Concern:
Pipe water supply and sewage water installation not as per common standard and not mentioned it on
the specification.
Company rejected that installation and request Contractor to rectify.
To rectify that Pipe installation Contractor or Sub Contractor must follow the minimum requirement
below:
Company Response
☐ Approved ☐ Rejected
Prepared by:
Juliaspi