CONSTRUCTION WORK OF 52" ONSHORE

UNLOADING LINE AND 6.625”ONSHORE EFFLUENT LINE

Morning : Sunny Night shift:N/A Yesterday PM TO N/A AM Cut off Date: Friday, 23 April 2021

Afternoon : Sunny Day Shift: 07.00 AM TO 3:30 PM Site Good

Daily Report

Contents

1 Manpower

2 Equipment

3 Material

4 Construction Work

5 Photo

6 Plan of next day and AOB

Prepared by: Aryani Yasrida Certified by: Aspar Abdul Latif Review by: Yudha Maulana

Signature: Signature: Signature:


CONSTRUCTION WORK OF 52" ONSHORE
UNLOADING LINE AND 6.625”ONSHORE EFFLUENT LINE

MANPOWER

Department Position Working Jakarta (Other Remark


on- Site Location)
Project Manager 1
Project Deputy Manager 1
Construction Manager 1
Project Control Manager 1
Management
HSE Manager 1
Engineering Manager 1
QC Manager 1
sub-total 2 5 0
Superintendent 1 had ID Badge
Project Control 1
Project Control Staff 2
Finance Control 1
Project Engineer 2 had ID Badge
Drafter 1
HSE Officer 1
Indirect Manpower
QA/QC Site Manager 1
QA/QC Field 1
HRD & Public Relation 2
Procurement 1
Paramedic 1
Authorized Gas Tester (AGT) 1
sub-total 15 1 0
Foreman 4
Safetyman 1 had ID Badge
Surveyor 1 had ID Badge
Heavy Equipment Operator 7 2 prsn had ID Badge
Rigger 1 had ID Badge
Driver 3 one prsn had ID Badge
Direct Manpower Mechanic / Electrical 1
Helper 9 2 4 prsn had ID Badge
HD Driver 1
Assistant Surveyor 1 had ID Badge
Campboss 1
Night Watch 6 1
sub-total 35 0 4
Total 52 6 4
CONSTRUCTION WORK OF 52" ONSHORE
UNLOADING LINE AND 6.625”ONSHORE EFFLUENT LINE

EQUIPMENT
Department Description Specification Qty Status Work Task Using Period Remark

Management

Vehicles - 5 Good Personnel 2 unit inspected


transportation
Computer - 9 Good
Printer Scan and Printer 3 Good
Management Scaner Scan and Printer 3 Good
Warehouse and
Container 20 feet 2 Good Material Storage
Camp House 4 Good Accomodation a year
Yard 12.815m2 1 Good Workshop a year
Office 1 Good Site Office a year
Equipment

Excavator PC200 CAT 320 3 Good Excavation 2 unit had safety sticker, 1
unit close finding

Lifting Pipe and Lifting 3 unit Inspected, close


Sideboom D8 CAT 583H 7 Good Material finding on process

LD 1000 MITSUBISHI LD 1000 2 Good Carry Material Inspected, close finding on


process

Twin Arch CATERPILLAR D-6D 1 Good Carry Material Inspected, close finding on
process
Inspected, close finding on
Dolly - 1 Good Carry Material process
Trailer VOLVO 1 Good Carry Material not inspected yet
Instrument
Construction
GPR Trolley 1c - 110 cm x 47 cm x 80 cm 1 Good Survey had safety sticker

Tripod 2c - 115cm x 20cm x 20cm 1 Good Survey had safety sticker

LEICA GS14
RTK LEICA CS07 2 Good Survey had safety sticker

Prisma 1c - 45cm x 40cm x 35cm 2 Good Survey had safety sticker

GPS Garmin Garmin; 1c - 45cm x 40cm x 1 Good Survey had safety sticker
35cm

Leica 06 plus Total


LEICA 06 2 Good Survey had safety sticker
Station

(2) Topcon S/N WP05319 &


Auto Level WP058349 2 Good Survey had safety sticker

Holiday Detector 1 Good Holiday Test had safety sticker


Total
CONSTRUCTION WORK OF 52" ONSHORE
UNLOADING LINE AND 6.625”ONSHORE EFFLUENT LINE

Material Delivered to Site


Specification/
NO. Description Unit Status on-site time Remark
Qty
1 Lowering Tools lot 1 Good 31/Mar/21
2 Steel Mat Unit 6 Good 31/Mar/21
3
4
5
6
7
8
9
10
11
C
i
CONSTRUCTION WORK v
si
al
Pre-Commissioning etc. n
Construction d
w
KP content Construction Clearing & Welding Welding Reinstate Cleaning & Hydrotest Hydrotest o
Stringing FJC Trenching Lowering Backfilling
Survey Grading 52" 6.625" ment Gauging 52" 6.625" fr
ik
m
l
Unit M M M Joint Joint Joint M M M M M M M
3
l
Quantity 220 220 - - - - - - - - - - - -
Prev.
KP 20+220 Current period - - - - - - - - - - - -
- Accumulation - - - - - - - - - - - -
KP 20+000 Completion% - - - - - - - - - - - -
Quantity 410 410 - - - - - - - - - - - -
Prev.

KP 20+000 Current period - - - - - - - - - - - -

- Accumulation - - - - - - - - - - - -
KP 19+590 Completion% - - - - - - - - - - - - ###
Quantity 546 546 - - - - - - - - - - - -
Prev.

KP 19+590 Current period - - - - - - - - - - - -

- Accumulation - - - - - - - - - - - -
KP 19+044 Completion% - - - - - - - - - - - - ###
Quantity 499 499 - - - - - - - - - - - -
Prev. 473 455

KP 19+044 Current period - - - - - - - - - - - -

- Accumulation 473 455 - - - - - - - - - - - -


KP 18+545 Completion% 94.79% 91.18% - - - - - - - - - - - - ###
Quantity 1239 1239 - - - - - - - - - - - -
Prev. 1239 1239

KP 18+545 Current period - - - - - - - - - - - -

- Accumulation 1239 1239 - - - - - - - - - - - -


C
i
CONSTRUCTION WORK v
si
al
Pre-Commissioning etc. n
Construction d
w
KP content Construction Clearing & Welding Welding Reinstate Cleaning & Hydrotest Hydrotest o
Stringing FJC Trenching Lowering Backfilling
Survey Grading 52" 6.625" ment Gauging 52" 6.625" fr
ik
m
l
Unit M M M Joint Joint Joint M M M M M M M
3
l
KP 17+306 Completion% 100.00% 100.00% - - - - - - - - - - - - ###
C
i
CONSTRUCTION WORK v
si
al
Pre-Commissioning etc. n
Construction d
w
KP content Construction Clearing & Welding Welding Reinstate Cleaning & Hydrotest Hydrotest o
Survey Grading Stringing 52" 6.625" FJC Trenching Lowering Backfilling ment Gauging 52" 6.625" fr
ik
m
l
Unit M M M Joint Joint Joint M M M M M M M
3
l
Quantity 47 47 - - - - - - - - - - - -
Prev. 47 47

KP 17+306 Current period - - - - - - - - - - - -

- Accumulation 47 47 - - - - - - - - - - - -
KP 17+259 Completion% 100.00% 100.00% - - - - - - - - - - - - ###
Quantity 1884 1884 - - - - - - - - - - - -
Prev. 1884 1884

KP 17+259 Current period - - - - - - - - - - - -

- Accumulation 1884 1884 - - - - - - - - - - - -


KP 15+375 Completion% 100.00% 100.00% - - - - - - - - - - - - ###
Quantity 1500 1500 - - - - - - - - - - - -
Prev. 1500 1075

KP 15+375 Current period 350 - - - - - - - - - - - -

- Accumulation 1500 1425 - - - - - - - - - - - -


KP 13+875 Completion% 100% 95.00% - - - - - - - - - - - - ###
TOTAL Quantity 6345 6345

Prev. Prog. Cumulative 5143 4700

Current Prog. Cumulative 0 350

TOTAL Prog. Cumulative 5143 5050

Prog. TOTAL Cumulative 81.1% 79.6%


prefabrication date: #REF!

Plan Actual
Plan Original Actual Quan Current Accum
ID Activity_Name complete complete Unit
start time Duration start time tity period ulation
time time
TK101
1 Tank wall plate cutting
2 The roof plate cutting
Tank bottom plate cutting(workshop
3 cutting 10 piece,another cutting in the
site)
4 Tank wall plate rolling
5 Roof group for welding
6 Grit blasting
7 Primer coat
8 Prefabricated wind girder
TK102 ### ### ### 12/30/1899 0 0 0 0
1 Tank wall plate cutting
2 The roof plate cutting
Tank bottom plate cutting(workshop
3 cutting 6 piece,another cutting in the
site)
4 Tank wall plate rolling
5 Roof group for welding
6 Grit blasting
7 Primer coat
8 Prefabricated wind girder
TK103 ### ### ### 12/30/1899 0 0 0 0
1 Tank wall plate cutting
2 The roof plate cutting
Tank bottom plate cutting(workshop
3 cutting 6 piece,another cutting in the
site)
4 Tank wall plate rolling
5 Roof group for welding
6 Grit blasting
7 Primer coat
8 Prefabricated wind girder
TK104 ### ### ### 12/30/1899 0 0 0 0
1 Tank wall plate cutting
2 The roof plate cutting
Tank bottom plate cutting(workshop
3 cutting 3 piece,another cutting in the
site)
4 Tank wall plate rolling
5 Roof group for welding
6 Grit blasting
7 Primer coat
8 Prefabricated wind girder
TK201 ### ### ### 12/30/1899 0 0 0 0
1 Tank wall plate cutting
2 The roof plate cutting
Tank bottom plate cutting(workshop
3 cutting 4 piece,another cutting in the
site)
4 Tank wall plate rolling
5 Roof group for welding
6 Grit blasting
7 Primer coat
8 Prefabricated wind girder
TK202 ### ### ### 12/30/1899 0 0 0 0
1 Tank wall plate cutting
2 The roof plate cutting
Tank bottom plate cutting(workshop
3 cutting 4 piece,another cutting in the
site)
4 Tank wall plate rolling
5 Roof group for welding
6 Grit blasting
7 Primer coat
8 Prefabricated wind girder
TK301 ### ### ### 12/30/1899 0 0 0 0
1 Tank wall plate cutting
2 The roof plate cutting
Tank bottom plate cutting(workshop
3 cutting 4 piece,another cutting in the
site)
4 Tank wall plate rolling
5 Roof group for welding
6 Grit blasting
7 Primer coat
8 Prefabricated wind girder
TK302 ### ### ### 12/30/1899 0 0 0 0
1 Tank wall plate cutting
2 The roof plate cutting
Tank bottom plate cutting(workshop
3 cutting 10 piece,another cutting in the
site)
4 Tank wall plate rolling
5 Roof group for welding
6 Grit blasting
7 Primer coat
8 Prefabricated wind girder
TK303 ### ### ### 12/30/1899 0 0 0 0
1 Tank wall plate cutting
2 The roof plate cutting
Tank bottom plate cutting(workshop
3 cutting 10 piece,another cutting in the
site)
4 Tank wall plate rolling
5 Roof group for welding
6 Grit blasting
7 Primer coat
8 Prefabricated wind girder
TK304 ### ### ### 12/30/1899 0 0 0 0
1 Tank wall plate cutting
2 The roof plate cutting
Tank bottom plate cutting(workshop
3 cutting 4 piece,another cutting in the
site)
4 Tank wall plate rolling
5 Roof group for welding
6 Grit blasting
7 Primer coat
TK401 ### ### ### 12/30/1899 0 0 0 0
1 Tank wall plate cutting
2 The roof plate cutting
Tank bottom plate cutting(workshop
3 cutting 4 piece,another cutting in the
site)
4 Tank wall plate rolling
5 Roof group for welding
6 Grit blasting
7 Primer coat
TK402 ### ### ### 12/30/1899 0 0 0 0
1 Tank wall plate cutting
2 The roof plate cutting
Tank bottom plate cutting(workshop
3 cutting 4 piece,another cutting in the
site)
4 Tank wall plate rolling
5 Roof group for welding
6 Grit blasting
7 Primer coat
#REF!

Comple
tion%
GENERAL INFORMATION
No. Description
1 Conduct Tool Box Meeting before work at KP 14+000
2 As built land contour from KP 14+400 to KP 14+100
3 Land clearing and grading from KP 14+300 to KP 13+950
4 Preparation and make temporary stockpile at KP19
5 Install temporary bridge at KP 18+525
6 Fabrication gauging plate 52" at Workshop Penajam
7 Installed wire sling on pipelayer
8
9

CONSTRUCTION PHOTO

Conduct Tool Box Meeting before work at KP 14+000 Land clearing and grading from KP 14+300 to KP 13+950

As built land contour from KP 14+400 to KP 14+100 Preparation and make temporary stockpile at KP19

Install temporary bridge at KP 18+525 Fabrication gauging plate 52" at Workshop Penajam
CONSTRUCTION WORK OF 52" ONSHORE
UNLOADING LINE AND 6.625”ONSHORE EFFLUENT LINE

PLAN FOR NEXT DAY

NO Construction Contents Person in Charge Remarks


1 Conduct Tool box meeting before work start Construction
2 Continue clearing and grading Construction
3 Continue survey and marking existing pipe / cable along ROW Surveyor
4 Continue survey as built contour Surveyor
5 Continue Install stake KP Surveyor
6
7
8
9
10

AOB

N/A