Emily-1 Project Fuel Terminal and Jetty Roofing and Siding Inspection Report
Emily-1 Project Fuel Terminal and Jetty Roofing and Siding Inspection Report
PTD-GEN-TPT9750-BPN-3025-FORM
EMILY-1 PROJECT FUEL TERMINAL AND JETTY Rev.
Date
ROOFING AND SIDING INSPECTION REPORT Page. of
Project Title : Emily -1 Project Fuel Terminal & Jetty
Job No : 9750
Client : INTERPORT Date : Thursday, May 07, 2020
Main Contractor : PT. TRIPATRA Engineers & Constructors Report No. : 9750-QC-MRR-BCI-00
Sub-Contractor : PT. Bahana Cipta Internusa Page : of
Installation of Framing
Condition of Fastening
COMMENT
M Saoki
QC Inspector Date Date Date