RATE ANALYSIS FOR BRICKWORK

Downloaded from TheConstructor.Org

Wall Dimensions Length Width Height Area m2 Vol. m3


Half Brick Wall 40.0 m 0.1 m 0.5 m 20.3 2.337

Full Brick Wall 0.0 m 0.0 m 0.0 m 0.0 0.000

C/S Mortar Ratio 1 :5

Dry Mortar Qty 0.91

MATERIAL Qty. Rs. /Unit

Bricks 494 4
Cement Bags 7.00 250
Sand m 3
1.22 900

LABOUR With Hand Mixing of Mortar Days

MASON 0.94 300


LABOUR 1.37 250
BAHISHTI (Water Carrier) 0.20 200

Prime Cost 5485.04

Scafolding
@2% of prime cost

Sundries
@3% of prime cost

CONTRACTOR PROFIT
Contractor Profit 15

TOTAL COST (Rs.) 6,


SUBTOT
AMT (Rs.)
AL (Rs.)
1976.00
1750.92
1093.62
4820.54

282
343
40

664.50

Amount
109.70
109.70

Amount
164.55
164.55

% 863.89

6,623.18