts and the openings for
anchorage shall be solidly filled with molten lead, trimmed flush with the finished
floor, stairs or curb. Wall handrails shall be supported on rail brackets, securely
fastened to back plates fixed to walls.
Steel members shall be sound and free from cracks, scales, blisters, surface flaws,
laminations, cracked edges and other defects. The structures shall be shop
fabricated in accordance with drawings but assembled, welded, riveted or bolted
at site prior to being lifted in position. Assembly shall not be allowed on the false
work. All members shall be cut truly square so as to butt properly and splices and
joints shall be made only in such position as shown on drawings or as directed by
the Client. All field work or fabrication, riveting, bolting and welding shall be
carried out in workmanlike manner. Bending, straining or pounding with sledges
shall not be allowed during erection. The structure shall be given one coat of
specified lead primer. All connections and meeting surfaces of structural steel
work shall be covered with sufficient primer to ensure that it squeezes out around
riveting or bolting. The structure shall be anchored by bolts and bed plates
embedded in masonry or concrete. The shoe plates shall be fabricated alongwith,
and the slotted sides shall be correctly aligned and fixed according to the position
shown on the drawings.
66
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The grills shall be manufactured using M.S. flats in sizes and designs required and
fixed as shown on drawings. Painting shall be done as per Section “Painting &
Decorating”.
All sections shall be from high strength aluminum alloy, full sections being
extruded integrally having mechanical joints. PVC weather strip shall be used to
render joints between the walls and outer frame, between the moving panel frame
and receiving limb of the fixed frame etc. proof against dust and moisture.
The sliding panels shall have Nylon Rollers and corresponding rail for friction-
free operation. PVC glazing channel of approved design shall be used for glazing.
All the aluminum sections shall be anodized as per BS and shall have a special
smooth and durable shop finish of lacquer.
All other specifications as to being level, plumb, flush and butt with the walls
shall apply as given under “Steel Casement Windows, Ventilators etc”.
These shall be provided at selected openings as shown on the drawings. The sizes
shall vary according to the architectural requirements. All doors shall be center
opening and sliding sideways. The glazing shall not be less than ¼” thick which
shall be smoke tinted, reflecting and polished plate glass perfectly matching with
the glazing provided elsewhere in the works.
The door shall be supported in top and bottom rails and shall be provided with
antifriction bearings preferably hermetically sealed for long life. The mechanical
arrangement shall consist of a system of noiseless levers, steel ropes and guides
for moving the openable portion of door uniformly in forward and backward
67
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
directions. Rubber or PVC pads shall be provided to reduce any impact due to
erratic functioning of the mechanical system. The drives shall be provided by
means of reversible electric motor of appropriate capacity. The opening and
closing operation shall be controlled by means of electronic beam and floor
detectors. The controlling arrangement shall incorporate necessary contactors and
relays for operation of the motor.
The doors shall be provided with means of operating them manually both from
inside and outside in the event of power failure. The bidder shall submit with the
tender four sets of technical literature; detailed drawings and illustrated pamphlets
completely describing the system adopted by the manufacturer. Any deviation
from the above specifications shall be clearly mentioned.
10.13 MEASUREMENTS:
Unless given otherwise in BOQ, doors, windows, ventilators and the like shall be
measured by the superficial area. Structural steel work including bolts, nuts,
washers, shims, plates, flats, etc. shall be measured by weight.
Gates and Sliding Doors – area shall be the area of the leaves (one side only).
Rolling (Roll-up) Shutters shall be measured from the external faces of the
vertical guides (channels) for width and from the floor level to the top of the
cover-box for height.
HAND RAILS:
Wooden hand rail shall be measured and paid under section “Carpentry, Joinery
and Glazing”.
i. The balustrade (balusters, anchors, flats under hand rails, etc.) for central
railing of stairs shall be measured by area. Length shall be same as the
length of the hand rail; and the height shall be the height from the top of
the finished floor of landings upto the bottom of the pipe hand rail or upto
the top of the flat under the wood hand rail, as the case may be.
68
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
ii. Support System for stairs wall side railing, shall be measured by length
which shall be equal to the length of the hand rail supported.
The rates shall be full compensation for every thing required to be furnished and
done to complete the work item in all respects and fixed/installed in its place,
conforming to these specifications, BOQ, drawings, manufacturers’ printed
catalogues/instructions in case of special items, and conditions of Contract. Since
the rates are for work items complete in all respects, it is further clarified that the
rates shall also include the following:
10.15.1 SCOPE:
69
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
10.15.2 MATERIALS:
10.15.3 WORKMANSHIP:
70
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
through material not over ½” thick, except where required for close
tolerance or barrel bolts.
All matching holes for rivets and black bolts shall register with
each other so that a gauge 1/16” less in diameter than the diameter
of hole will pass freely through the assembled members in a
direction at right angles to such members. Finished holes shall be
not more than 1/16” in diameter larger than the diameter of the
rivet or black bolt passing through them, unless otherwise required
by the Consultant.
Riveted members shall have all parts firmly drawn and held
together before and during riveting, and special care shall be taken
in this respect for all single riveted connections. For multiple
riveted connections, a service bolt shall be provided in every third
or fourth hole.
71
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
All loose, burned or otherwise defective rivets shall be cut out and
replaced before the structure is loaded, and special care shall be
taken to inspect all single-riveted connections.
The threaded portion of each bolt shall project through the nut at-
least one thread.
f) Slab Bases and Caps: Slab bases and slab caps, except when cut
from material with true surfaces, shall be accurately machined over
the bearing surfaces, and shall be in effective contact with the end
of the stanchion. A bearing face which is to be grouted direct into
a foundation need not be machined if such face is true and parallel
to the upper face.
72
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
h) Shop Painting: All surfaces shall be painted with one coat of red
oxide primer unless otherwise required. The surface to be painted
shall be cleaned to remove all loose scale and loose rust. Shop
contact surfaces shall be prime painted unless specified to the
contrary. They shall be brought together while the paint is still
wet.
Welds & adjacent parent metal shall not be painted prior to de-
slagging, inspection and approval.
73
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
with the same type of paint as shop primer paint. In the galvanized
steel pipe railing all welds shall be ground smooth and painted
with two coats of grey zinc base paint of approved quality. The
site painting shall not be done in rainy weather or when the
humidity is such as to cause condensation on the surfaces to be
painted.
74
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION – 11
PAINTING AND DECORATING
11.1 SCOPE:
All work under this section shall conform to BS-CP-231 as applicable and the
specifications of this section “Brushes for Painting” shall conform to BS-2092.
Holes and irregularities in the surfaces shall be repaired with lime putty
and the surface shall be allowed to dry before white-wash is applied. All
greasy spots shall be given a coat of rice, water and sand. Surfaces
discolored by smoke shall be washed with a mixture of wood ashes and
water or yellow earth before being white-washed.
Cement concrete surface shall be scraped off with a wire brush to remove
greasy patches, if any, and washed with soap-suds. The surface shall be
rinsed with water to remove traces of alkali. A coat of Sodium Silicate
and water in the ratio 1:5 shall be given on the entire concrete surface to
avoid future scaling or flaking off. Half to one part (by weight) of tallow
in small lumps shall be added to 16 parts of quick lime, slaking it with
only just sufficient water to form a thick paste, stirring occasionally and
allowing it to stand till it cools down. The paste shall then be thinned
down to required consistency by adding water, shall be strained and
applied to surface.
75
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Whitewash shall be prepared from pure fat lime brought to the site of
work in an unslaked condition and in order to slake the lime, water shall
be added to it in a tub till the mixture attains the consistency of cream, and
is allowed to rest for 24 to 48 hours. It shall then be strained through
coarse cloth and 4 ounces of gum or rice dissolved in hot water shall be
added to each cubic foot of it.
11.3.4 Application:
Whitewash shall be applied with a brush. Each coat shall consist of four
strikes, one in each direction. Each coat of whitewash shall be allowed to
dry and be inspected by the Client or their authorized subordinate. The
next coat shall not be applied unless the previous one has been approved
by either of them. A dry coat must not show any sign of cracking, nor
must whitewash come off readily on fingers when rubbed.
Three coats of whitewash shall be sufficient. In case the surface is still not
in an acceptable condition, the Contractor shall provide additional coats at
no extra cost to the Client.
All floor, doors, windows and other articles etc., shall be properly
protected from whitewash and cleaned after completion of work.
11.3.7 Measurement:
All the work under this section shall be measured by actual area over
which treatment is applied. Deduction shall be made for the openings of
any size from the two sides, unit of measurement shall be % Sft or m2 as
given in BOQ.
76
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The rates shall be full compensation for everything furnished and done to
complete the whitewash in all respects including provision, erection and
removal of scaffolds, ladders, etc, as per drawings, these specifications
and conditions of contract.
Payment shall be made under the relevant BOQ item for “Whitewash on
new surfaces”.
11.4.4 Application:
The surface shall be given a coat of whitewash prior to color wash. Each
coat of color-wash shall be allowed to dry and shall be inspected by the
Client. The next coat shall not be applied unless the previous one has
been approved by them. The first coat of white wash and the color- wash
coats shall be applied with brush. Each coat shall consist of four strokes,
one in each direction. The completed wash shall be of uniform color, free
from blots, lines or cut shades and shall present a smooth regular surface
which shall neither crack nor come off readily on fingers when rubbed.
Each room shall be finished in one operation and work shall not start in a
room so late that it cannot be finished the same day.
77
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
One coat of white wash and two coats of color wash shall be sufficient. If
the surface is still not in an acceptable condition, the Contractor shall
apply additional coats of color wash at no extra cost to the Client.
11.4.7 Measurement:
Payment shall be made under the relevant BOQ item for: “Color-Wash
on new Surfaces”.
11.5.1 Materials:
11.5.2 Storage:
Water paints shall not be applied earlier than 12 months, unless plastered
surfaces are primed per printed instructions of the manufacturers of the
paints. Water paints shall not be applied in damp weather nor when it is
excessively hot and dry.
78
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Surfaces shall be cleaned of all loose, foreign materials, grease, oil and
dust. Efflorescent salts shall be allowed to diffuse to the surface until
white residue stops appearing on the surfaces. All loose powder shall be
removed by sweeping with a brush or using a rubbing stone and sand
paper. All surfaces shall be perfectly smooth, dry and clean. All holes
shall be filled with gypsum which shall be allowed to set hard.
11.5.5 Priming:
11.5.6 Filling:
Any minor interior filling of the surface shall be carried out at this stage.
Putty for filling shall be made by mixing 4 parts of good quality chalk
(and one part of Zinc Oxide powder if recommended by the printer
manufacturer) with the primer till a smooth knifing paste is formed.
Filling shall be allowed to dry over night. No filling shall be done on
exterior surfaces.
11.5.7 Mixing:
11.5.8 Application:
Water paints shall be applied quickly and boldly leaving no dry edge. The
brushes shall be dipped in paint and stroked cross-wise on the wall, then
immediately stroked up and down and stopped. The brush shall be loaded
fairly generously and full even coat shall be applied without brushing out
too far. These four strokes shall constitute one coat.
79
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
11.5.10 Colour:
11.5.12 Measurement:
11.6.1 Materials:
80
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
11.6.2 Storage:
The surfaces shall be clean, dry and sound. These shall be cleaned of all
loose, foreign matters, and greasy spots. The surfaces shall not be too
smooth and glazy. Cement paints shall not be applied on gypsum plaster,
metal and wood.
11.6.4 Mixing:
Where the backing is smooth or dense (including concrete and old cement
paint surfaces), is of dark color or where the work is carried out in an
exposed position, sand shall be added to the paint as under:
11.6.5 Weather:
81
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
11.6.6 Application:
The surface shall be wetted down with clean water before application of
paint. Paint shall be applied by means of brush after the soaking shine is
over. The first coat shall be well scrubbed into the surface and allowed to
harden (minimum 24 hours in warm climates and longer in cold climates)
before the second coat is applied. The brushes shall be washed in clean
water frequently.
11.6.7 Curing:
After the first coat hardens, the surface shall be soaked evenly, four or five
times and the second coat shall be applied after leaving for at least over
night. Subsequent coat shall not be applied unless previous coat has been
cured. In dry and hot climates, it is necessary that each subsequent coat
shall not be applied unless the surface is soaked evenly with water
(preferably with hose pipe).
Three coats shall be sufficient to produce the desired result, failing which
additional costs shall be applied by the Contractor at no extra cost to the
Client.
11.6.10 Protection and Cleaning: the Provisions of Clause 11.3.6 shall apply.
11.6.12 Payment and Rates: The Provisions of Clause 11.3.8 shall be applicable.
11.6.13 Pay Item: Payment shall be made under the relevant BOQ item for:
11.7.1 Scope:
All portions of wood built into or against masonry, concrete and plaster, or
used as sub-frames for railing, paneling, doors etc. and all other wood
82
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
11.7.3 Application:
83
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
11.8.1 Materials:
Primer shall be “Paint Priming Red and White Lead Brushing” of Paintex
Ltd., or approved equal.
Knotting: After rubbing, all knots in the wood shall be killed or covered
with:
OR
c) A preparation of red lead and glue size in equal weight applied hot.
Knots in Deodar or other resinous wood shall be painted over with
hot lime. This paint shall be scraped off after 24 hours, the knots
primed with red lead and glue laid hot. Then one coat of knotting
varnish shall be applied.
84
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Rubbing: After knotting, the surface shall be rubbed again with pumice
stone, or fine sand paper before the priming cost is applied.
11.8.3 Priming:
Before fixing the wood work in position, and on the smooth, moisture free
wood surface:
Two coats of the primer specified in Clause 11.8.1 shall be applied. The
primer shall be thinned with approved quality of mineral spirit, if required.
The primed surface shall be allowed to dry hard for 24 hours before
scuffing and over coating.
11.8.4 Undercoating:
All holes, cracks, gapping joints and other defects shall be stopped with an
approved putty. The surface shall then be allowed to dry for 6 to 8 hours.
11.8.6 Finishing:
Two coats of the specified enamel paint shall then be applied, allowing 16
hours between coats. The surface shall be sand papered before applying
each coat. The paint may be thinned to improve brushing quality,
particularly during summer. Upto 10% mineral spirit may be added if
brushes are used; or upto 25% white spirit may be added if paint is applied
by spraying.
85
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Two coats of primer, one undercoat and two finish coats, shall be
sufficient to produce the required finish, failing which the Contractor shall
apply additional finish coats to give the desired results at no extra cost to
the Client.
Painting shall not be measured separately for direct payment, and the rates
and prices under section “Carpentry, Joinery and Glazing” or any other
section for the wood work items shall be inclusive of painting as per
Clause 11.8.
Measurements:
86
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Note: In the case of chowkat having two rebates, one for wooden door
and the other for wire gauze shutter, the surface area of the frame
(chowkat) shall be included in the measurement of only one door.
11.8.10 Payment and Rates shall be full compensation for every thing furnished
and done to complete painting in all respects as per these specifications,
drawings and conditions of contract, including also providing, erecting
and removal of ladders, scaffoldings, etc.
11.8.11 Pay items: Payment shall be made under the relevant BOQ item for:
11.9.1 Material:
New wood work to be polished shall be finished smooth with the plane
making sure that no plane marks are left after finishing.
The surface shall be made perfectly smooth by rubbing it with sand paper
or pumice stone.
It shall then be stopped and rubbed perfectly smooth first with medium
grained sand paper and then with fine sand paper. The final rubbing shall
be done with sand paper which has been slightly moistened with linseed
oil and rubbed for a few seconds.
87
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
11.9.3 Application:
Wax polish shall be applied with a clean cloth pad and rubbed
continuously for at least half an hour.
When the surface is quite dry, the second coat shall be applied in the same
manner and rubbed continuously for one hour, or till the surface has dried.
The final coat shall then be applied and rubbed for two hours (more if
necessary), till the surface has assumed a uniform gloss and is quite dry,
showing no signs of stickiness when touched. The final polish depends
largely on the amount of rubbing which shall be done continuously with
uniform pressure and with frequent change in direction.
11.9.4 Protection and Cleaning:
Provisions of Clause 11.8.9 for painting, shall apply here. Payment for
wax polishing, where a pay item has been specifically given in BOQ, shall
be made as under:
11.10.1 Material:
88
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
11.10.4 Filling:
After the surface has been prepared it shall be painted with a filler
composed of 5-lbs of whiting mixed with 1/3 of a gallon of methylated
spirit and then rubbed with sand paper. Alternatively, a piece of rag
moistened with linseed oil shall be rubbed on the surface and then Plaster
of Paris, Red Ochre (sufficient to tint it) and linseed oil shall be mixed
together to form a stiff paste which shall be applied sparingly and rubbed
hard on the surface to fill up the pores of the wood.
11.10.5 Application:
A thin coat of polish shall then be rubbed with sand paper a few hours
later, and then second coat shall be applied. The surfaces shall be rubbed
again and third coat applied. To finish off, the surface shall be rubbed
lightly and quickly with a circular motion by means of a piece of a flannel
rolled into the form of a rubber, covered with a piece of rag slightly damp
with methylated spirit. If the rage sticks, the surface shall be touched with
linseed oil.
The provisions of Clause 11.8.9 for “Painting” shall apply here. Payment
for French Polishing, where a pay item has specifically been given in
BOQ, shall be as under:
New Wood work to be varnished shall be finished smooth with the plane
making sure that no marks are visible on the finished surface. It shall be
rubbed perfectly smooth with sand paper or pumice stone.
89
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Stopping: The surface of the wood shall be then stopped, with hot weak
glue size (1-lb of glue making about 1-gallon of size) so as to close up the
holes. The surface when it dries up shall be again thoroughly sand
papered. After rubbing the surfaces another coat of the same glue size
shall be applied cold.
If the wood work is to be stained, the staining colour shall be mixed with
second coat of size which shall be applied regularly, evenly and quickly
keeping the colour on the flow.
If the wood work is of an oily nature, a little “Multani Mitti” and ochre
shall be added to the first coat of size (otherwise varnish would not dry
readily).
The sized wood shall then be rubbed with sand paper leaving the colour
even and rubbing with the grain.
11.11.3 Application:
Varnish shall then be applied in very thin coats with a special fine-haired
varnishing brush and not with an ordinary paint brush. Unless otherwise
specified, the best Copal varnish shall be used. If more than one coat have
been specified the first coat shall be rubbed with fine sand paper. Other
coats shall be applied as directed by the Client.
The provisions of Clause 11.8.9 for Painting shall apply. Where a pay
item has been given in BOQ, payment shall be made for varnishing as
under:
11.12.1 Material:
90
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
11.12.2 Weather:
Painting shall not be done in damp, wet, stormy or extremely hot weather.
Too quick drying in the baking heat of the sun shall be avoided.
The surface shall be thoroughly cleaned of all rust, scale and foreign
matter by means of steel scrapers, chisels, steel wire brush, sand paper,
sand blasting or any other suitable mechanical means as may be required
by the Client, till the bright shining surface of the iron appears. The
surface shall then be cleaned with dry cotton waste and the primer applied
immediately especially if the weather is damp, to avoid rusting.
11.12.4 Pretreatment/Phosphating:
91
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
11.12.6 Filling:
11.12.7 Finishing:
The provisions of Clause 11.8.9 shall apply. When a pay item for painting
iron and steel surfaces has been given in BOQ, payment shall be made as
under:-
Iron and steel shall be blasted clean. When this is not possible, all dirt,
grease and chemical contamination shall be removed, followed by
92
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
chipping, scraping and wire brushing to remove all loose mill scale and
surface rust.
One coat of “Kemobel Metal Primer” (or approved equal) over cleaned
iron and steel surfaces or one coat of “Kemobel Concrete Primer” (or
approved equal) over cleaned surfaces of concrete, plaster, masonry and
wood shall be applied. The primer shall be allowed to dry for 8-16 hours.
Then two coats of “Kemobel” finish (or approved equal) shall be applied
by brush or spray.
Pay Items: Payment shall be made under the relevant BOQ item for:
“Kemobel Chemical Resistant Finish Over the specified new surfaces”.
11.13.2 “Kemobel Chlorinated Rubber Thick Coating” Over Iron, Mild Steel
and Concrete Surfaces:
Then one or two coats (as indicated in the pay item) shall be “Kemobel
Chlorinated Rubber Thick Coating” (or approved equal) shall be applied
after allowing the primer to dry for 8-16 hours. Then two coats of
“Kemobel” finish shall be applied by brush or spray.
Pay Items: Payment shall be made under the relevant BOQ item for:
93
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Structural and heavy steel shall be grit, shot or sand blasted to SA2.5 and
other steel degreased and derusted. Other contaminants shall be removed
with abrasive paper and solvent.
Priming: Over grit, shot or sand blasted surfaces, one coat of “Permobel
Zinc Rick Primer” of Paintex Ltd (or approved equal) shall be applied.
Nine (9) parts by volume of Primer Component “A” shall be mixed with
one part component “B” and the mixture allowed to stand for 10 minutes
before use. The mixture must be used within 36 hours. Over surfaces not
grit, shot or sand blasted, one coat of “Permobel Epoxy Red Oxide Zinc
Chromate Primer” of Paintex Ltd (or approved equal) shall be applied, by
mixing 2 parts component “A” with one part component “B” before use.
Primers shall allowed to cure for 12-18 hours before application of finish.
Finishing: Two (unless indicated three in the pay item) unthinned coats
of “Permobel Epoxy Finish” of ICI Ltd (or approved equal) shall be
applied over the primed surfaces, allowing for overnight drying between
coats. “Permobel Thinner” of Paintex Ltd (or approved equal) shall be
used to thin the primer and finishes and to clean the brushes.
Pay Items: Payment shall be made under the relevant BOQ items for:
The surface shall be ensured to be sound, firmly adhering and free from
dirt, grease, etc. Four parts of base shall be mixed thoroughly with one
part hardener by volume., “Epoxy Thinner” of Paintex Ltd (or approved
equal) shall be used, if required for brushing or spraying. Two coats of
“Epoxy” of Paintex Ltd (or approved equal) shall be applied, allowing 12-
94
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
16 hours for drying between coats. 5-7 days shall be allowed for full
curing before use, especially in case of floor.
Pay Items: Payment shall be made under the relevant BOQ items for:
11.13.5 Painting with Coaltar Epoxy, over steel, hard concrete and hard
cement renderings:
Steel surface shall be sand blasted and cleaned of all traces of dust
and grit, then Paintex Coaltar Epoxy (or approved equal) shall be
applied with 4-6 hours of blasting. In cases where whole of the
area (as in case of tanks) cannot be blasted for painting within 4-6
hours, small area be blasted, cleaned and coated with “Permobel
Protective Primer” of Paintex Ltd (or approved equal) and left for
painting. Two coats of Coaltar Epoxy shall then be applied
allowing 12-16 hours (not more than 24 hours in any case)
between the two coats.
The surface shall be dry right through. All loose and friable
material shall be removed by thorough sand papering. All minor
cracks and holes shall be made good with Epoxy Sand Mortar (or
Paintex Ltd or approved equal) which shall be allowed to cure for
12-16 hours before painting. Two coats of Coaltar Epoxy) of
Paintex Ltd (or approved equal) shall then be applied, allowing 12-
16 horus (not more than 24 hours in any case) between two coats.
d) Pay Items: Payment shall be made under the relevant BOQ items
for:
95
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
All dirt, rust, oil, greasy spots and grime shall be removed. Metal surfaces
shall be cleaned by wirebrushing and scraping. The surface shall be wiped
clean with a solvent soaked rag. One coat of appropriate Dulux Primer (or
approved equal) shall then be applied.
Pay Items: Payment shall be made under the relevant BOQ items
for:
96
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION – W-1
EXCAVATION AND BACKFILLING FOR
WATER SUPLY & SEWERAGE SYSTEMS
(EXTERNAL)
The work covered by this section of the specifications consists of furnishing all
plant, labour, equipment, appliances and materials required, in performing all
operations in connection with excavation, trenching and backfilling for water
lines, sewer lines, drainage structures and appurtenances, in strict accordance with
this section of the specification and the applicable drawings, and subject to the
terms and conditions of the Contract.
The site of all excavation shall cleared of all shrubs, plants, bushes, large roots,
rubbish and other surface materials. All such material shall be removed and
disposed of, at no extra cost, in a manner satisfactory to the Client. All trees and
shrubbery that are designated by the Consultant to remain shall be adequately
protected and preserved in an approved manner.
W1.3 EXCAVATION
W1.3.1 General:
97
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
W.1.3.2.1 General:
98
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
99
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
All earth excavation under this contract, which is not included under the
classification of “Earth Excavation in Trenches” shall be classified and
paid for as “Earth Excavation for Structures” and shall also include
removal of rubbish, debris and other surface materials or any other form of
accumulation at no extra cost to the Client.
When foundation level is reached, the Client will inspect the exposed
ground and give directions as to what further excavation, if any, they
consider necessary. The excavation shall be done in such a manner as to
ensure that the work rests on a solid and perfectly clean foundation.
Where excavation is to be covered subsequently by permanent
construction, the Contractor shall, immediately after exposing the
specified satisfactory foundation, proceed with the construction on that
foundation. If the Contractor allows any portion of such foundation to
deteriorate due to exposure, he shall make good the foundations at no
extra cost to the Client and to the satisfaction of the Client.
All sewers shall be constructed and laid with a true grade and in straight
lines between manholes or curves, as shown on the drawings. The sewers
shall be laid by the aid of suitable boning rods and sight rail; the latter
100
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The Contractor shall also provide at his own cost all labour and material
necessary to enable the Client or their staff to check the levels and
dimensions of the work wherever the Client or their staff requires him to
do so. All sight rails and boning rods shall be of well seasoned wood of
ample size and strength. The sight rails and boning rods shall be suitably
and accurately planed and not warped. No defective or damaged sight
rails or boning rods shall be allowed. The sight rails shall be secured to
the posts by heavy wrought steel clamps to the approval of the Client and
in such a manner that they shall be fixed immovably in the correct line and
level.
All boning rods and sight rails shall have the centre line accurately marked
thereon by a thin saw cut and shall be painted black and white to the
requirements of the Client.
All boning rods shall be suitably shod with iron shoes. At least four
separate sight rails shall always be maintained to correct levels and
alignment along the centre line of sewer at every place where construction
work is proceeding, and the alignment and level of the sight rails shall be
checked by level and line at least twice every day to ensure that no
disturbance or interference of the alignment and level has taken place.
Wherever required, the Contractor shall erect and maintain such additional
sight rails as the Client shall direct. The Contractor shall at all times see
that his workmen or other unauthorized persons are not allowed,
accidentally or otherwise, to tamper or interface with sight rails or other
alignment or level marks.
101
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
As part of the work under the excavation items, the Contractor shall shore
up all buildings, walls and other structures, the stability of which is liable
to be endangered by the execution of the work, and be fully responsible
for all damages to persons or property resulting from any accident to any
such buildings, walls and other structures.
As part of the work under the excavation items, and at no extra cost to the
Client, the Contractor shall build all drains and do ditching, pumping,
bailing and all other work necessary to keep the excavation clear of
sewerage and extraneous water during the progress of the work and until
the finished work is safe from injury. The contractor shall provide all
necessary pumping equipment for the dewatering work, as well as
operating personnel, POL, power, etc. all at no extra cost to the Client.
All water pumped or drained from the work shall be disposed of in a
manner satisfactory to the Client. Necessary precautions against flooding
102
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
shall be taken. Dewatering of subsoil water, however, will not form a part
of dewatering of excavation and shall be paid separately.
The Client may order, in writing, any or all shoring and sheet piling to be
left in place for purpose of preventing injury to the structures, other
property or persons, whether such sheeting was shown sheeting shall be
cut off at the elevation ordered, in any case at least 18” below the final
ground surface. The sheeting remaining in place as ordered by the
Consultant shall be driven tight and shall be paid as an item separate from
excavation.
The Contractor shall take special care of the existing sub-surface facilities
likely to be encountered during the execution of work which require
special precaution for their protection, such as sewers drain pipes, water
mains, conduits, electric cables, communication cables and the
foundations of adjacent structures. The Contractor shall be responsible for
the damage to any such facility and shall repair the same at his expense
whether or not this facility has been shown on the drawings.
W1.4.1 General:
103
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
104
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
105
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The Consultant will make tests using the calibrated sand cone
method to determine the density of soil in place. If soil in place
fails to meet the specified degree of compaction, the areas
represented by the failing tests shall be removed, replaced and
compacted to the specified density in the manner directed by the
Client at no additional cost to the Client. Equipment for testing
shall be provided by the Contractor at no additional cost to the
Client.
106
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
No earth shall be taken from any existing ponds or depressions or any point
contiguous thereto, and all earth borrow shall be free from stones, clods, trash,
lumber, debris, sewage, slush, stumps, roots and others objectionable and
detrimental organic matter.
Earth fill brought from outside shall be sandy clay having approximately the
following constituents: Sand 50 to 70%, clay 30 to 50%, Silt upto 20%.
The rate agreed for earth borrow shall be inclusive of obtaining, loading, haulage,
placing, compacting, dressing to the designed section and requirements of the
project Backfilling and compaction shall be done as per Clause W1.4.
W1.6.1 General:
W1.6.2 Unless given otherwise in BOQ, payment shall be made under the
following items:
107
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
108
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Pay Item:
109
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
110
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION - W – 2
The materials used and workmanship shall be highest quality and grade and
unless otherwise specified shall conform to the relevant British Standards and
Code of Practice CP-301 (1965) “Water Supply, CP-304 (1968) “Sanitary
Pipework above Ground”, CP-405 (1952) “Sanitary Appliance, CP-301 (1950)
“Building Drainage”, and CP-303 (1952) “Surface Water and Subsoil Drainage”,
and the relevant ASTM Specifications for details and work indicated on the
drawings or Bill of quantities and as directed by the Client.
W2.2 MATERIALS:
Fine and Coarse Aggregate shall be sand, gravel or crushed stone conforming to
BS-882 (1954) “Concrete Aggregates from Natural Sources’.
Water shall be clear, fresh, free from impurities, excessive salt content and
deleterious matter.
Reinforced Concrete pipes and collars etc. upto 9” dia shall conform to BS-556
“A” class, above 9” dia to ASTM designation C-76, Class II, Wall “B”, unless
otherwise indicated. These shall be cast spun and shall have reinforcing steel and
core thickness in strict conformity with the above mentioned specifications. The
inside surface shall be perfectly smooth and liquid resisting and completely
hardened before use. It will be at the option of the Contractor to use spigot and
socket or tongue and groove joint pipes.
Cast Iron Pipes and fittings shall conform to BS-416 (1967) “Cast Iron Spigot
and Socket Soil, Waste and Ventilating Pipes and Fittings for use above ground”
and shall be of following grades, weights and metal thickness:
Pipe and fittings for use underground shall conform to BS-437 “Cast Iron Spigot
and Socket Drain Pipes”.
Pipes and Fittings shall conform to BS-416 and to BS-1130 for metal thickness
and dimensions.
The pipes and fittings shall be coated with bitumen from inside and outside, and
coating, shall be hard enough not to flow at a temperature of 145 deg. F.
Jointing and Packing Materials: Lead shall be sound, free from inclusions and
shall be of the best quality available in the market. The packing material shall be
of pure jute, hemp or hempen yarn. The mortar used for caulking joints shall be
1:2 cement sand mortar with minimum water added to just wet all particles of the
cement and sand dry mix.
Galvanized Iron Pipes, and Fittings: shall be of the best approved quality,
locally manufactured, and shall conform to BS-1387 (1967) “Steel Tubes and
Tubulars (medium)” and to other relevant British Standards as applicable,
galvanized in conformity with BS-729 Part-I “Hot-dip galvanized coatings”.
All G.I. pipes shall conform to British Standard Specifications and shall have
threads suitable to be jointed with G.I. pipes.
Before being buried in trenches, all G.I. pipes and fittings shall be coated with
Walis Dove’s Bitumastic solution. The solution shall be applied after heating the
same to appropriate temperature and by dipping the G.I. pipes and fittings into the
solution whilst it is in a molten state. The dipping shall be done 3 times, each
time the pipe or fitting shall be allowed to cool to room temperature before it is
dipped into solution. The ends of pipes/fittings shall be plugged before dipping
into solution.
112
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Valves: Sluice valves shall conform to BS-1218 “Sluice Valves for Water Works
Purposes”.
Gate valves shall conform to BS-3464 “Cast Iron Gate Valves for general
purposes” and to BS-1952 “Copper alloy gate valves for general purposes” as
applicable.
Fire Hydrants: shall conform to BS-750 and shall be of screwdown streamline
Pattern. Body shall be best quality close grained grey cast iron with spindle of
Manganese-Bronze having tensile strength of not less than 28 tons per Sq.in,
machined from solid rolled bars. The seats of valves and other gun metal parts
shall be of best quality gun-metal of Brinell Hardness No. 80. The direction of
closing shall be by clock-wise rotation and outlet shall have screwed joint for
accommodating 2.5” dia hose connection. Inlet flanges of hydrants shall be
suitable, for jointing with flanges of hydrant bends and Tees. All fire hydrants
shall be coated with high quality Bitumastic paint to give a uniform protective
coating on Cast Iron.
Surface Boxes for Sluice Valves & Fire Hydrants shall conform to British
Standard Specifications and these shall be of the sizes specified in the following:
They shall be made of close grained best quality grey castiron. All surface boxes
shall be provided with hinged flaps and locking arrangement. Duplicate keys of
locks shall be supplied with each Box before being sent out of factory.
Cast Iron Trap, Manhole Frame and Cover, Gully Traps, Gratings and
Flushing Cisterns shall be cast from a mixture of cast iron scrap and suitable
grade of Pig Iron, and resultant metal shall be of strong grey structure, free from
chips, air bubbles and sand holes & shall be smooth and even both inside and
outside.
Cement Concrete Gully Traps shall be of best and approved quality and the
water seal shall not be less than 2.1/2” deep.
113
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Ceramic Lavatory Basins shall conform to BS-1188 and shall be of design, type,
make and colour as specified. W.Cs shall conform to BS-1213 “Ceramic
Washdown W.C. pans” or as specified, type, make and colour as aproved.
Manhole Step Iron shall be of solid round section with their tails flattened.
Hangers, Supports and Anchors for fixing pipes to wall and ceilings shall be of
approved design consistent with good engineering practice and shall be mild steel
painted with bitumastic enamel paint, or the paint of the same quality as for the
pipes supported by these hanger supports or anchors or any approved rust proof
paint.
Pipe Sleeves for passage of pipes through masonry, RCC walls or floor slabs shall
be of asbestos cement or 16-gauge black steel. Diameter of pipe sleeve shall be
1” larger than the outside dia of the pipe for which it is used.
All materials, fittings, fixtures etc. shall be approved by the Client. No substitute
shall be accepted in place of the specific types or brands provided for in the Bill
of Quantities unless approved.
The Contractor shall carefully investigate the structural and finish conditions
affecting all his work and shall arrange his work accordingly, furnishing such
fittings and accessories as may be required, to meet site conditions with the
approval of the Client.
Pipes and accessories shall be carefully examined before being laid and defective
of damaged pipes shall not be used. The pipes shall be brushed clean inside and
outside to remove any soil or foreign matter that may have accumulated on inside
of the sockets and outside of spigots, before being lowered into the trench, and
shall be kept clean during laying operation by plugging or other approved method.
The bottom of the trench shall be shaped to give substantially uniform
circumferential support to the lower fourth of each pipe. Pipe laying shall
proceed upgrade with the spigot ends of the bell and spigot pipe pointing in the
direction of flow. Each pipe shall be laid true to line and grade and in such
manner as to form close concentric joint with the adjoining pipe.
If the width of the trench at the pipe exceeds the necessary, due to any reason
other than under direction from Client, the Contractor shall install at no additional
cost to the Client, such concrete cradling, pipe encasement or other bedding as
may be required to satisfactorily support the added load of the backfill. Trenches
114
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
shall be kept free from water until the pipe jointing material has set, and pipe shall
not be laid when the condition of the trench or the weather condition is unsuitable
for such work. At times when work is not in progress, open ends of pipe and
fittings shall be securely and satisfactorily closed so that no trench water, earth or
other substance will enter the pipe and fittings.
As the work progresses, the interior of the sewer shall be cleaned of all dirt and
superfluous materials of every description. Where cleaning after laying is
difficult because of small pipe size, a suitable swab or drag shall be kept in the
pipe and pulled forward past each joint immediately after the jointing has been
completed.
Where sewers cross above water line, the sewer pipe for a distance of 10’ each
side of the crossing shall be of cast iron steel or other approved pressure pipe and
with no joint closer than 3’ to the crossing or shall be fully encased in concrete of
min. 6” thickness.
The jointing of pipes with collars shall be done first with spun yarn rope (dipped
in hot Asphalt composition) fitting in between the ends of pipes and pressed
together. The dia of rope shall not exceed ¾” or as directed by the Client. The
collar shall then be brought in the middle of the joint. Wooden wedges shall be
placed at two or three places around the pipe so that the collar may have uniform
gap all round the pipe for pressing pipes together. At a time five or six pipes shall
be jointed together. After putting bitumen soaked hemp rope, suitable jacks and
wedges or any other approved method shall be used. The inside of the collar and
outside portion of the pipe shall be cleaned with brush, cement sand mortar of 1:2
ratio applied and then the pipes inserted from both ends of the collar. The mortar
containing as little quantity of water as possible shall be carefully inserted by
hand into the joints and tightly pressed with caulking tool. The mortar shall be
finished off on the outside at an angle of 45 deg. The wooden wedges shall be
carefully removed and mortar filled in the cavity before finishing. The joints shall
be protected from weather and maintained wet for at least ten days and shall not
be covered with backfill until the joints have been tested and approved.
For jointing of pipes with spigot and socket joints, the first pipe shall be bedded
with the socket end upstream. The interior surface of the socket shall be carefully
cleaned with a wet brush and its lower portion filled with mortar to such a depth
as to bring together the inner surfaces of the abutting pipes flush and even. All
further joints shall be made in this manner. The remaining of the socket joints
shall be filled in with mortar and well pressed with the help of caulking tool. The
mortar shall be finished smooth on the outside at an angle of 45 deg. The joints
shall be protected and cured as for collar joints.
115
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The pipes shall run exposed or embedded in walls and floors as specified or
shown on drawings. Where embedding in walls or floors is required, the
necessary instructions and route of pipe work shall be approved by the Client.
Pipes running exposed on walls and ceiling shall be properly clamped with
hangers, supports and clamps. For passage of pipes through masonry wall and
RCC beams and slab and walls, pipe sleeves shall be embedded and properly
caulked and water proofed.
Horizontal soil and waste pipes unless otherwise specified shall be given a grade
of ¼” per ft. and 1/8” per ft. respectively.
All main vertical soil stacks shall extend full size to above the roof line, except
where otherwise indicated. The part of the soil stack carried up as vent pipe shall
not have any bend or angle except when unavoidable, in which case the angle
shall be as obtuse as possible. The vent stack shall joint the soil stack at a point
not less than 3’ above the highest connection to the soil stack. Horizontal waste
lines receiving the discharge from two or more fixtures on the first floor shall be
provided with end vents, unless separate venting of fixtures is called for. Changes
in pipe size of soil, waste and drain lines shall be made with reducing fittings or
recessed reducers. All changes in direction shall be made by the appropriate use
of 45 deg. Tees, long or short sweep 1/4 to 1/16 bends, etc. or equivalent fittings
as approved. Single and double sanitary tees and quarter bends may be used in
drainage lines only where the direction of flow is from horizontal to vertical.
Short sweep not less than 3” in dia may be used where the change in direction of
flow is either in plan or from vertical to horizontal and may be used for making
necessary offsets between the ceiling and the next floor above. The use of short
sweep bends or fittings, where deemed necessary because of installation
conditions, shall be subject to the approval of the Client.
The Contractor shall provide offsets in the piping where required or directed by
the Client to avoid interference with other work, or to increase the head-room
under piping or to improve the appearance of the pipe work. Piping shall be
installed in such a manner that will permit freedom of movement during
expansion & contraction without causing the pipes to be wrapped and adequately
insulated against noise transmission through pipe-work in habitable rooms. All
piping shall be installed in such a manner as to prevent delay or interference with
the work of others working in the same area. All openings in pipes shall be kept
closed during construction work with plugs. Slip joints shall be permitted only in
trap seals or on the inlet side of the traps. Tucker or hub drainage fittings shall be
116
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
used for matting union connections wherever practicable. The use of long screws
and bushings is prohibited.
Clean Outs shall be of the same size as the pipe except the cleanout lugs larger
than 4” will not be required. Cleanouts installed in connection with cast iron
spigot and socket pipe shall consist of a long sweep ¼ bend or one or two 1/8
bends extended to an easily accessible place, or where indicated on the drawings.
An extra-heavy cast-brass ferrule with counter-sunk trap screw cover shall be
caulked into the hub of the fitting and shall be flush with the floor. Where
cleanouts in connection with threaded pipe are indicated and are accessible they
shall be cast iron drainage T-pattern 90 deg. Branch fittings with extra-heavy
brass screws plugs of the same size as the pipe upto and including 4”. Test tees
with cast iron cleanout plugs shall be installed at the foot of all soil, waste and
drain stacks and on each building drain outside the building. In addition,
cleanouts shall be provided at all changes of direction in excess of 45 deg. And at
distance not exceeding 50’ in horizontal drain line 4” and smaller size, and not
exceeding 100’ in drain lines larger than 4”. Underground cleanouts shall be
extended to an accessible location, to the surface of the floor above or to grade,
subject to approval of the Client. Panels and plates for access to cleanouts shall
be provided.
Each Fixture and piece of equipment, including floor drain, required connections
to the drainage system shall be equipped with a trap. Traps are to be supplied
with the fixtures as possible, and no fixture shall be double trapped. Except as
otherwise indicated, traps installed on bell and spigot pipe shall be of cast iron.
Traps installed on threaded pipe shall be recess drainage pattern.
Floor Traps with gratings shall be made of high grade, strong, tough and even
grained metals. Castings shall be free from blowholes, porosity, hard sports,
excessive shrinkage, cracks or other defects, shall be smooth and well cleaned
both inside and outside. Castings shall not be repaired, plugged, brazed or
burned. The wall thickness of iron casting shall be not less than ¼”.
Joints for Cast Iron soil, waste and vent pipes shall be made with lead, jute,
hemp or hempen spun yarn. The material shall be well packed into the annular
space so as to prevent the entrance of lead into the pipe. Run lead joints shall be
applied to perfectly dry pipes. Under wet condition lead fibre joints shall be made
both with quantities and depth of jointing materials and by method as per BS:CP-
301 (1950). The remainder of the space shall be filled with molten lead that is hot
enough to show a rapid change in colour when stirred. The lead shall be caulked
to form a tight joint without over straining the bell.
117
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Manholes shall be located at every change of grade and direction and at suitable
intervals and of sizes as shown on drawings. The top of manhole shall be about
3” above the surrounding ground and it shall be sloped all-round from C.I. frame
to avoid any obstacle to the pedestrians unless for a pavement the top is required
to be flush with the pavement level. Frame and cover shall be painted with
bitumastic paint. Brick masonry chamber shall be constructed around the Gully
Trap and shall have C.I. grating, frame and cover. The chamber shall be finished
smooth from inside and outside and the C.I. grating, frame & cover shall be
painted with bitumastic paint.
The disposal work shall comprise an out-fall to the public sewer. In the absence
of such an arrangement it shall be connected with a septic tank. The septic tank
shall be water tight structure of the capacity, shape and size as specified in the
BOQ or shown on drawings. Mica flap ventilation cowl and C.I. pipe shaft shall
be provided on the intercepting Manhole. The treated fluid from the septic tank
shall be led into a soakage pit. The soakage pit shall be a well sunk to a depth of
about 2’ to 3’ below the natural water table or as directed by the Client. The pit
shall be filled with stones or brick bats and suitably sealed on ground level with
RCC slab, as approved by the Client.
The pipes shall run exposed or embedded in walls and floors as specified or
shown on drawings. Where embedding walls or floor is required, the necessary
instructions and route of pipe work shall be approved by the Client. Pipes
running exposed on walls and ceiling shall be properly clamped with Hangers,
Supports & Clamps. For passage of pipes through masonry wall & RCC
structures, asbestos cement pipe sleeves shall be embedded, properly caulked and
water proofed. Pipes laid underground shall be provided with protective coat as
specified.
All screwed joints both internal and external shall be carefully examined. The
threads of the joints shall be perfect for the full depth of the joint. In case there is
any flaw in the threads, the thread shall be corrected using dies of proper size.
The screwed ends of pipes or specials to be joined shall be slightly tapered. The
jointing work shall be so arranged that the two ends of the pipes or specials
jointed shall be at equal distance from the middle of the socket and shall have a
space of not more than ¼” between them. Country cotton yarn smeared with
genuine white lead shall be wound in the grooves of the outside threads of the
pipes from end of the joint. The strand of cotton yarn shall project outside ends of
the joint or inside the pipe. White lead paste shall be thin & made up by boiling
genuine and moist white lead in linseed oil.
118
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Union couplings of approved quality and make shall be provided on the pipelines
in numbers desired by the Client, for easy maintenance of all parts of work.
Specials and fittings such as tees, bends, reduces, etc. shall conform to B.S.
specifications and shall be suitable for the class of pipe. All changes in directions
in the pipe line shall be effected by means of bends of large radii and the use of
elbows shall be restricted only where there is no room for bends, but square
elbows shall not be permissible for effecting changes of direction unless
otherwise approved by the Client.
The Contractor shall provide and install on the site of works Fire Fighting Mains
with Fire-hydrants according to Bs: CP-402-101 (1952) using specified materials,
and Dry-riser System within the building including dry-riser pipes, inlets, outlets
valves and hangers, anchors, concrete anchor blocks etc. as per samples
previously submitted and approved by the Client and in accordance with
requirements of BOQ, as shown on the drawings and conforming to best
engineering practices.
119
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The pipework shall conform to all relevant clauses of this section. The Contractor
shall provided and install pipe hangers, anchors, and supports required for proper
supports, shall be rigid enough to prevent undue strains on equipment served.
Hangers, except for the springs, shall be designed as to yield a Safety factor of
five based on the ultimate tensile strength of material.
They shall be located so as not to interfere with the free expansion and contraction
of piping between anchors or guides. The following table gives the maximum
spacing for Hangers and supports for various pipe diameters:
Anchors shall be welded steel plated type with wrought steel straps unless
otherwise approved by the Client. All anchors shall be designed for rigid
fastening to the structure either directly or through brackets. Anchors or guides
shall be capable of with-standing the forces imposed by expansion and
contraction and during operation. Pipe sleeves shall be furnished & set in position
at proper and permanent location for all piping passing through masonry walls,
floors, partitions etc. Sleeves in walls and partitions shall be furnished & set in
position at proper and permanent location for all ping passing through masonry
walls, floors, partitions etc. Sleeves in walls and partitions shall be flush with
finished surface. Sleeves in floors for exposed risers shall end 1.5” above
finished surface of floor and flush with ceiling below. Space between Sleeves and
Pipe shall be caulked with cement mortar and non-extruding bitumastic filler for
water tightness shall be connected to FIRE BRIGADE type inlets with drip cock
installed on the wall near entrance to lower most floors approximately 3’ above
floor level. It shall be housed in Cast Iron Box with locking arrangement and
with a wire glass front marked “fire dry riser inlet’. Outlets of specified size or
landing valves shall be provided approximately 3’ above floor level on each floor
at locations shown on the drawings. These shall be housed in cast iron boxes with
locking arrangement and with wired glass front marked “FIRE DRY RISER
OUTLET”. Inlets and outlets shall be on standard manufacture to be approved by
the Client & shall be suitable for fire mains installed on the works. The body of
inlets & outlets shall be of gun metal and the spindles and wheels shall be of
bronze. Each dry riser shall have air relief valve fitted at the top. Metal indicator
plates showing the position of indoor “Inlets” and “Outlets” of dry risers shall be
fixed outside the buildings and position of such indication plates shall be
approved by the Client. These plates shall comply with BS-750.
120
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
No work shall be covered over or surrounded with concrete until it has been tested
by the Contractor and inspected and approved by the Client.
a) Drainage Pipes:
The test shall be applied before the pipes are launched with concrete or
covered and repeated after back filling the trench. Water test shall be
carried out in drainage lines of RCC or cast iron. Pipe should be subject to
a test pressure of at least 5’ head of water at the highest point of the
section under test. The test should be carried out by suitably plugging the
lower end of the drain and the ends of connections, if any, and filling the
system with water. A knuckle bend should be temporarily jointed in at the
top end and a sufficient length of vertical pipe jointed to it so as to provide
the required test head which shall be maintained for 30 minutes without
showing a drop of more than 3 inches.
In RCC pipe lines water should be added until absorption by pipes and
joints has ceased. A slight amount of sweating which is uniform may be
overlooked but excessive sweating in a particular part of joint shall be
taken as a defect.
Any leakage visible shall indicate defective work which shall be cut out
and made good by replacement by the Contractor at his cost and retested
for acceptance.
121
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
b) Water Pipes:
After laying, jointing and anchoring, the main should be slowly and
carefully charged with water, so that all air is expelled, then allowed to
stand full for several days before testing under pressure is not exceeded.
Pressure gauges should preferably be recalibrated before the test.
The test may be the maximum working pressure at the point of reading
plus 50%. The test pressure should be maintained by the pump for about
one hour and if there is any leakage it should be measured by the quantity
of water pumped into the main in that time. A general leakage of one
gallon per inch of diameter per mile per 24 hours per 100 ft. head may be
considered reasonable, but any visible individual leak should be repaired.
Any defective pipe-length, joints fittings, and valves and any defective
material shall be replaced or defective work rectified by the Contractor
and retested for acceptance, all at Contractor’s cost.
PVC Pipes:
PVC pipes shall be best quality manufactured by Pakistan PVC Ltd or approved
equivalent conforming to BSS-3506-1969. The fittings such as flanges, sockets,
tees and bends shall conform to BS-4346-1969. The pipes and fittings shall be
capable of withstanding a pressure of 400’ head of water. The joining shall be
done by PVC solvent cement 70.
PVC Valves:
Sluice valves for PVC pipes shall conform to relevant British Specifications and
the jointing will be done as for PVC pipes.
Copper Pipes:
Copper pipes and fittings shall conform to BS-2871 Part-I (1971). They shall be
suitable to be jointed from outside with couplings manufactured to the same
specifications as those for pipes. The pipes and fittings shall be capable of
withstanding a pressure of 400’ head of water. The jointing will be done
manipulative, i.e. the pipe ends have to be opened out with special tools, the pipe
ends shall be cupped by means of a drift; the fittings comprising a brass nipple
122
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
with shaped ends and a central spanner grip. The cupped ends of tubes shall be
fitted to the shaped ends of the nipple and recessed fly nuts are tightened thereby
making a water tight metal or metal joint.
Stainless Steel and Cast Steel Pipes: Stainless steel and cast steel pipes and
fittings shall be of best quality and conform to relevant British Specifications.
The pipes and fittings shall be capable of withstanding pressure 400’ head of
water. The jointing shall be done by sleeve welded joints.
W2.11 MEASUREMENT:
Pipes shall be measured in running feet or meters (as given in BOQ) of the
finished length without adding lengths consumed in joints and without deducting
lengths of specials, fittings, valves and the like installed in the line.
Specials/fittings used in G.I., PVC, Copper, and lead pipe lines shall not be
measured for separate payment.
Floor traps, valves, chambers, manholes, fixtures and similar items shall be
measured by number.
W2.12 RATES:
Rates shall be full compensation for everything required to be furnished and done
to complete the work (pay) items as per specifications in all respects.
Inter-alia as specified and required, the rates shall cover all costs for :-
Fixing arrangements such as hanging systems, clamps, holder bats, nuts, bolts,
screws, sleeves etc. and all jointing materials. Concrete bedding and backing
blocks shall be paid under section “Concreting”. Rates for other bedding
123
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
materials like sand, stone or brick ballast shall also cover shaping them for pipe
circumference and compacting etc.
The contractor shall provide and fix the equipment/ materials of superior quality
as indicated below or approved equivalent as per approval of the Engineer.
124
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
SECTION – E-1
ELECTRICAL SPECIFICATION
(INTERNAL & EXTERNAL)
1. GENERAL INSTRUCTIONS:
c) All material shall be as specified, genuine make, new and unused to fully
meet with the requirements and details furnished in the Exhibited
Drawings. If the make of material is not specified or detail of some
component of a job is not given, the Contractor shall at his own
responsibility and expense, obtain all information which may be necessary
for completion of the work and get approval from the Client. The
Contractor shall, in general, use materials of highest grade and quality
conforming British Standards or equivalent Specifications.
d) The Contractor shall set out the work himself and if any discrepancy is
found is drawings or B.O.Q., shall report the matter to the Client and shall
act as directed by them in writing. If any defective or modified setting out
is carried out by the Contractor on his own will, he shall rectify or make
good the same at his own cost.
125
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
g) The work will not be extended now and the Contractor is supposed to
submit such rates which will be considered applicable for the
extensions/new buildings in the project within reasonable time.
h) The Contractor is supposed to perform his own survey of the works and
base his rates upon the same. Incase he finds that the routes/works
proposed in the tender drawings are at some/all places not workable as
such due to some unforeseen circumstances or differ much in assumed
volume of work, he is supposed to submit his own working drawings, at
his own cost, for approval to the Client to proceed as reinstructed.
THE TENDER:
The tenderer shall submit with his tender a full and clear description of the
fittings/equipment he proposes to supply together with such drawings,
illustrations and technical data as may be necessary. Six copies of all description
drawings and illustrations etc. are to be submitted. The tenderer shall carefully
examine the specifications, the schedule of quantities and prices, the drawings and
other information supplied herewith, and shall on his responsibility and at his own
expense obtain all the information which may be necessary for preparation of the
tender.
The schedule of quantities and rates must be fully priced, monied out and totaled
in ink and signed by the tenderer, and shall truly set forth the actual prices and
money calculations used by the tenderer in arriving at the amount stated in the
tender.
The rate and the total amount in local currency for supply, installation and
testing of all materials included in the schedule of quantities.
126
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
3. SCOPE OF WORK:
The works to be carried out under these Specifications include supply and
installation, compete in all respects of electrical and other relevant materials
incidental to proper completion of the installation. The Specifications are
intended to provide a broad outline of the required equipment and installations
and are not intended to include details of design and constructions:
ii. Complete wiring of lights, fans and switch sockets and other outlets as
indicated on the drawings or necessary for satisfactory completion of the
works including lamps holders, ceiling roses and other accessories as
required.
iii. All material shall be suitable for system voltage 415/240 volts A.C. at 50
Hertz except as otherwise required. They will be of genuine make without
fail and brand new completely unused.
iv. Providing, fixing and connecting other such items that may have left out
above and are found necessary for completion of the Project.
All components of work usually carried out such as finishing, painting, testing,
cleaning etc. of complete installation are included in the given rates by the
Contractor.
127
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
4. LIGHTING FIXTURES:
The fittings shall be as specified in the Bill of Quantities. The lighting fixtures
shall be provided with all necessary supports, suspension arrangements, lamps,
lamp holders, chokes, hooks, hardware, starters, etc. as required for installation.
The light fittings shall have all required accessories of first class quality and shall
be tested and commissioned.
The chokes should be Polyester filled having high efficiency. The starters as well
as the chokes should be made of M/s. PHILIPS or equivalent. The fittings shall
have spring loaded roller type lamp holders. The items shall be of top quality and
approved by the Client in writing.
Each of the fluorescent tubes and high pressure mercury lamp fittings must be
power factor corrected by a capacitor.
All fittings shall be supplied complete with lamps and other accessories.
In case a specified luminaires is not available at any cost or has become obsolete,
the Contractor shall request for an alternative specification and shall not proceed
without approval from the Client.
Moreover:
iv. The switches must be rated minimum 40% greater than total current drawn
in a multi-point circuit whether it be 5, 15 or more Amperes.
128
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
5. SWITCHES:
The switches shall be rated as called for in BOQ but as warranted by the total
current drawn by a point. The minimum rating should be 5 Amp. They will be
miniature royal type, one way or twoway as required. Bakelite made and fitted on
a recessed type switch-board.
A gang of switches may be formed by more than one switch on one common
board. The switches should be of approved manufacturers single or twoway as
called for in the Schedule of Quantities.
The switch board shall be fabricated on a C.I. box of the requisite size or made
out of 2 mm thick sheet steel protected by an external coat of bitumen.
They should be recessed mounted in wall 4.5 feet above finished floor level.
The selected colours and make must be consistent throughout the installation in
the building.
6. FANS
All fans shall be A.C. capacitor type fans of sizes as called for in schedule of
quantities. They should be complete with accessories e.g. fan box with 5/8”
suspension hook, necessary length down-rod, canopy, ceiling rose, flexible cord
24/.20” size (23/.0076”) oversheathed, brass hardware, etc.
All fans must be accompanied by multi-step fan regulators suitable for recessed
mounting. The regulator may well be multistep choke type or may consist of a
dimmer switch.
Dimmer switch if used must be rated at least 200 W and should have an internal
circuit for freedom from radio interference.
Exhaust fans should be complete with capacitor, metallic stove enameled frame,
air-pressure operated and gravity controlled louvers.
129
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
All the fans, whether ceiling or exhaust, should be of M/s. Parwaz/Millat make
unless otherwise called for in schedule of quantities.
In case of fan of the specified sweep is not made by the specified companies, it
will be procured on special order for the same companies. Anyhow, if the fans of
such specified sweep and variety are regularly made by any other company, it
may be used provided it is one of the following makes:
G.F.C.
PAK FAN
ROYAL FAN
Provision and installation of a Fan-box, metallic body, top quality with 5/8” dia.
suspension hook and holdfast is integral part of every ceiling fan.
7. SWITCH-SOCKET OUTLETS:
They will in general be mounted 12” above finished floor level or as per site
requirement on a C.I. or 2 mm thick sheet steel box recessed in wall. They should
be mounted above counters in kitchens or other such places if required.
The box shall be bitumen coated on the outer surface in touch with the wall when
recessed mounted.
a) GENERAL:
The Contractor shall furnish all materials and labour to install wires and
cables as indicated on drawings and listed in the schedule of quantities.
The Contractor shall provide, without any extra cost, materials for
terminations etc. such as lugs, solder, clamps, supports, bushes, fixing pins
etc. necessary for a complete wiring installation. Other miscellaneous
items such as filling compound, identification tags/boards, earthing clips
and straps shall also be furnished for a complete wiring installation in
accordance with the best modern practices.
130
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Nominal
Conductor Size & Gauge of Conduit in mm
size
sq.mm. 20 25 32 38 50
Max. Number of Cables
1.5 8 16 21 35 -
2.5 6 13 20 28 -
6.0 4 7 12 16 21
10.0 2 4 7 10 14
16.0 - 3 5 8 11
25.0 - 3 5 7 9
35.0 - - 2 3 4
50.0 - - 2 3 4
The Contractor shall provide and install all cables and wires of the sizes
called for in drawings and in the schedule of quantities or found otherwise
necessary for a complete wiring e.g. for wiring measuring instruments
within a Distribution Board or Panel etc.
The cables for pointing wiring only may be one of the following makes in
the order of preference:
131
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
After finishing the pouring, the concealed conduit shall have a covering of
35 to 50 mm of concrete around it including the thickness of the finishing
plaster.
For passing through the walls, the conduit should be recessed 1” in the
wall while the wire run be vertical i.e. from floor towards the ceiling or
vice versa. The conduit may be flush with the wall (excluding plaster) if
the wiring is horizontal.
The installation of wires and cables in PVC or steel conduit pipes shall be
done with care to prevent damage to the cables.
132
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
iii. Runs with two 90 degree bends – not more than 25 ft.
The minimum length of all inspection boxes shall not be less than four
times the cable manufacturer’s recommended bending radius of the cable.
Where ever the conduit may have to run directly underground, it will be
laid at a depth of 0.8 m below finished ground level.
Rates quoted for such run will mean to include all these and other
incidental materials to complete the job in every respect.
All conditions except for those specific for the concealed wiring as laid down
above in item 8, shall apply to the wiring in conduit on surface whether it be steel
or PVC.
The conduit on surface of the wall will be installed at a height determined by the
Client but normally it will be 1’-6” below the ceiling.
The saddles and clamps used for the PVC conduit shall be made of PVC and
those for the steel conduit shall be made of cast iron.
The maximum distance between any two neighbouring saddles and clamps shall
be 2’ Additional saddles and clamps shall be provided close to the bends and
other such points of stress and no weak and loose point shall be in the installation
for any cause.
The steel conduit should be de-rusted, and cleaned from inside as well as outside
and given one coat of red Lead Oxide as a primer over which should be given two
coats of black enamel. The enamel should be fine and of such high quality that it
should not crust off by the minor bending or jerking etc.
133
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
a) PVC CONDUIT:
The jointing shall be done by PVC solvent cement-70. The solvent shall
be applied so as to yield a water tight joint.
The minimum size of the conduit used shall be dia 20mm unless otherwise
specified.
The conduit should have specific volume resistivity of 3-5 x 1015 ohms and
a dielectric strength of 23-28 kV/mm.
The Contractor will supply and install all accessories in the quoted price
for the supply and installation of PVC Conduit.
Soft metal bushes should be used at terminal ends in order to protect wire
insulation from damage during and after pulling operations.
134
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
All conduit shall be heavy gauge 16 SWG steel min. and threaded type in
standard manufactured length complete with all accessories and protected by a
black enamel coating.
The black enamel coating shall be of such good quality that it should not flake or
crack during bending or rough usage. An additional coating should be given after
installation in position.
The minimum size of the conduit used shall be dia. 20 mm unless otherwise
called for in BOQ or drawings. The total cross sectional area of the cable drawn
in the conduit should not be more than 40% of the cross sectional area of the
conduit itself.
If installed concealed in the slab/walls, only one coat of hot bitumen all around is
required.
The horizontal runs of conduit on surface shall not be more than 450 to 600 mm
below the ceiling level (unless otherwise called for in BOQ or drawings) and
where hindrance is met on the route, the conduit shall be taken around the
hindrance above or below neatly and then run at the same level.
12. CLEANING:
The cleaning of the entire conduit system shall be essentially completed before
wiring is installed. Conduits shall be tested for continuity and obstructions. Any
obstructions found shall be cleared by use of a cutting mandrel or other approved
device and the conduit be cleaned out before the installation of cable.
The cables shall be armoured, PVC/PVC or XLPE insulated and of sizes as called
for in schedule of quantities and drawings.
135
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
They will be laid in conduit, ducts, RCC pipe, directly underground etc. as
required.
All passages of common traffic, whether they be roads, streets or verandas etc.
shall in any case be crossed through large size high quality and pressure bearing
RCC pipes. Minimum diameter of the pipes shall be 100 mm.
The cables or conduit shall be laid 0.8 m below finished ground level surrounded
by a layer of at least 150 mm insulation grade sand unless otherwise required.
Pass of BS size sieve No. 14 and retain of No. 18 size clean and dry river sand
may be used if ready prepared insulation grade sand is not available.
Burnt bricks should be laid over the sand and then the trench should be back-filled
and compacted to 95% of maximum dry density of the back-fill material.
Route Indicators, which in any case are integral part of the installation, should be
metallic comprising dia. 75 to 100 mm sign board welded to dia. 12 mm G.I. pipe
750 mm long overall unless otherwise detailed in the drawing.
Distribution boards/Pillar Boxes shall be fabricated out of sheet steel at least 1.5
mm thick, stove enameled and shall be having hinged door, handle, lock and key
arrangement.
They shall comprise of fuses, switch-fuses or MCB’s having the rating as called
for in BOQ.
The fuses shall invariably be high rupturing capacity type made by Power
Electronics, SA Electric Co., Electrech or approved equivalent. The approval
must be achieved in writing.
All boards should be provided with identification tags/stickers, bus bars, phase
indication miniature lamps etc. They shall be recessed mounted on wall, fixed on
136
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
surface, stand free on floor or may be masonry pad mounted in open as called for
in schedule of quantities or drawings.
In general, the distribution boards shall be recessed type, the pillar boxes masonry
pad mounted and the main panels in power stations free standing.
The distribution boards shall in general be provided with cable end boxes or
sealing glands so that no leakage of current may be possible.
Soft metal bushes must be provided for smaller sizes (below and including
16 mm.sq.) cables outgoing or incoming to the distribution boards.
The masonry pad for mounting the Pillar Boxes shall be as detailed in the
drawings. The pad shall be plastered ½” thick all around. The Pillar Boxes shall
be weather proof and shall be fixed mounted on the masonry pad.
The circuit breakers used in the distribution boards mentioned above or otherwise
(e.g. for plug-in-box etc. if required) shall be any of the makes given below and
shall have the specified number of poles, interrupting current capacity of
sensitivity. In case a circuit breaker of the given make is not available, an
alternative can be used only with the written approval of the Client.
The MCB’s, single pole or double pole, shall be of one of the following
genuine make only:
1. LEGRAND 2. SIEMENS
3. TERRASAKI 4. FUJI
The three phase MCB’s should be three pole with neutral link having a
minimum interrupt capacity of 7500 Amperes at 415 volts unless
otherwise called for in BOQ.
137
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The Three phase MCB’s shall be one of the following makes only:
LEGRAND
FUJI
TERRASAKI
SIEMENS
All the MCB’s, whether single or multi-pole one, must be fitted both with
the magnetic as well thermal tripping devices.
1. LEGRAND 2. FUJI
3. TERRASAKI 4. SIEMENS
5. HITACHI
The Contractor shall propose the selected make to the Client and shall
proceed after approval. One and the same make, shall be consistently used
throughout the installation as far as feasible.
All the MCB’s should be adjustable type having the ratings as given in the
BOQ and capacities as given against each below unless otherwise called
for in the Schedule of Quantities:
15 to 80 7.5
100 to 150 10.0
200 to 300 15.0
400 to 600 20.0
700 to 800 40.0
1000 to 1200 60.0
As a general rule the breaking capacity of the breakers towards the starting
end of the supply shall be greater than that of the distribution side.
138
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
All the E.L.C.B.’s should be of the rating as called for in the Schedule of
Quantities and having the interrupting capacity or sensitivity as given
below unless otherwise called for:
Only those Earth Leakage Breakers are permitted which are fitted with
built-in over-load and short circuit release. Any breakers installed
otherwise will have to be removed and replaced by the required ones at the
cost of the Contractor.
139
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The switch-fuses where ever indicated shall be rotary cam type with H.R.C. fuses.
In case the switch-fuse of the specified rating or a rating close to (but larger than)
the same is not available, a Fuse-Switch or a Load Break Switch with Separate
H.R.C. fuses and bases may be used.
17. EARTHING:
The earthing arrangement shall conform drawings and latest I.E.E. regulations.
All metallic parts in the installation are in general to be earthed.
Minimum size of the earthing conductor shall be dia. 2 mm and that of Earth Lead
dia. 4 mm but the size otherwise given in the drawings or BOQ must be followed.
The earth Lead shall be drawn in G.I. pipe from the Earth Set to the requisite
Earth Point, Distribution Board or Machine etc. unless otherwise called for in
BOQ.
140
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The Contractor shall prepare and submit for approval, the drawings, literature of
the fittings/equipment, appliance and fixtures which shall in any case be installed
only after written approval by the Client as required subject to a maximum of six
no. drawings.
The Contractor is supposed to submit the shop drawings of all the Distribution
Boards and the Panels for approval before installation and purchase of the items.
The drawings should give full details of all materials, finishes and set up. The
Contractor should submit three sets of the drawings for the purpose and proceed
only as per the approved drawings.
The Contractor should also submit working drawings for all other installation
work (e.g., luminaires, switch-sockets, switch-boards etc.) proposing the process
of installation he is going to adapt in the actual work.
The Contractor is responsible for submitting in triplicate the “As Built Drawings”
of the electrical works if there be some variation of any nature and any magnitude
in execution to the original tendered drawings on any account.
Failure to submit the above drawings and get them approved by the Client may
result in withholding of his final bill/security money.
Steel poles shall be either seam welded or seamless extruded. The finished
product shall represent the best quality by modern manufacturing standards.
The steel used to manufacture the poles shall have specifications not less than the
following:
The diameters and sections of the poles shall be as shown on the drawing.
141
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Wall thickness of any pole at any place shall be standard as per thickest size
manufactured and easily available in the market at the time of installation. It
shall, however, not be less than 5 mm at any place for any section.
The poles shall be relieved of all welding and drawing stresses and thoroughly
cleaned of all oxidation, scale, oils and contaminants before finishing.
The poles should be given a Lead-oxide prime coating from ground line to top
and a bituminous solution coating from bottom to ground. A silver white
coloured, fine quality, two coat enamel should be applied over the primer unless
otherwise directed.
20. TESTING:
Upon completion of the installations the Contractor shall perform field tests on all
equipments, materials, system. All tests shall be conducted in presence of the
Client or their appointed representative.
In general all test made by the Contractor shall be of the nature to assure that the
entire installation is sound and that all circuits lighting, power and equipment etc.
will function properly and as intended.
The Contractor shall furnish and install all tools, instruments, test equipment,
materials etc. and furnish all personnel required for carrying out complete testing.
The Contractor shall record all test results and submit the same to the Client duly
initialed by his testing engineer.
142
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The insulation resistance test shall be performed on all electrical equipment and
wiring. Using Megger tester or any self contained instrument such as direct
indicating Ohmmeter of the generator type.
Only D.C. potentials shall be used for such testing and those shall be as follows:
Circuits under 230 V = 500 V test voltage
Circuits 230-400 V = 1000 V test voltage
The insulation test between each cable of a circuit as well as between earth and
individual cable shall be made. All equipment shall be tested to earth.
If the insulation resistance of the circuit under test is found less than that specified
above, the cause of low reading shall be removed.
The corrective measures shall include dry out procedure by means of heaters if
equipment is found to contain moisture but if circuits are found defective, these
shall be removed and replaced and then tested again.
The tests shall be carried out at least three times and the readings shall not vary
from each other more than 7.0% of average value.
Each resistance tests shall be made by the Contractor on the earthing system,
separating and reconnecting each earth connection as may be required.
The electrical resistance of the ECC together with the resistance of the earthing
lead measured from the connection with earth electrode to any other position in
the completed installation shall not exceed one Ohm.
Approval for the soundness of all the electrical installation from the relevant
department is the liability of the Contractor. The final payment of the Contractor
may be withheld until the approval is achieved.
143
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
Pumps shall be made by K.S.B. Grundfos or equal approved and will be complete
with impellers, coupling flanges, reducers, enlargers, etc. to connect them with the
incoming and outgoing lines and to commission them satisfactorily.
The concrete foundation and another bolts shall be considered integral part of the
motor pump.
Timer, instruments, float-less control replay, probe rods, probe rod holder, control
resistances etc. will be provided within the quoted price for all automatic electric
motor pumps. The timer will be adjusted to the requirements as indicated by
Client incharge at Site. The timer and other instruments will be of the best quality
available in the market.
The work will be considered incomplete unless the installation is tested and
commissioned to the entire satisfaction of the Client. The work must conform
drawings and BOQ.
The rosette and jack must be made out of Chromium plated Brass of high
conductivity.
The joint of telephone cable with the rosette or jack may be soldered.
144
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
The Junction Boxes should be of a size not only sufficient for the number
of pairs for which hit is designed/called for in the BOQ but must have
space enough for 100% increase.
The Junction Boxes may be mounted 4’ (1200 mm) above relevant floor
level. They are required to be recessed in walls.
Rechargeable lead acid battery bank should be provided along with the
battery charger of rating suitable for the trouble free function of the
exchange.
145
CLIENT: CONSULTANT: PROJECT:
CONSTRUCTION OF CB MEDICAL
COLLEGE NEAR OLD CGH AT
Lahore Cantonment G3 Engineering Consultants
SARFARAZ RAFIQUI ROAD LAHORE
Board (Pvt.) Ltd. CANTT
January, 2019 BIDDING DOCUMENTS
VOLUME II: SPECIFICATIONS
installed. They should be provided along with the lead of suitable length
up to the relevant telephone outlet.
Any approval required from PTC department for installation of the sets
will be liability of the Contractor.
It may be assumed that the air is not normally heavily polluted by dust, smoke,
corrosive gases or vapour. However, at certain times of the year severe dust
storms may be experienced.
The reference ambient temperature assured for the purpose of these standards are:
Maximum 45 º C
Max. over any 24 hrs. 40º C
Mean in the year 25º C
Minimum -5º C
The maximum value of ambient temperature and humidity, however, does not
occur simultaneously. During the monsoon season high humidity may persist for
several days at a time.
The altitude for installation shall not exceed 1500 meters above mean sea level.
146