You are on page 1of 461

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(1) Clearing & Grubbing (with Stripping)


Unit of Measurement : ha
Output per hour : 0.05

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (12 cu. yd) 2 1.00 1,420.00 2,840.00


b. Payloader (1.50 cu.m.) 1 1.00 1,733.00 1,733.00
c. Bulldozer, D6H SERIES II PSDS/DD 1 1.00 3,379.00 3,379.00

(Hauling Distance - within three (3) km.)

Assumed 150mm cut

Sub - Total for B 7,952.00


C. Total (A + B) 8,099.36
D. Output per hour = 0.05 ha.
E. Direct Unit Cost (C ÷ D) 161,987.20
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 161,987.20
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 14,578.85
I. Contractor's Profit (CP) 8% of G 12,958.98
J. Value Added Tax (VAT) 5% of (G + H + I) 9,476.25
K. Total Unit Cost (G + H + I + J) 199,001.28
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(3)a Individual Removal of Trees (small a, 150mm Ø up to 300mm Ø)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.33 69.42 22.91


b. Skilled Labor 1 0.33 50.18 16.56
c. Unskilled Labor 2 0.33 38.97 25.72

Sub - Total for A 65.19

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.25 1,537.00 384.25


b. Dump Truck (12 cu. yd) 1 0.17 1,420.00 241.40
c. Chain Saw 1 0.17 75.36 12.81
Minor Tools (5% of Labor Cost) 3.26

* Boom Truck - if necessary for trimming in Urban


Areas

Sub - Total for B 641.72


C. Total (A + B) 706.91
D. Output per hour = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 706.91
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Rope, 1" dia. - 5 uses m. 20.00 3.50 14.00

Sub - Total for F 14.00


G. Direct Unit Cost (E + F) 720.91
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 64.88
I. Contractor's Profit (CP) 8% of G 57.67
J. Value Added Tax (VAT) 5% of (G + H + I) 42.17
K. Total Unit Cost (G + H + I + J) 885.64
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(3)b Individual Removal of Trees (small b, above 300mm Ø up to 500mm Ø)
Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.67 69.42 46.51


b. Skilled Labor 1 0.67 50.18 33.62
c. Unskilled Labor 2 0.67 38.97 52.22

Sub - Total for A 132.35

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Dump Truck (12 cu. yd) 1 0.33 1,420.00 468.60
c. Chain Saw 1 0.33 75.36 24.87
Minor Tools (5% of Labor Cost) 6.62

* Boom Truck - if necessary for trimming in Urban


Areas

Sub - Total for B 1,268.59


C. Total (A + B) 1,400.94
D. Output per hour = 1.0000 ea.
E. Direct Unit Cost (C ÷ D) 1,400.94
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Rope, 1" dia. - 5 uses m. 20.00 3.50 14.00

Sub - Total for F 14.00


G. Direct Unit Cost (E + F) 1,414.94
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 127.34
I. Contractor's Profit (CP) 8% of G 113.20
J. Value Added Tax (VAT) 5% of (G + H + I) 82.77
K. Total Unit Cost (G + H + I + J) 1,738.25
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(4)a Individual Removal of Trees (large a, above 500mm Ø up to 750mm Ø)
Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 3.33 69.42 231.17


b. Skilled Labor 1 3.33 50.18 167.10
c. Unskilled Labor 2 3.33 38.97 259.54

Sub - Total for A 657.81

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 2.50 1,537.00 3,842.50


b. Dump Truck (12 cu. yd) 1 1.67 1,420.00 2,371.40
c. Chain Saw 1 1.67 75.36 125.85
Minor Tools (5% of Labor Cost) 32.89

* Boom Truck - if necessary for trimming in Urban


Areas

Sub - Total for B 6,372.64


C. Total (A + B) 7,030.45
D. Output per hour = 01 ea.
E. Direct Unit Cost (C ÷ D) 7,030.45
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Rope, 1" dia. - 5 uses m. 20.00 3.50 14.00

Sub - Total for F 14.00


G. Direct Unit Cost (E + F) 7,044.45
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 634.00
I. Contractor's Profit (CP) 8% of G 563.56
J. Value Added Tax (VAT) 5% of (G + H + I) 412.10
K. Total Unit Cost (G + H + I + J) 8,654.11
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(4)b Individual Removal of Trees (large b, above 750 up to 900mm Ø)
Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 6.67 69.42 463.03


b. Skilled Labor 1 6.67 50.18 334.70
c. Unskilled Labor 2 6.67 38.97 519.86

Sub - Total for A 1,317.59

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 5.00 1,537.00 7,685.00


b. Dump Truck (12 cu. yd) 1 3.33 1,420.00 4,728.60
c. Chain Saw 1 3.33 75.36 250.95
Minor Tools (5% of Labor Cost) 65.88

* Boom Truck - if necessary for trimming in Urban


Areas

Sub - Total for B 12,730.43


C. Total (A + B) 14,048.02
D. Output per hour = 01 ea.
E. Direct Unit Cost (C ÷ D) 14,048.02
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Rope, 1" dia. - 5 uses m. 20.00 3.50 14.00

Sub - Total for F 14.00


G. Direct Unit Cost (E + F) 14,062.02
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1,265.58
I. Contractor's Profit (CP) 8% of G 1,124.96
J. Value Added Tax (VAT) 5% of (G + H + I) 822.63
K. Total Unit Cost (G + H + I + J) 17,275.19
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1) Removal of Structures and Obstruction


Unit of Measurement : ls
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

See derivation for Item Nos. 101(1)a to 101(1)d 0


0
0

Sub - Total for A 0.00

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

0.00
0.00
0.00

See derivation for Item Nos. 101(1)a to 101(1)d

Sub - Total for B 0.00


C. Total (A + B) 0.00
D. Output per hour = 1.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 0.00

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

See derivation for Item Nos. 101(1)a to 101(1)d

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 0.00
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 0.00
I. Contractor's Profit (CP) 8% of G 0.00
J. Value Added Tax (VAT) 5% of (G + H + I) 0.00
K. Total Unit Cost (G + H + I + J) 0.00
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1)a Removal of Concrete Bridge Structures


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 1,998.10 999.05


b. Jackhammer 2 1.00 150.00 300.00
c. Air Compressor (356 - 450 cfm) 1 1.00 965.00 965.00
d. Dump Truck (12 cu.yd.) 1 0.125 1,420.00 177.50
e. Payloader (1.50 cu.m.) 1 0.125 1,733.00 216.63
f. Truck Mounted Crane (31 - 35 mt) 1 0.25 1,861.00 465.25
g. Cutting Outfit 1 1.00 45.45 45.45

* Disposal area (within three (3) km.)

Sub - Total for B 3,168.88


C. Total (A + B) 3,494.54
D. Output per hour = 1.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 3,494.54

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Oxy/Acytelene set 0.10 2,500.00 250.00

Sub - Total for F 250.00


G. Direct Unit Cost (E + F) 3,744.54
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 337.01
I. Contractor's Profit (CP) 8% of G 299.56
J. Value Added Tax (VAT) 5% of (G + H + I) 219.06
K. Total Unit Cost (G + H + I + J) 4,600.16
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1)b Removal of Steel Bridge Structures


Unit of Measurement : kg.
Output per hour : 1,000.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Truck Mounted Crane (31 - 35 mt) 1 1.00 1,861.00 1,861.00


b. Service Truck/Cargo Truck (2 - 5 mt) 1 1.00 783.00 783.00
c. Welding Machine (300A), Gas/Diesel Driven 1 1.00 371.00 371.00
d. Cutting Outfit 1 1.00 45.45 45.45
Minor Tools (10% of Labor Cost) 32.57

Sub - Total for B 3,093.02


C. Total (A + B) 3,418.68
D. Output per hour = 1000.0000 kg.
E. Direct Unit Cost (C ÷ D) 3.42

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Oxy/Acytelene set 0.00025 2,500.00 0.63


b. Welding Rod kg. 0.002 90.00 0.18
c. Rope 1" dia. m. 0.05 3.50 0.18

* Include shoring materials if needed based on


actual field condition

Sub - Total for F 0.98


G. Direct Unit Cost (E + F) 4.40
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 0.40
I. Contractor's Profit (CP) 8% of G 0.35
J. Value Added Tax (VAT) 5% of (G + H + I) 0.26
K. Total Unit Cost (G + H + I + J) 5.40
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1)c Removal of Stone Masonry Lined Drainage Structures


Unit of Measurement : cu.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 1,998.10 999.05


b. Backhoe (0.80 cu.m.) - for loading 1 0.50 1,537.00 768.50
c. Dump Truck (12 cu. yd) 1 1.00 1,420.00 1,420.00

* Disposal area (within three (3) km.)

Sub - Total for B 3,187.55


C. Total (A + B) 3,334.91
D. Output per hour = 10.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 333.49

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 333.49
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 30.01
I. Contractor's Profit (CP) 8% of G 26.68
J. Value Added Tax (VAT) 5% of (G + H + I) 19.51
K. Total Unit Cost (G + H + I + J) 409.69
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1)d Removal of Concrete Drainage Structures


Unit of Measurement : cu.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 1,998.10 999.05


b. Backhoe (0.80 cu.m.) - for loading 1 0.25 1,537.00 384.25
c. Dump Truck (12 cu. yd) 1 0.50 1,420.00 710.00
d. Cutting Outfit 1 1.00 45.45 45.45

* Disposal area (within three (3) km.)

Sub - Total for B 2,138.75


C. Total (A + B) 2,336.29
D. Output per hour = 2.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 1,168.15
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Oxy/Acetylene set 0.10 2,500.00 250.00

Sub - Total for F 250.00


G. Direct Unit Cost (E + F) 1,418.15
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 127.63
I. Contractor's Profit (CP) 8% of G 113.45
J. Value Added Tax (VAT) 5% of (G + H + I) 82.96
K. Total Unit Cost (G + H + I + J) 1,742.19
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)a Removal of RCPC (24" dia.) - 610mm dia.


Unit of Measurement : ea
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00


b. Boom Truck (2 - 5 mt) 1 0.50 1,017.90 508.95
Minor Tools (10 % of Labor Cost) 14.74

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B 2,060.69


C. Total (A + B) 2,208.05
D. Output per hour = 6.0000 ea.
E. Direct Unit Cost (C ÷ D) 368.01

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 368.01
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 33.12
I. Contractor's Profit (CP) 8% of G 29.44
J. Value Added Tax (VAT) 5% of (G + H + I) 21.53
K. Total Unit Cost (G + H + I + J) 452.10
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)b Removal of RCPC (30" dia.) - 760mm dia.


Unit of Measurement : ea
Output per hour : 5.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00


b. Boom Truck (2 - 5 mt) 1 0.50 1,017.90 508.95
Minor Tools (10 % of Labor Cost) 14.74

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B 2,060.69


C. Total (A + B) 2,208.05
D. Output per hour = 5.0000 ea.
E. Direct Unit Cost (C ÷ D) 441.61
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 441.61
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 39.74
I. Contractor's Profit (CP) 8% of G 35.33
J. Value Added Tax (VAT) 5% of (G + H + I) 25.83
K. Total Unit Cost (G + H + I + J) 542.52
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)c Removal of RCPC (36" dia.) - 910mm dia


Unit of Measurement : ea
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00


b. Boom Truck (2 - 5 mt) 1 0.50 1,017.90 508.95
Minor Tools (10 % of Labor Cost) 14.74

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B 2,060.69


C. Total (A + B) 2,208.05
D. Output per hour = 4.0000 ea.
E. Direct Unit Cost (C ÷ D) 552.01
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 552.01
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 49.68
I. Contractor's Profit (CP) 8% of G 44.16
J. Value Added Tax (VAT) 5% of (G + H + I) 32.29
K. Total Unit Cost (G + H + I + J) 678.15
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)d Removal of RCPC (42" dia.) - 1070mm dia.


Unit of Measurement : ea
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00


b. Boom Truck (2 - 5 mt) 1 0.50 1,017.90 508.95
Minor Tools (10 % of Labor Cost) 14.74

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B 2,060.69


C. Total (A + B) 2,208.05
D. Output per hour = 4.000 ea.
E. Direct Unit Cost (C ÷ D) 552.01
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 552.01
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 49.68
I. Contractor's Profit (CP) 8% of G 44.16
J. Value Added Tax (VAT) 5% of (G + H + I) 32.29
K. Total Unit Cost (G + H + I + J) 678.15
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)e Removal of RCPC (48" dia.) - 1220mm dia


Unit of Measurement : ea
Output per hour : 3.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00


b. Boom Truck (2 - 5 mt) 1 0.50 1,017.90 508.95
Minor Tools (10 % of Labor Cost) 14.74

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B 2,060.69


C. Total (A + B) 2,208.05
D. Output per hour = 3.000 ea.
E. Direct Unit Cost (C ÷ D) 736.02

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 736.02
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 66.24
I. Contractor's Profit (CP) 8% of G 58.88
J. Value Added Tax (VAT) 5% of (G + H + I) 43.06
K. Total Unit Cost (G + H + I + J) 904.19
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)f Removal of RCPC (60" dia.) - 1520mm dia.


Unit of Measurement : ea
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00


b. Boom Truck (2 - 5 mt) 1 0.50 1,017.90 508.95
Minor Tools (10 % of Labor Cost) 14.74

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B 2,060.69


C. Total (A + B) 2,208.05
D. Output per hour = 2.000 ea.
E. Direct Unit Cost (C ÷ D) 1,104.02

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 1,104.02
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 99.36
I. Contractor's Profit (CP) 8% of G 88.32
J. Value Added Tax (VAT) 5% of (G + H + I) 64.59
K. Total Unit Cost (G + H + I + J) 1,356.29
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)g Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200mm Ø), L=10 ft.
Unit of Measurement : ea.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) 1 1.00 922.00 922.00


b. Cargo Truck (2 - 5 mt) 1 0.50 783.00 391.50
Minor Tools (10% of Labor Cost) 14.74

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B 1,328.24


C. Total (A + B) 1,475.60
D. Output per hour = 2.0000 ea.
E. Direct Unit Cost (C ÷ D) 737.80
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 737.80
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 66.40
I. Contractor's Profit (CP) 8% of G 59.02
J. Value Added Tax (VAT) 5% of (G + H + I) 43.16
K. Total Unit Cost (G + H + I + J) 906.38
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)a.1 Removal of Existing Concrete Pavement (0.23m thk.)


Unit of Measurement : sq.m.
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 1.00 1,998.10 1,998.10


b. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
c. Dump Truck (12 cu. yd) 1 0.50 1,420.00 710.00
Minor Tools (10% of Labor Cost) 14.74

* Disposal area (within three (3) km.)

Sub - Total for B 4,455.84


C. Total (A + B) 4,603.20
D. Output per hour = 40.00 sq.m.
E. Direct Unit Cost (C ÷ D) 115.08
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 115.08
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 10.36
I. Contractor's Profit (CP) 8% of G 9.21
J. Value Added Tax (VAT) 5% of (G + H + I) 6.73
K. Total Unit Cost (G + H + I + J) 141.38
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)a.2 Removal of Existing PCC Pavement, 0.23m thk. (for Reblocking at intermittent section)
Unit of Measurement : sq.m.
Output per hour : 30.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 1.00 1,998.10 1,998.10


b. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
c. Dump Truck (12 cu. yd) 1 0.50 1,420.00 710.00
d. Concrete Saw (7.5 Hp), 14" Blade Ø 1 0.50 32.63 16.32
Minor Tools (10% of Labor Cost) 14.74

* Disposal area (within three (3) km.)

Sub - Total for B 4,472.15


C. Total (A + B) 4,619.51
D. Output per hour = 30.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 153.98
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20

Sub - Total for F 1.20


G. Direct Unit Cost (E + F) 155.18
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 13.97
I. Contractor's Profit (CP) 8% of G 12.41
J. Value Added Tax (VAT) 5% of (G + H + I) 9.08
K. Total Unit Cost (G + H + I + J) 190.64
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)b Removal of Existing Asphalt Pavement (100mm thk.)


Unit of Measurement : sq.m.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader w/ Scarifier, G710A 1 1.00 2,173.00 2,173.00


b. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
c. Dump Truck (12 cu. yd) 1 0.50 1,420.00 710.00
Minor Tools (10% of Labor Cost) 14.74

* Disposal area (within three (3) km.)

Sub - Total for B 4,630.74


C. Total (A + B) 4,778.10
D. Output per hour = 60.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 79.63
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 79.63
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 7.17
I. Contractor's Profit (CP) 8% of G 6.37
J. Value Added Tax (VAT) 5% of (G + H + I) 4.66
K. Total Unit Cost (G + H + I + J) 97.83
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)c Removal of Sidewalk (100mm thk)


Unit of Measurement : sq.m.
Output per hour : 75.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 1.00 1,998.10 1,998.10


b. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00
c. Dump Truck (12 cu. yd) 1 0.50 1,420.00 710.00

* Disposal area (within three (3) km.)

Sub - Total for B 4,245.10


C. Total (A + B) 4,392.46
D. Output per hour = 75.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 58.57
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 58.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5.27
I. Contractor's Profit (CP) 8% of G 4.69
J. Value Added Tax (VAT) 5% of (G + H + I) 3.43
K. Total Unit Cost (G + H + I + J) 71.95
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(4)a Removal of Curb


Unit of Measurement : m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 1,998.10 999.05


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Dump Truck (12 cu. yd) 1 0.50 1,420.00 710.00

* Disposal area (within three (3) km.)

Sub - Total for B 2,477.55


C. Total (A + B) 2,624.91
D. Output per hour = 50.00000 m.
E. Direct Unit Cost (C ÷ D) 52.50
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 52.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4.72
I. Contractor's Profit (CP) 8% of G 4.20
J. Value Added Tax (VAT) 5% of (G + H + I) 3.07
K. Total Unit Cost (G + H + I + J) 64.49
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(4)b Removal of Curb & Gutter


Unit of Measurement : m
Output per hour : 30.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe w/ Pavement (0.80 cu.m.) 1 0.50 1,998.10 999.05


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Dump Truck (12 cu. yd) 1 0.50 1,420.00 710.00

* Disposal area (within three (3) km.)

Sub - Total for B 2,477.55


C. Total (A + B) 2,624.91
D. Output per hour = 30.00000 m.
E. Direct Unit Cost (C ÷ D) 87.50
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 87.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 7.87
I. Contractor's Profit (CP) 8% of G 7.00
J. Value Added Tax (VAT) 5% of (G + H + I) 5.12
K. Total Unit Cost (G + H + I + J) 107.49
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(1) Roadway Excavation (Unsuitable)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (12 cu. yd) 2 1.00 1,420.00 2,840.00


b. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00
c. Payloader (1.50 cu.m.) at disposal site 1 0.10 1,733.00 173.30
Minor Tools (10% of Labor Cost) 18.63

* Disposal area (within three (3) km.)

Sub - Total for B 4,568.93


C. Total (A + B) 4,755.26
D. Output per hour = 20.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 237.76
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 237.76
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 21.40
I. Contractor's Profit (CP) 8% of G 19.02
J. Value Added Tax (VAT) 5% of (G + H + I) 13.91
K. Total Unit Cost (G + H + I + J) 292.09
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(2)a Roadway Excavation (Surplus Common)


Unit of Measurement : cu.m.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Bulldozer, D6H SERIES II PSDS/DD 1 1.00 3,379.00 3,379.00


b. Payloader (1.50 cu.m.) 1 1.00 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) - at disposal area 1 0.25 1,733.00 433.25
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00

(Hauling Distance - within three (3) km.)

Sub - Total for B 8,385.25


C. Total (A + B) 8,532.61
D. Output per hour = 60.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 142.21
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 142.21
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 12.80
I. Contractor's Profit (CP) 8% of G 11.38
J. Value Added Tax (VAT) 5% of (G + H + I) 8.32
K. Total Unit Cost (G + H + I + J) 174.71
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(2)b Roadway Excavation (Surplus Common)


Unit of Measurement : cu.m.
Output per hour : 80.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Bulldozer, D6H SERIES II PSDS/DD 1 1.00 3,379.00 3,379.00


b. Payloader (1.50 cu.m.) 1 1.00 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) - at disposal area 1 0.30 1,733.00 519.90
d. Dump Truck (12 cu.yd.) 3 1.00 1,420.00 4,260.00
e. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00

(Hauling Distance - within three (3) km.)

Sub - Total for B 11,428.90


C. Total (A + B) 11,576.26
D. Output per hour = 80.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 144.70
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 144.70
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 13.02
I. Contractor's Profit (CP) 8% of G 11.58
J. Value Added Tax (VAT) 5% of (G + H + I) 8.47
K. Total Unit Cost (G + H + I + J) 177.77
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)a Roadway Excavation (Surplus Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 56.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Bulldozer w/ Ripper, D6H SERIES II PSDS/DD 1 1.00 3,885.85 3,885.85


b. Payloader (1.50 cu.m.) 1 1.00 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) - at disposal area 1 0.25 1,733.00 433.25
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e. Backhoe (0.80 cu.m.) w/ attachment 1 1.00 1,537.00 1,537.00

(Hauling Distance - within three (3) km.)

Sub - Total for B 10,429.10


C. Total (A + B) 10,576.46
D. Output per hour = 56.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 188.87
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 188.87
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 17.00
I. Contractor's Profit (CP) 8% of G 15.11
J. Value Added Tax (VAT) 5% of (G + H + I) 11.05
K. Total Unit Cost (G + H + I + J) 232.02
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)b Roadway Excavation (Surplus Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 42.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Bulldozer w/ Ripper, D6H SERIES II PSDS/DD 1 1.00 3,885.85 3,885.85


b. Payloader (1.50 cu.m.) 1 1.00 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) - at disposal area 1 0.20 1,733.00 346.60
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00

(Hauling Distance - within three (3) km.)

Sub - Total for B 8,805.45


C. Total (A + B) 8,952.81
D. Output per hour = 42.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 213.16
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 213.16
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 19.18
I. Contractor's Profit (CP) 8% of G 17.05
J. Value Added Tax (VAT) 5% of (G + H + I) 12.47
K. Total Unit Cost (G + H + I + J) 261.87
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)c Roadway Excavation (Surplus Hard Rock) - Blasting


Unit of Measurement : cu.m.
Output per hour : 4.20

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman (Drilling) 1 0.40 69.42 27.768
b. Skilled Labor 2 0.40 50.18 40.144
c. Unskilled Labor 4 0.40 38.97 62.352
a. Construction Foreman (Blasting) 1 0.20 69.42 13.884
b. Skilled Labor 1 0.20 50.18 10.036
c. Unskilled Labor 2 0.20 38.97 15.588
a. Construction Foreman (Disposal) 1 0.40 69.42 27.768
b Unskilled Labor 2 0.40 38.97 31.176
Sub - Total for A 228.72

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.20 1,537.00 307.40


b. Payloader (1.50 cu.m.) 1 0.15 1,733.00 259.95
c. Payloader (1.50 cu.m.) - at disposal area 1 0.05 1,733.00 86.65
d. Dump Truck (12 cu.yd.) 1 0.40 1,420.00 568.00
e. Pneumatic Drilling Machine 2 0.40 170.00 136.00
f. Air Compressor (161 - 185 cfm) 1 0.40 502.00 200.80
(Hauling Distance - within three (3) km.)

Sub - Total for B 1,558.80


C. Total (A + B) 1,787.52
D. Output per hour = 4.2000 cu.m.
E. Direct Unit Cost (C ÷ D) 425.60
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Dynamite kg. 0.40 280.00 112.00


b. Detonation Cord m. 2.00 80.00 160.00
c. Detonator pc. 0.15 260.00 39.00
d. Ammonium Sulfate kg. 0.20 75.00 15.00
e. Blasting Cap pc. 0.40 45.00 18.00
f. Safety Fuse m. 0.10 40.00 4.00

Sub - Total for F 348.00


G. Direct Unit Cost (E + F) 773.60
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 69.62
I. Contractor's Profit (CP) 8% of G 61.89
J. Value Added Tax (VAT) 5% of (G + H + I) 45.26
K. Total Unit Cost (G + H + I + J) 950.37
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)d Roadway Excavation (Surplus Hard Rock) - Blasting (Tunnel Excavation)
Unit of Measurement : cu.m.
Output per hour : 1.65

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman (Drilling) 1 1.00 69.42 69.42
b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88
a. Construction Foreman (Blasting) 1 1.00 69.42 69.42
b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94
a. Construction Foreman (Disposal) 1 0.50 69.42 34.71
b Unskilled Labor 2 0.50 38.97 38.97
Sub - Total for A 596.88

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Backhoe w/ Chipping Hammer (0.80 cu.m.) 1 0.10 1,998.10 199.81
c. Dump Truck (12 cu. yd) 1 0.50 1,420.00 710.00
d. Pneumatic Drilling Machine 2 1.00 170.00 340.00
e. Air Compressor (161 - 185 cfm) 1 1.00 502.00 502.00
f. Payloader (1.50 cu.m.) 1 0.20 1,733.00 346.60
g. Payloader (1.50 cu.m.) - at disposal area 1 0.03 1,733.00 51.99
h. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50

(Hauling Distance - within three (3) km.)

Sub - Total for B 3,041.40


C. Total (A + B) 3,638.28
D. Output per hour = 1.65 cu.m.
E. Direct Unit Cost (C ÷ D) 2,205.02
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Dynamite kg. 2.00 280.00 560.00


b. Detonation Cord m. 1.40 80.00 112.00
c. Detonator pc. 2.00 260.00 520.00
d. Ammonium Sulfate kg. 1.00 75.00 75.00
e. Blasting Cap pc. 0.45 45.00 20.25
f. Safety Fuse m. 0.10 40.00 4.00

Sub - Total for F 1,291.25


G. Direct Unit Cost (E + F) 3,496.27
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 314.66
I. Contractor's Profit (CP) 8% of G 279.70
J. Value Added Tax (VAT) 5% of (G + H + I) 204.53
K. Total Unit Cost (G + H + I + J) 4,295.17
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(4) Roadway Excavation (Surplus Unclassified)


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Bulldozer, D6H SERIES II PSDS/DD 1 1.00 3,379.00 3,379.00


b. Payloader (1.50 cu.m.) 1 1.00 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) - at disposal area 1 0.20 1,733.00 346.60
d. Dump Truck (12 cu. yd) 2 1.00 1,420.00 2,840.00

(Hauling Distance - within three (3) km.)

Sub - Total for B 8,298.60


C. Total (A + B) 8,445.96
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 168.92

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 168.92
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 15.20
I. Contractor's Profit (CP) 8% of G 13.51
J. Value Added Tax (VAT) 5% of (G + H + I) 9.88
K. Total Unit Cost (G + H + I + J) 207.52
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)a Structure Excavation (Common Soil)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (12 cu. yd) 2 1.00 1,420.00 2,840.00


b. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00
Minor Tools (10% of Labor Cost) 18.63

Sub - Total for B 4,395.63


C. Total (A + B) 4,581.96
D. Output per hour = 20.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 229.10

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 229.10
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 20.62
I. Contractor's Profit (CP) 8% of G 18.33
J. Value Added Tax (VAT) 5% of (G + H + I) 13.40
K. Total Unit Cost (G + H + I + J) 281.45
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)b Structure Excavation (Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 14.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (12 cu. yd) 2 1.00 1,420.00 2,840.00


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50
c. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 1,998.10 999.05
Minor Tools (10% of Labor Cost ) 18.63

Sub - Total for B 4,626.18


C. Total (A + B) 4,812.51
D. Output per hour = 14.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 343.75

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 343.75
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 30.94
I. Contractor's Profit (CP) 8% of G 27.50
J. Value Added Tax (VAT) 5% of (G + H + I) 20.11
K. Total Unit Cost (G + H + I + J) 422.30
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)c Structure Excavation (Solid Rock)


Unit of Measurement : cu.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (12 cu. yd) 1 1.00 1,420.00 1,420.00


b. Backhoe (0.80 cu.m.) 1 0.25 1,537.00 384.25
c. Backhoe w/ Breaker (0.80 cu.m.) 1 0.75 1,998.10 1,498.58
Minor Tools (10% of Labor Cost) 18.63

Sub - Total for B 3,321.46


C. Total (A + B) 3,507.79
D. Output per hour = 4.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 876.95

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 876.95
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 78.93
I. Contractor's Profit (CP) 8% of G 70.16
J. Value Added Tax (VAT) 5% of (G + H + I) 51.30
K. Total Unit Cost (G + H + I + J) 1,077.33
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)a Bridge Excavation (Common Soil)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

b. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00


b. Dump Truck (12 cu. yd) 2 1.00 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 19.75

Sub - Total for B 4,396.75


C. Total (A + B) 4,594.29
D. Output per hour = 20.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 229.71
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 229.71
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 20.67
I. Contractor's Profit (CP) 8% of G 18.38
J. Value Added Tax (VAT) 5% of (G + H + I) 13.44
K. Total Unit Cost (G + H + I + J) 282.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)b Bridge Excavation (Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 14.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 1,998.10 999.05
c. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 19.75

Sub - Total for B 4,627.30


C. Total (A + B) 4,824.84
D. Output per hour = 14.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 344.63

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 344.63
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 31.02
I. Contractor's Profit (CP) 8% of G 27.57
J. Value Added Tax (VAT) 5% of (G + H + I) 20.16
K. Total Unit Cost (G + H + I + J) 423.38
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)c Bridge Excavation (Solid Rock)


Unit of Measurement : cu.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Backhoe w/ Breaker (0.80 cu.m.) 1 1.00 1,998.10 1,998.10
c. Dump Truck (12 cu. yd) 1 0.50 1,420.00 710.00
Minor Tools (10% of Labor Cost) 19.75

Sub - Total for B 3,496.35


C. Total (A + B) 3,693.89
D. Output per hour = 4.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 923.47
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 923.47
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 83.11
I. Contractor's Profit (CP) 8% of G 73.88
J. Value Added Tax (VAT) 5% of (G + H + I) 54.02
K. Total Unit Cost (G + H + I + J) 1,134.49
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)d Bridge Excavation (Solid Rock)


Unit of Measurement : cu.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Jack Hammer 2 1.00 150.00 300.00


b. Air Compressor (356 - 450 cfm) 1 1.00 965.00 965.00
c. Backhoe (0.80 cu.m.) 1 0.15 1,537.00 230.55
d. Dump Truck (12 cu. yd) 1 0.15 1,420.00 213.00
Minor Tools (10% of Labor Cost) 19.75

Sub - Total for B 1,728.30


C. Total (A + B) 1,925.84
D. Output per hour = 1.500 cu.m.
E. Direct Unit Cost (C ÷ D) 1,283.90
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 1,283.90
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 115.55
I. Contractor's Profit (CP) 8% of G 102.71
J. Value Added Tax (VAT) 5% of (G + H + I) 75.11
K. Total Unit Cost (G + H + I + J) 1,577.27
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(3) Foundation Fill


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 225.30

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Plate Compactor (5 Hp) 1 1.00 123.00 123.00


b. Water Truck/Pump (16000L) 1 0.01 2,450.00 24.50
Minor Tools (10% of Labor Cost) 22.53

Sub - Total for B 170.03


C. Total (A + B) 395.33
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 316.26
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Filling Materials cu.m. 1.15 465.00 534.75

Sub - Total for F 534.75


G. Direct Unit Cost (E + F) 851.01
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 76.59
I. Contractor's Profit (CP) 8% of G 68.08
J. Value Added Tax (VAT) 5% of (G + H + I) 49.78
K. Total Unit Cost (G + H + I + J) 1,045.47
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(4) Excavation ordered below Plan Elevation


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (12 cu. yd) 2 1.00 1,420.00 2,840.00


b. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00
Minor Tools (10% of Labor Cost) 18.63

Sub - Total for B 4,395.63


C. Total (A + B) 4,581.96
D. Output per hour = 20 cu.m.
E. Direct Unit Cost (C ÷ D) 229.10

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 229.10
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 20.62
I. Contractor's Profit (CP) 8% of G 18.33
J. Value Added Tax (VAT) 5% of (G + H + I) 13.40
K. Total Unit Cost (G + H + I + J) 281.45
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)a Shoring


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

Note:
*) The component quantity of items of work involved such as item 404/405/509 shall be based on the
actual design of the shoring.
**) Costing of this item shall be based on the standard Detailed Unit Price Analysis (DUPA) of item 404/405/509
as processed component pay item.

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.0000 l.s.
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount

F. Materials/Processed Component Pay Item

a. 404 - Reinforcing Steel Bar kg. *


b. 405 - Structural Concrete cu.m. *
c. 509 - Steel Sheet Pile l.m. *

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)b Cribbing/Cofferdamming


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 160 69.42 11,107.20


b. Skilled Labor 2 160 50.18 16,057.60
c. Unskilled Labor 4 160 38.97 24,940.80

Sub - Total for A 52,105.60

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (36 - 40 mt) 1 160.00 1,902.00 304,320.00


b. Vibro Hammer (Hydraulic Operated) 1 160.00 2,123.00 339,680.00
c. Welding Machine (300 A, Gas/Diesel Driven 1 40.00 371.00 14,840.00
d. Cutting Outfit 1 40.00 45.45 1,818.00
e. Water Pump, 100mm suction diameter 1 160.00 266.25 42,600.00

Sub - Total for B 703,258.00


C. Total (A + B) 755,363.60
D. Output = 1.0000 l.s.
E. Direct Unit Cost (C ÷ D) 755,363.60
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Steel Sheet Pile kg. 69,120.00 48.00 3,317,760.00


b. Walling, Bracing, Diagonal, etc. kg. 7,323.77 48.00 351,540.96
Miscellaneous (1% of Materials Cost) 36,693.01

Note:
a.) The assume dimesion of area to be provided with cofferdam is 12m x 12m square with
Steel Sheet Piles depth of 9m at 48 kg./m.
b.) The quantity of component materials requirement may vary depending on the actual
design of Cribbing/Cofferdamming.

Sub - Total for F 3,705,993.97


G. Direct Unit Cost (E + F) 4,461,357.57
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 401,522.18
I. Contractor's Profit (CP) 8% of G 356,908.61
J. Value Added Tax (VAT) 5% of (G + H + I) 260,989.42
K. Total Unit Cost (G + H + I + J) 5,480,777.77
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(6) Pipe Culvert and Drain Excavation


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (12 cu. yd) 2 1.00 1,420.00 2,840.00


b. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00
Minor Tools (10% of Labor Cost) 18.63

Sub - Total for B 4,395.63


C. Total (A + B) 4,581.96
D. Output per hour = 20.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 229.10
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 229.10
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 20.62
I. Contractor's Profit (CP) 8% of G 18.33
J. Value Added Tax (VAT) 5% of (G + H + I) 13.40
K. Total Unit Cost (G + H + I + J) 281.45
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(1)a Embankment (from Borrow)


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 4,778.86
D. Output per hour = 50.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 95.58
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Common Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 160.00 200.00

Sub - Total for F 200.00


G. Direct Unit Cost (E + F) 295.58
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 26.60
I. Contractor's Profit (CP) 8% of G 23.65
J. Value Added Tax (VAT) 5% of (G + H + I) 17.29
K. Total Unit Cost (G + H + I + J) 363.12
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(1)b Embankment from Roadway Excavation


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
For Excavation Work:
a. Construction Foreman 1 0.83 69.42 57.62
b. Unskilled Labor 2 0.83 38.97 64.69

Spreading and Compaction:


a. Construction Foreman 1 1.00 69.42 69.42
b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 269.67

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment
For Excavation Work:
a. Bulldozer, D6H SERIES II PSDS/DD 1 0.83 3,379.00 2,804.57
b. Payloader (1.50 cu.m.) 1 0.83 1,733.00 1,438.39
c. Dump Truck (12 cu.yd.) 2 0.83 1,420.00 2,357.20

Spreading and Compaction:


a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00
b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 11,231.66


C. Total (A + B) 11,501.33
D. Output per hour = 50.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 230.03
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 230.03
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 20.70
I. Contractor's Profit (CP) 8% of G 18.40
J. Value Added Tax (VAT) 5% of (G + H + I) 13.46
K. Total Unit Cost (G + H + I + J) 282.59
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(2) Selected Borrow for topping , case 1


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 4,778.86
D. Output per hour = 50.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 95.58
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Selected Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 420.00 525.00

Sub - Total for F 525.00


G. Direct Unit Cost (E + F) 620.58
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 55.85
I. Contractor's Profit (CP) 8% of G 49.65
J. Value Added Tax (VAT) 5% of (G + H + I) 36.30
K. Total Unit Cost (G + H + I + J) 762.38
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(3) Selected Borrow for topping , case 2


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 4,778.86
D. Output per hour = 50.00000 cu.m.
E. Direct Unit Cost (C ÷ D) 95.58
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Selected Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 420.00 525.00

Sub - Total for F 525.00


G. Direct Unit Cost (E + F) 620.58
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 55.85
I. Contractor's Profit (CP) 8% of G 49.65
J. Value Added Tax (VAT) 5% of (G + H + I) 36.30
K. Total Unit Cost (G + H + I + J) 762.38
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(4) Earth Berm


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 225.30

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Plate Compactor (5 Hp) 1 1.00 123.00 123.00


b.Water Truck/Pump (16000L) 1 0.01 2,450.00 24.50
Minor Tools (10% of Labor Cost) 22.53

Sub - Total for B 170.03


C. Total (A + B) 395.33
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 316.26
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Filling Materials cu.m. 1.25 420.00 525.00

Sub - Total for F 525.00


G. Direct Unit Cost (E + F) 841.26
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 75.71
I. Contractor's Profit (CP) 8% of G 67.30
J. Value Added Tax (VAT) 5% of (G + H + I) 49.21
K. Total Unit Cost (G + H + I + J) 1,033.49
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(1) Subgrade Preparation (Common Material)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 4,778.86
D. Output per hour = 300.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 15.93
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 15.93
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1.43
I. Contractor's Profit (CP) 8% of G 1.27
J. Value Added Tax (VAT) 5% of (G + H + I) 0.93
K. Total Unit Cost (G + H + I + J) 19.57
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(2) Subgrade Preparation (Existing Pavement)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 4,778.86
D. Output per hour = 300.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 15.93
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 15.93
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1.43
I. Contractor's Profit (CP) 8% of G 1.27
J. Value Added Tax (VAT) 5% of (G + H + I) 0.93
K. Total Unit Cost (G + H + I + J) 19.57
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(3) Subgrade Preparation (Unsuitable Material)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 4,778.86
D. Output per hour = 300.00000 sq.m.
E. Direct Unit Cost (C ÷ D) 15.93
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 15.93
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1.43
I. Contractor's Profit (CP) 8% of G 1.27
J. Value Added Tax (VAT) 5% of (G + H + I) 0.93
K. Total Unit Cost (G + H + I + J) 19.57
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 200 Aggregate Subbase Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 4,778.86
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 95.58
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Aggregate Subbase Course cu.m. 1.15 350.00 402.50


(w/ 15% Shrinkage Factor)

Sub - Total for F 402.50


G. Direct Unit Cost (E + F) 498.08
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 44.83
I. Contractor's Profit (CP) 8% of G 39.85
J. Value Added Tax (VAT) 5% of (G + H + I) 29.14
K. Total Unit Cost (G + H + I + J) 611.89
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 200(1) Aggregate Subbase Course (for Intermittent Reblocking)


Unit of Measurement : cu.m
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Plate Compactor (5 Hp) 1 0.25 123.00 30.75
d. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,662.25


C. Total (A + B) 4,809.61
D. Output per hour = 40.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 120.24

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Aggregate Subbase Course cu.m. 1.15 580.00 667.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 667.00


G. Direct Unit Cost (E + F) 787.24
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 70.85
I. Contractor's Profit (CP) 8% of G 62.98
J. Value Added Tax (VAT) 5% of (G + H + I) 46.05
K. Total Unit Cost (G + H + I + J) 967.12
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 201 Aggregate Base Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 4,778.86
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 95.58

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Aggregate Base Course cu.m. 1.15 650.00 747.50


(w/ 15% Shrinkage Factor)

Sub - Total for F 747.50


G. Direct Unit Cost (E + F) 843.08
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 75.88
I. Contractor's Profit (CP) 8% of G 67.45
J. Value Added Tax (VAT) 5% of (G + H + I) 49.32
K. Total Unit Cost (G + H + I + J) 1,035.72
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 201(1) Aggregate Base Course (for Reblocking)


Unit of Measurement : cu.m
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
a. Plate Compactor (5 Hp) 1 0.25 123.00 30.75
d. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,662.25


C. Total (A + B) 4,809.61
D. Output per hour = 40.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 120.24
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Aggregate Base Course cu.m. 1.15 650.00 747.50


(w/ 15% Shrinkage Factor)

Sub - Total for F 747.50


G. Direct Unit Cost (E + F) 867.74
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 78.10
I. Contractor's Profit (CP) 8% of G 69.42
J. Value Added Tax (VAT) 5% of (G + H + I) 50.76
K. Total Unit Cost (G + H + I + J) 1,066.02
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 202 Crushed Aggregate Base Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 4,778.86
D. Output per hour = 50.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 95.58
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Crushed Aggregate Base Course cu.m. 1.15 700.00 805.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 805.00


G. Direct Unit Cost (E + F) 900.58
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 81.05
I. Contractor's Profit (CP) 8% of G 72.05
J. Value Added Tax (VAT) 5% of (G + H + I) 52.68
K. Total Unit Cost (G + H + I + J) 1,106.36
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 203 Lime Stabilized Road Mix Base Course


Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 459.12

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 5,090.62
D. Output per hour = 15.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 339.37
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Hydrated Lime, Type N (Normal) bag 2.80 180.00 504.00


b. Aggregate Base Course cu.m. 1.15 650.00 747.50

Sub - Total for F 1,251.50


G. Direct Unit Cost (E + F) 1,590.87
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 143.18
I. Contractor's Profit (CP) 8% of G 127.27
J. Value Added Tax (VAT) 5% of (G + H + I) 93.07
K. Total Unit Cost (G + H + I + J) 1,954.39
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 204 Portland Cement Stabilized Road Mix Base Course
Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 459.12

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 5,090.62
D. Output per hour = 15.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 339.37

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 3.00 220.00 660.00


b. Aggregate Base Course cu.m. 1.15 650.00 747.50

Sub - Total for F 1,407.50


G. Direct Unit Cost (E + F) 1,746.87
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 157.22
I. Contractor's Profit (CP) 8% of G 139.75
J. Value Added Tax (VAT) 5% of (G + H + I) 102.19
K. Total Unit Cost (G + H + I + J) 2,146.04
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 205 Asphalt Stabilized Road Mix Base Course


Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 459.12

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50
d. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00

Sub - Total for B 5,567.50


C. Total (A + B) 6,026.62
D. Output per hour = 15.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 401.77

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Emulsified Asphalt SS-1 m.t. 0.07 44,000.00 3,080.00


b. Aggregate Base Course cu.m. 1.15 650.00 747.50

Sub - Total for F 3,827.50


G. Direct Unit Cost (E + F) 4,229.27
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 380.63
I. Contractor's Profit (CP) 8% of G 338.34
J. Value Added Tax (VAT) 5% of (G + H + I) 247.41
K. Total Unit Cost (G + H + I + J) 5,195.66
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 206 Portland Cement Treated Plant Mix Base Course
Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Batching Plant (30 cu.m.) 1 0.50 1,759.50 879.75


b. Dump Truck (12 cu.yd.) 3 0.50 1,352.00 2,028.00
c. Motorized Road Grader (140 hp), G710A 1 0.50 2,173.00 1,086.50
d. Vibratory Roller (10 m.t.), SD100DC 1 0.50 1,846.00 923.00
e. Payloader (1.50 cu.m.), LX80-2C 1 0.50 1,733.00 866.50
f. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50
g. Asphalt Distributor, 10 ft. wide (5 ton) 1 0.10 936.00 93.60

Sub - Total for B 6,489.85


C. Total (A + B) 6,815.51
D. Output per hour = 15.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 454.37
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 3.00 220.00 660.00


b. Aggregate Base Course cu.m. 1.15 650.00 747.50
c. MC 70 Cut-back Asphalt m.t. 0.0075 40,300.00 302.25

Sub - Total for F 1,709.75


G. Direct Unit Cost (E + F) 2,164.12
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 194.77
I. Contractor's Profit (CP) 8% of G 173.13
J. Value Added Tax (VAT) 5% of (G + H + I) 126.60
K. Total Unit Cost (G + H + I + J) 2,658.62
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 300(1) Gravel Surface Course (Uncrushed) Item


Unit of Measurement : cu.m Unit
Output per hour : 50.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 4,778.86 C.
D. Output per hour = 50.0000 cu.m. D.
E. Direct Unit Cost (C ÷ D) 95.58 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Uncrushed Aggregate Surface Course cu.m. 1.15 700.00 805.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 805.00


G. Direct Unit Cost (E + F) 900.58 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 81.05 H.
I. Contractor's Profit (CP) 8% of G 72.05 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 52.68 J.

461-5
K. Total Unit Cost (G + H + I + J) 1,106.36 K.

119+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 300(2) Crushed Aggregate Surface Course Item


Unit of Measurement : cu.m Unit
Output per hour : 50.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 4,778.86 C.
D. Output per hour = 50.0000 cu.m. D.
E. Direct Unit Cost (C ÷ D) 95.58 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Crushed Aggregate Surface Course cu.m. 1.15 750.00 862.50


(w/ 15% Shrinkage Factor)

Sub - Total for F 862.50


G. Direct Unit Cost (E + F) 958.08 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 86.23 H.
I. Contractor's Profit (CP) 8% of G 76.65 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 56.05 J.

461-5
K. Total Unit Cost (G + H + I + J) 1,177.00 K.

121+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 301(1) Bituminous Prime Coat (MC Cut-back Asphalt) Item
Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. MC 70 Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00


(w/ 5% wastage)

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 46,491.23 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,184.21 H.
I. Contractor's Profit (CP) 8% of G 3,719.30 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 2,719.74 J.

461-5
K. Total Unit Cost (G + H + I + J) 57,114.48 K.

123+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 301(2) Bituminous Prime Coat (RC Cut-back Asphalt) Item
Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 47,829.98 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,304.70 H.
I. Contractor's Profit (CP) 8% of G 3,826.40 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 2,798.05 J.

461-5
K. Total Unit Cost (G + H + I + J) 58,759.13 K.

125+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 302(1) Bituminous Tack Coat (RC Cut-back Asphalt) Item
Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 47,829.98 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,304.70 H.
I. Contractor's Profit (CP) 8% of G 3,826.40 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 2,798.05 J.

461-5
K. Total Unit Cost (G + H + I + J) 58,759.13 K.

127+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 302(2) Bituminous Tack Coat (Emulsified Asphalt) Item


Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00 46,200.00


(w/ 5% wastage)

Sub - Total for F 46,200.00


G. Direct Unit Cost (E + F) 50,376.23 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,533.86 H.
I. Contractor's Profit (CP) 8% of G 4,030.10 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 2,947.01 J.

461-5
K. Total Unit Cost (G + H + I + J) 61,887.20 K.

129+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(1) Bituminous Seal Coat (Cover Aggregate) Item


Unit of Measurement : m.t. Unit
Output per hour : 16.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 20 1.00 38.97 779.40

Sub - Total for A 848.82

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00


b. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 2,264.50


C. Total (A + B) 3,113.32 C.
D. Output per hour = 16.0000 m.t. D.
E. Direct Unit Cost (C ÷ D) 194.58 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Cover Aggregate m.t. 1.15 406.25 467.19


(w/ 15% Shrinkage Factor)

Note: 1.60 m.t./cu.m.


using unit wt. of 1,600 kg./m³

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 661.77 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 59.56 H.
I. Contractor's Profit (CP) 8% of G 52.94 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 38.71 J.

461-5
K. Total Unit Cost (G + H + I + J) 812.98 K.

131+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(2) Bituminous Seal Coat (MC Cut-back Asphalt) Item
Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. MC Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00


(w/ 5% Wastage)

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 46,491.23 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,184.21 H.
I. Contractor's Profit (CP) 8% of G 3,719.30 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 2,719.74 J.

461-5
K. Total Unit Cost (G + H + I + J) 57,114.48 K.

133+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(3) Bituminous Seal Coat (RC Cut-back Asphalt) Item
Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% Wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 47,829.98 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,304.70 H.
I. Contractor's Profit (CP) 8% of G 3,826.40 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 2,798.05 J.

461-5
K. Total Unit Cost (G + H + I + J) 58,759.13 K.

135+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(4) Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150) Item
Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Asphalt Cement Penetration Grade 120-150 m.t. 1.05 50,775.00 53,313.75


(w/ 5% Wastage)

Sub - Total for F 53,313.75


G. Direct Unit Cost (E + F) 57,489.98 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5,174.10 H.
I. Contractor's Profit (CP) 8% of G 4,599.20 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 3,363.16 J.

461-5
K. Total Unit Cost (G + H + I + J) 70,626.44 K.

137+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(1) Bituminous Surface Treatment (Aggregate Grading) Item


Unit of Measurement : m.t. Unit
Output per hour : 16.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 20 1.00 38.97 779.40

Sub - Total for A 848.82

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00


c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 2,458.50


C. Total (A + B) 3,307.32 C.
D. Output per hour = 16.0000 m.t. D.
E. Direct Unit Cost (C ÷ D) 206.71 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Aggregates m.t. 1.15 406.25 467.19


(w/ 15% Shrinkage Factor)

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 673.90 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 60.65 H.
I. Contractor's Profit (CP) 8% of G 53.91 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 39.42 J.

461-5
K. Total Unit Cost (G + H + I + J) 827.88 K.

139+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(2) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150) Item
Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Asphalt Cement Penetration Grade 120-150 m.t. 1.05 50,775.00 53,313.75


(w/ 5% Wastage)

Sub - Total for F 53,313.75


G. Direct Unit Cost (E + F) 57,489.98 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5,174.10 H.
I. Contractor's Profit (CP) 8% of G 4,599.20 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 3,363.16 J.

461-5
K. Total Unit Cost (G + H + I + J) 70,626.44 K.

141+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(3) Bituminous Surface Treatment (MC Cut-back Asphalt) Item
Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. MC Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00


(w/ 5% Wastage)

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 46,491.23 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,184.21 H.
I. Contractor's Profit (CP) 8% of G 3,719.30 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 2,719.74 J.

461-5
K. Total Unit Cost (G + H + I + J) 57,114.48 K.

143+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(4) Bituminous Surface Treatment (RC Cut-back Asphalt) Item
Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% Wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 47,829.98 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,304.70 H.
I. Contractor's Profit (CP) 8% of G 3,826.40 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 2,798.05 J.

461-5
K. Total Unit Cost (G + H + I + J) 58,759.13 K.

145+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(5) Bituminous Surface Treatment (Emulsified Asphalt) Item


Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00 46,200.00


(w/ 5% wastage)

Sub - Total for F 46,200.00


G. Direct Unit Cost (E + F) 50,376.23 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,533.86 H.
I. Contractor's Profit (CP) 8% of G 4,030.10 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 2,947.01 J.

461-5
K. Total Unit Cost (G + H + I + J) 61,887.20 K.

147+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(1) Bituminous Penetration Macadam Pavement (Aggregates) Item


Unit of Measurement : m.t. Unit
Output per hour : 16.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 20 1.00 38.97 779.40

Sub - Total for A 848.82

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00


c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 2,458.50


C. Total (A + B) 3,307.32 C.
D. Output per hour = 16.0000 m.t. D.
E. Direct Unit Cost (C ÷ D) 206.71 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Aggregates m.t. 1.15 406.25 467.19


(w/ 15% Shrinkage Factor)

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 673.90 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 60.65 H.
I. Contractor's Profit (CP) 8% of G 53.91 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 39.42 J.

461-5
K. Total Unit Cost (G + H + I + J) 827.88 K.

149+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(2) Bituminous Penetration Macadam Pavement (Asphalt Cement) Item
Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Asphalt Cement (w/ 5% Wastage) m.t. 1.05 50,775.00 53,313.75

Sub - Total for F 53,313.75


G. Direct Unit Cost (E + F) 57,489.98 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5,174.10 H.
I. Contractor's Profit (CP) 8% of G 4,599.20 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 3,363.16 J.

461-5
K. Total Unit Cost (G + H + I + J) 70,626.44 K.

151+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(3) Bituminous Penetration Macadam Pavement (RC Cut-back Asphalt) Item
Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% Wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 47,829.98 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,304.70 H.
I. Contractor's Profit (CP) 8% of G 3,826.40 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 2,798.05 J.

461-5
K. Total Unit Cost (G + H + I + J) 58,759.13 K.

153+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(4) Bituminous Penetration Macadam Pavement (Emulsified Asphalt) Item
Unit of Measurement : m.t. Unit
Output per hour : 0.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87 C.
D. Output per hour = 0.300 m.t. D.
E. Direct Unit Cost (C ÷ D) 4,176.23 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00 46,200.00


(w/ 5% wastage)

Sub - Total for F 46,200.00


G. Direct Unit Cost (E + F) 50,376.23 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,533.86 H.
I. Contractor's Profit (CP) 8% of G 4,030.10 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 2,947.01 J.

461-5
K. Total Unit Cost (G + H + I + J) 61,887.20 K.

155+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(a) Bituminous Road Mix Surface Course Item


Unit of Measurement : m.t. Unit
Output per hour : 12.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 236.51

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Motorized Road Grader w/ Scarifier (140 hp), G7 1 1.00 2,824.90 2,824.90


b. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
c. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
d. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00
e. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50
Minor Tools (10% of Labor Cost) 23.65

Sub - Total for B 6,610.05


C. Total (A + B) 6,846.56 C.
D. Output per hour = 12.0000 m.t. D.
E. Direct Unit Cost (C ÷ D) 570.55 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Crushed Gravel m.t. 1.15 406.25 467.19


b. MC Cut-back Asphalt (7%) m.t. 0.07 40,300.00 2,821.00
c. Hydrated Lime (0.75%) bag 0.30 180.00 54.00

0.0575(2.335)(1.05) = 0.141
0.0075(35.29) = 0.26, say 0.30

Sub - Total for F 3,342.19


G. Direct Unit Cost (E + F) 3,912.73 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 352.15 H.
I. Contractor's Profit (CP) 8% of G 313.02 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 228.89 J.

461-5
K. Total Unit Cost (G + H + I + J) 4,806.79 K.

157+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(b) Bituminous Road Mix Surface Course Item


Unit of Measurement : m.t. Unit
Output per hour : 12.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 236.51

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Motorized Road Grader w/ Scarifier (140 hp), G7 1 1.00 2,824.90 2,824.90


b. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
c. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
d. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00
e. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50
Minor Tools (10% of Labor Cost) 23.65

Sub - Total for B 6,610.05


C. Total (A + B) 6,846.56 C.
D. Output per hour = 12.0000 m.t. D.
E. Direct Unit Cost (C ÷ D) 570.55 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Crushed Gravel m.t. 1.15 406.25 467.19


b. Emulsified Asphalt (10%) m.t. 0.10 44,000.00 4,400.00
c. Hydrated Lime (0.75%) bag 0.30 180.00 54.00

0.08(2.335)(1.05) = 0.196
0.0075(35.29) = 0.26, say 0.30

Sub - Total for F 4,921.19


G. Direct Unit Cost (E + F) 5,491.73 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 494.26 H.
I. Contractor's Profit (CP) 8% of G 439.34 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 321.27 J.

461-5
K. Total Unit Cost (G + H + I + J) 6,746.60 K.

159+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(1) Aggregates for Bituminous Road Mix Surface Course Item
Unit of Measurement : m.t. Unit
Output per hour : 12.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 236.51

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Motorized Road Grader w/ Scarifier (140 hp), G7 1 1.00 2,824.90 2,824.90


b. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
c. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50
Minor Tools (10% of Labor Cost) 23.65

Sub - Total for B 5,674.05


C. Total (A + B) 5,910.56 C.
D. Output per hour = 12.0000 m.t. D.
E. Direct Unit Cost (C ÷ D) 492.55 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Crushed Gravel m.t. 1.15 406.25 467.19

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 959.73 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 86.38 H.
I. Contractor's Profit (CP) 8% of G 76.78 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 56.14 J.

461-5
K. Total Unit Cost (G + H + I + J) 1,179.03 K.

161+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(2) Bituminous Material for Bituminous Road Mix Surface Course Item N
Unit of Measurement : m.t. Unit o
Output per hour : 1.00 Outpu

Designation No. of Person No. of Hours Hourly Rate Amount

Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 236.51

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment B.

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00

Sub - Total for B 936.00


Total (A + B) 1,172.51 C.
Output per hour = 1.0000 m.t. D.
Direct Unit Cost (C ÷ D) 1,172.51 E.

Name and Specification Unit Quantity Unit Cost Amount

Materials F.

a. MC Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00

Sub - Total for F 42,315.00


Direct Unit Cost (E + F) 43,487.51 G.
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 3,913.88 H.
Contractor's Profit (CP) 8% of G 3,479.00 I.
Value Added Tax (VAT) 5% of (G + H + I) 2,544.02 J.

461-5
Total Unit Cost (G + H + I + J) 53,424.41 K.

163+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 307 Bituminous Plant Mix Surface Course-General (50mm thk.) Item N
Unit of Measurement : sq.m. Unit o
Output per hour : 171.30 Outpu

Designation No. of Person No. of Hours Hourly Rate Amount

Labor A.
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 581.90

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment B.

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 15,413.82


Total (A + B) 15,995.72 C.
Output per hour = 171.300 sq.m. D.
Direct Unit Cost (C ÷ D) 93.38 E.

Name and Specification Unit Quantity Unit Cost Amount

Materials F.

a. Bituminous Material (8%) m.t 0.00981 44,000.00 431.64


b. Aggregates, Sand (79%) cu.m. 0.041 650.00 26.65
c. Aggregates, 3/8 (19%) cu.m. 0.010 650.00 6.50
d. Mineral Filler (7%) bag 0.130 240.56 31.27
e. Diesel L 1.165 240.56 280.25

Sub - Total for F 776.32


Direct Unit Cost (E + F) 869.69 G.
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 78.27 H.
Contractor's Profit (CP) 8% of G 69.58 I.
Value Added Tax (VAT) 5% of (G + H + I) 50.88 J.

461-5
Total Unit Cost (G + H + I + J) 1,068.42 K.

165+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 308(a) Cold Asphalt Plant Mix (50mm thk.) Item N
Unit of Measurement : sq.m. Unit o
Output per hour : 171.30 Outpu

Designation No. of Person No. of Hours Hourly Rate Amount

Labor A.
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 581.90

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment B.

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 15,413.82


Total (A + B) 15,995.72 C.
Output per hour = 171.300 sq.m. D.
Direct Unit Cost (C ÷ D) 93.38 E.

Name and Specification Unit Quantity Unit Cost Amount

Materials F.

a. Emulsified Asphalt (10%) m.t 0.01226 44,000.00 539.44


b. Aggregates, Sand (79%) cu.m. 0.041 650.00 26.65
c. Aggregates, 3/8 (19%) cu.m. 0.01 650.00 6.50
d. Mineral Filler (7%) bag 0.13 240.56 31.27
e. Diesel L 1.165 240.56 280.25

Sub - Total for F 884.12


Direct Unit Cost (E + F) 977.49 G.
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 87.97 H.
Contractor's Profit (CP) 8% of G 78.20 I.
Value Added Tax (VAT) 5% of (G + H + I) 57.18 J.

461-5
Total Unit Cost (G + H + I + J) 1,200.85 K.

167+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 308(b) Cold Asphalt Plant Mix (50mm thk.) Item N
Unit of Measurement : sq.m. Unit o
Output per hour : 171.30 Outpu

Designation No. of Person No. of Hours Hourly Rate Amount

Labor A.
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 581.90

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment B.

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 15,413.82


Total (A + B) 15,995.72 C.
Output per hour = 171.300 sq.m. D.
Direct Unit Cost (C ÷ D) 93.38 E.

Name and Specification Unit Quantity Unit Cost Amount

Materials F.

a. MC - 70 Cut-back Asphalt (7%) m.t 0.00858 40,300.00 345.77


b. Aggregates, Sand (79%) cu.m. 0.0488 650.00 31.72
c. Aggregates, 3/8 (19%) cu.m. 0.01 650.00 6.50
d. Mineral Filler (7%) bag 0.13 240.56 31.27
e. Diesel L 1.165 240.56 280.25

Sub - Total for F 695.52


Direct Unit Cost (E + F) 788.90 G.
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 71.00 H.
Contractor's Profit (CP) 8% of G 63.11 I.
Value Added Tax (VAT) 5% of (G + H + I) 46.15 J.

461-5
Total Unit Cost (G + H + I + J) 969.16 K.

169+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 309 Bituminous Plant Mix (Stockpile Maintenance Mixture) Item N
Unit of Measurement : sq.m. Unit o
Output per hour : 171.30 Outpu

Designation No. of Person No. of Hours Hourly Rate Amount

Labor A.
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 581.90

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment B.

a. Dump Truck (12 cu. yd) 2 1.00 1,420.00 2,840.00


b. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
c. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 11,367.82


Total (A + B) 11,949.72 C.
Output per hour = 171.300 sq.m. D.
Direct Unit Cost (C ÷ D) 69.76 E.

Name and Specification Unit Quantity Unit Cost Amount

Materials F.

a. MC - 70 Cut-back Asphalt (10%) m.t 0.01226 40,300.00 494.08


b. Aggregates, Sand (79%) cu.m. 0.041 650.00 26.65
c. Aggregates, 3/8 (19%) cu.m. 0.01 650.00 6.50
d. Mineral Filler (7%) bag 0.13 240.56 31.27
e. Diesel L 1.165 240.56 280.25

Sub - Total for F 838.75


Direct Unit Cost (E + F) 908.51 G.
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 81.77 H.
Contractor's Profit (CP) 8% of G 72.68 I.
Value Added Tax (VAT) 5% of (G + H + I) 53.15 J.

461-5
Total Unit Cost (G + H + I + J) 1,116.11 K.

171+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.1) Bituminous Concrete Surface Course (30mm thk.) Item N
Unit of Measurement : sq.m. Unit o
Output per hour : 285.51 Outpu

Designation No. of Person No. of Hours Hourly Rate Amount

Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 581.90

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment B.

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 6,554.19


Total (A + B) 7,136.09 C.
Output per hour = 285.51 sq.m. D.
Direct Unit Cost (C ÷ D) 24.99 E.
Name and Specification Unit Quantity Unit Cost Amount

Materials F.

a. Bituminous Concrete Surface Course m.t. 0.074 4,500.00 333.00


thickness = 30mm (w/ 5% wastage)

Sub - Total for F 333.00


Direct Unit Cost (E + F) 357.99 G.
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 32.22 H.
Contractor's Profit (CP) 8% of G 28.64 I.
Value Added Tax (VAT) 5% of (G + H + I) 20.94 J.

461-5
Total Unit Cost (G + H + I + J) 439.80 K.

173+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.2) Bituminous Concrete Surface Course (40mm thk.) Item N
Unit of Measurement : sq.m. Unit o
Output per hour : 214.13 Outpu

Designation No. of Person No. of Hours Hourly Rate Amount

Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 581.90

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment B.

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
c. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
Minor Tools (10% of Labor Cost ) 58.19

Sub - Total for B 6,554.19


Total (A + B) 7,136.09 C.
Output per hour = 214.13 sq.m. D.
Direct Unit Cost (C ÷ D) 33.33 E.
Name and Specification Unit Quantity Unit Cost Amount

Materials F.

a. Bituminous Concrete Surface Course m.t. 0.098 4,500.00 441.00


thickness = 40mm (w/ 5% wastage)

Sub - Total for F 441.00


Direct Unit Cost (E + F) 474.33 G.
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 42.69 H.
Contractor's Profit (CP) 8% of G 37.95 I.
Value Added Tax (VAT) 5% of (G + H + I) 27.75 J.

461-5
Total Unit Cost (G + H + I + J) 582.71 K.

175+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.3) Bituminous Concrete Surface Course (50mm thk.) Item N
Unit of Measurement : sq.m. Unit o
Output per hour : 171.30 Outpu

Designation No. of Person No. of Hours Hourly Rate Amount

Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 581.90

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment B.

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
c. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 6,554.19


Total (A + B) 7,136.09 C.
Output per hour = 171.300 sq.m. D.
Direct Unit Cost (C ÷ D) 41.66 E.
Name and Specification Unit Quantity Unit Cost Amount

Materials F.

a. Bituminous Concrete Surface Course m.t. 0.123 4,500.00 553.50


thickness = 50mm (w/ 5% wastage)

Sub - Total for F 553.50


Direct Unit Cost (E + F) 595.16 G.
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 53.56 H.
Contractor's Profit (CP) 8% of G 47.61 I.
Value Added Tax (VAT) 5% of (G + H + I) 34.82 J.

461-5
Total Unit Cost (G + H + I + J) 731.15 K.

177+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.1) Bituminous Concrete Surface Course (30mm thk.) Item N
Unit of Measurement : sq.m. Unit o
Output per hour : 285.51 Outpu

Designation No. of Person No. of Hours Hourly Rate Amount

Labor A.
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 512.48

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment B.

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 51.25

Sub - Total for B 15,406.88


Total (A + B) 15,919.36 C.
Output per hour = 285.51 sq.m. D.
Direct Unit Cost (C ÷ D) 55.76 E.
Name and Specification Unit Quantity Unit Cost Amount

Materials F.

a. Asphalt Cement (8%) m.t 0.00588 40,300.00 236.96


b. Aggregates, Sand (79%) cu.m. 0.025 650.00 16.25
c. Aggregates, 3/8 (19%) cu.m. 0.006 650.00 3.90
d. Mineral Filler (7%) bag 0.078 240.56 18.76
e. Diesel L 0.699 240.56 168.15

Sub - Total for F 444.03


Direct Unit Cost (E + F) 499.79 G.
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 44.98 H.
Contractor's Profit (CP) 8% of G 39.98 I.
Value Added Tax (VAT) 5% of (G + H + I) 29.24 J.

461-5
Total Unit Cost (G + H + I + J) 613.99 K.

179+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.2) Bituminous Concrete Surface Course (40mm thk.) Item N
Unit of Measurement : sq.m. Unit o
Output per hour : 214.13 Outpu

Designation No. of Person No. of Hours Hourly Rate Amount

Labor A.
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 581.90

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment B.

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 15,413.82


Total (A + B) 15,995.72 C.
Output per hour = 214.13 sq.m. D.
Direct Unit Cost (C ÷ D) 74.70 E.
Name and Specification Unit Quantity Unit Cost Amount

Materials F.

a. Asphalt Cement (8%) m.t 0.00785 40,300.00 316.36


b. Aggregates, Sand (79%) cu.m. 0.033 650.00 21.45
c. Aggregates, 3/8 (19%) cu.m. 0.008 650.00 5.20
d. Mineral Filler (7%) bag 0.104 240.56 25.02
e. Diesel L 0.932 240.56 224.20

Sub - Total for F 592.23


Direct Unit Cost (E + F) 666.93 G.
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 60.02 H.
Contractor's Profit (CP) 8% of G 53.35 I.
Value Added Tax (VAT) 5% of (G + H + I) 39.02 J.

461-5
Total Unit Cost (G + H + I + J) 819.32 K.

181+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.3) Bituminous Concrete Surface Course (50mm thk.) Item N
Unit of Measurement : sq.m. Unit o
Output per hour : 171.30 Outpu

Designation No. of Person No. of Hours Hourly Rate Amount

Labor A.
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 581.90

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment B.

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 15,413.82


Total (A + B) 15,995.72 C.
Output per hour = 171.300 sq.m. D.
Direct Unit Cost (C ÷ D) 93.38 E.
Name and Specification Unit Quantity Unit Cost Amount

Materials F.

a. Asphalt Cement (8%) m.t 0.00981 40,300.00 395.34


b. Aggregates, Sand (79%) cu.m. 0.041 650.00 26.65
c. Aggregates, 3/8 (19%) cu.m. 0.01 650.00 6.50
d. Mineral Filler (7%) bag 0.13 240.56 31.27
e. Diesel L 1.165 240.56 280.25

Sub - Total for F 740.02


Direct Unit Cost (E + F) 833.40 G.
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 75.01 H.
Contractor's Profit (CP) 8% of G 66.67 I.
Value Added Tax (VAT) 5% of (G + H + I) 48.75 J.

461-5
Total Unit Cost (G + H + I + J) 1,023.83 K.

183+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.1 PCC Pavement (Plain) - Conventional Method, 150mm thk. Item N
Unit of Measurement : sq.m. Unit o
Output per hour : 107.33 Outpu

Designation No. of Person No. of Hours Hourly Rate Amount

Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment B.

a. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00


b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 12,033.49


Total (A + B) 12,771.27 C.
Output per hour = 107.33 sq.m. D.
Direct Unit Cost (C ÷ D) 118.99 E.
Name and Specification Unit Quantity Unit Cost Amount

Materials F.

a. Reinforcing Steel Bar kg. 0.33 40.00 13.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.0825 850.00 70.13
f. Gravel cu.m. 0.15 650.00 97.50
g. Cement bag 1.43 220.00 314.60
h. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
j. Grease/Tar L 0.0015 300.00 0.45

Sub - Total for F 533.74


Direct Unit Cost (E + F) 652.73 G.
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 58.75 H.
Contractor's Profit (CP) 8% of G 52.22 I.
Value Added Tax (VAT) 5% of (G + H + I) 38.18 J.

461-5
Total Unit Cost (G + H + I + J) 801.88 K.

185+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.1.1 PCC Pavement (Plain) - Conventional Method, 150mm thk. Item N
Unit of Measurement : sq.m. Unit o
Output per hour : 107.33 Outpu

Designation No. of Person No. of Hours Hourly Rate Amount

Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment B.

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 818.99


Total (A + B) 1,556.77 C.
Output per hour = 107.33 sq.m. D.
Direct Unit Cost (C ÷ D) 14.50 E.
Name and Specification Unit Quantity Unit Cost Amount

Materials F.

a. Reinforcing Steel Bar kg. 0.33 40.00 13.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.15 850.00 127.50
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
h. Grease/Tar L 0.0015 300.00 0.45

Sub - Total for F 179.02


Direct Unit Cost (E + F) 193.52 G.
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 17.42 H.
Contractor's Profit (CP) 8% of G 15.48 I.
Value Added Tax (VAT) 5% of (G + H + I) 11.32 J.

461-5
Total Unit Cost (G + H + I + J) 237.74 K.

187+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.2 PCC Pavement (Plain) - Conventional Method, 200mm thk.
Unit of Measurement : sq.m.
Output per hour : 80.50

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00


b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 12,033.49


Total (A + B) 12,771.27
Output per hour = 80.500 sq.m.
Direct Unit Cost (C ÷ D) 158.65
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.39 36.00 14.04


b. Curing Compound L 0.29 75.00 21.75
c. Asphalt Sealant L 0.12 50.00 6.00
d. Steel Forms (Rental) m 0.46 56.00 25.76
e. Sand cu.m. 0.11 500.00 55.00
f. Gravel cu.m. 0.20 600.00 120.00
g. Cement bag 1.90 240.00 456.00
h. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 1 1/2" dia. m 0.0086 97.00 0.83
j. Grease/Tar L 0.0056 210.00 1.18

Sub - Total for F 701.76


Direct Unit Cost (E + F) 860.41
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 77.44
Contractor's Profit (CP) 8% of G 68.83
Value Added Tax (VAT) 5% of (G + H + I) 50.33

461-5
Total Unit Cost (G + H + I + J) 1,057.01

189+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.2.1 PCC Pavement (Plain) - Conventional Method, 200mm thk.
Unit of Measurement : sq.m.
Output per hour : 80.50

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 818.99


Total (A + B) 1,556.77
Output per hour = 80.5 sq.m.
Direct Unit Cost (C ÷ D) 19.34
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.39 40.00 15.60


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.2 850.00 170.00
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0086 34.33 0.30
h. Grease/Tar L 0.0056 300.00 1.68

Sub - Total for F 225.18


Direct Unit Cost (E + F) 244.51
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 22.01
Contractor's Profit (CP) 8% of G 19.56
Value Added Tax (VAT) 5% of (G + H + I) 14.30

461-5
Total Unit Cost (G + H + I + J) 300.39

191+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.3 PCC Pavement (Plain) - Conventional Method, 230mm thk.
Unit of Measurement : sq.m.
Output per hour : 70.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00


b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 12,033.49


Total (A + B) 12,771.27
Output per hour = 70.0000 sq.m.
Direct Unit Cost (C ÷ D) 182.45
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.43 40.00 17.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.1265 850.00 107.53
f. Gravel cu.m. 0.23 650.00 149.50
g. Cement bag 2.19 220.00 481.80
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. m 0.0071 97.00 0.69
j. Grease/Tar L 0.0087 300.00 2.61

Sub - Total for F 796.92


Direct Unit Cost (E + F) 979.37
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 88.14
Contractor's Profit (CP) 8% of G 78.35
Value Added Tax (VAT) 5% of (G + H + I) 57.29

461-5
Total Unit Cost (G + H + I + J) 1,203.16

193+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.3.1 PCC Pavement (Plain) - Conventional Method, 230mm thk.
Unit of Measurement : sq.m.
Output per hour : 70.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 818.99


Total (A + B) 1,556.77
Output per hour = 70 sq.m.
Direct Unit Cost (C ÷ D) 22.24
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.43 40.00 17.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.23 850.00 195.50
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0071 34.33 0.24
h. Grease/Tar L 0.0087 300.00 2.61

Sub - Total for F 253.15


Direct Unit Cost (E + F) 275.39
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 24.79
Contractor's Profit (CP) 8% of G 22.03
Value Added Tax (VAT) 5% of (G + H + I) 16.11

461-5
Total Unit Cost (G + H + I + J) 338.32

195+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.4 PCC Pavement (Plain) - Conventional Method, 250mm thk.
Unit of Measurement : sq.m.
Output per hour : 64.40

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00


b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 12,033.49


Total (A + B) 12,771.27
Output per hour = 64.400 sq.m.
Direct Unit Cost (C ÷ D) 198.31
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.45 40.00 18.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.15 44.00 6.60
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.1375 850.00 116.88
f. Gravel cu.m. 0.25 650.00 162.50
g. Cement bag 2.38 220.00 523.60
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. m 0.0078 97.00 0.76
j. Grease/Tar L 0.0095 300.00 2.85

Sub - Total for F 863.50


Direct Unit Cost (E + F) 1,061.81
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 95.56
Contractor's Profit (CP) 8% of G 84.95
Value Added Tax (VAT) 5% of (G + H + I) 62.12

461-5
Total Unit Cost (G + H + I + J) 1,304.44

197+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.4.1 PCC Pavement (Plain) - Conventional Method, 250mm thk.
Unit of Measurement : sq.m.
Output per hour : 64.40

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 818.99


Total (A + B) 1,556.77
Output per hour = 64.4 sq.m.
Direct Unit Cost (C ÷ D) 24.17
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.45 40.00 18.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.15 44.00 6.60
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.25 850.00 212.50
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
h. Grease/Tar L 0.0095 300.00 2.85

Sub - Total for F 272.54


Direct Unit Cost (E + F) 296.71
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 26.70
Contractor's Profit (CP) 8% of G 23.74
Value Added Tax (VAT) 5% of (G + H + I) 17.36

461-5
Total Unit Cost (G + H + I + J) 364.51

199+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.5 PCC Pavement (Plain) - Conventional Method, 280mm thk.
Unit of Measurement : sq.m.
Output per hour : 57.50

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00


b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 12,033.49


Total (A + B) 12,771.27
Output per hour = 57.500 sq.m.
Direct Unit Cost (C ÷ D) 222.11
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.17 44.00 7.48
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.154 850.00 130.90
f. Gravel cu.m. 0.28 650.00 182.00
g. Cement bag 2.66 220.00 585.20
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. m 0.0078 97.00 0.76
j. Grease/Tar L 0.0078 300.00 2.34

Sub - Total for F 961.00


Direct Unit Cost (E + F) 1,183.11
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 106.48
Contractor's Profit (CP) 8% of G 94.65
Value Added Tax (VAT) 5% of (G + H + I) 69.21

461-5
Total Unit Cost (G + H + I + J) 1,453.45

201+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.5.1 PCC Pavement (Plain) - Conventional Method, 280mm thk.
Unit of Measurement : sq.m.
Output per hour : 57.50

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 818.99


Total (A + B) 1,556.77
Output per hour = 57.5 sq.m.
Direct Unit Cost (C ÷ D) 27.07
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.17 44.00 7.48
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.28 850.00 238.00
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
h. Grease/Tar L 0.0078 300.00 2.34

Sub - Total for F 300.41


Direct Unit Cost (E + F) 327.48
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 29.47
Contractor's Profit (CP) 8% of G 26.20
Value Added Tax (VAT) 5% of (G + H + I) 19.16

461-5
Total Unit Cost (G + H + I + J) 402.31

203+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.6 PCC Pavement (Plain) - Conventional Method, 300mm thk.
Unit of Measurement : sq.m.
Output per hour : 53.67

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00


b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 12,033.49


Total (A + B) 12,771.27
Output per hour = 53.67 sq.m.
Direct Unit Cost (C ÷ D) 237.96
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.165 850.00 140.25
f. Gravel cu.m. 0.30 650.00 195.00
g. Cement bag 2.85 220.00 627.00
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. m 0.0094 97.00 0.91
j. Grease/Tar L 0.0094 300.00 2.82

Sub - Total for F 1,028.22


Direct Unit Cost (E + F) 1,266.18
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 113.96
Contractor's Profit (CP) 8% of G 101.29
Value Added Tax (VAT) 5% of (G + H + I) 74.07

461-5
Total Unit Cost (G + H + I + J) 1,555.50

205+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.6.1 PCC Pavement (Plain) - Conventional Method, 300mm thk.
Unit of Measurement : sq.m.
Output per hour : 53.67

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 818.99


Total (A + B) 1,556.77
Output per hour = 53.67 sq.m.
Direct Unit Cost (C ÷ D) 29.01

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.3 850.00 255.00
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0094 34.33 0.32
h. Grease/Tar L 0.0094 300.00 2.82

Sub - Total for F 320.38


Direct Unit Cost (E + F) 349.39
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 31.45
Contractor's Profit (CP) 8% of G 27.95
Value Added Tax (VAT) 5% of (G + H + I) 20.44

461-5
Total Unit Cost (G + H + I + J) 429.22

207+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.1 PCC Pavement (Plain) - Using Concrete Paver, 230mm thk.
Unit of Measurement : sq.m.
Output per hour : 90.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50


b. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
f. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
g. Concrete Vibrator 1 0.10 91.25 9.13
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 18,043.23


Total (A + B) 18,703.07
Output per hour = 90.0000 sq.m.
Direct Unit Cost (C ÷ D) 207.81

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.43 40.00 17.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Sand cu.m. 0.1265 850.00 107.53
e. Gravel cu.m. 0.23 650.00 149.50
f. Cement bag 2.19 220.00 481.80
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. m 0.0071 97.00 0.69
i. Grease/Tar L 0.0087 300.00 2.61

Sub - Total for F 773.92


Direct Unit Cost (E + F) 981.74
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 88.36
Contractor's Profit (CP) 8% of G 78.54
Value Added Tax (VAT) 5% of (G + H + I) 57.43

461-5
Total Unit Cost (G + H + I + J) 1,206.06

209+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.1.1 PCC Pavement (Plain) - Using Concrete Paver, 230mm thk.
Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
d. Concrete Vibrator 1 0.10 91.25 9.13
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 7,341.10


Total (A + B) 8,000.94
Output per hour = 100.0000 sq.m.
Direct Unit Cost (C ÷ D) 80.01

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.43 40.00 17.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Ready Mix Concrete, 3500 psi cu.m. 0.23 850.00 195.50
e. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
f. Pipe Sleeve, 1" dia. m 0.0071 34.33 0.24
g. Grease/Tar L 0.0087 300.00 2.61

Sub - Total for F 230.15


Direct Unit Cost (E + F) 310.16
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 27.91
Contractor's Profit (CP) 8% of G 24.81
Value Added Tax (VAT) 5% of (G + H + I) 18.14

461-5
Total Unit Cost (G + H + I + J) 381.04

211+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.2 PCC Pavement (Plain) - Using Concrete Paver, 250mm thk.
Unit of Measurement : sq.m.
Output per hour : 82.80

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50


b. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
f. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
g. Concrete Vibrator 1 0.10 91.25 9.13
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 18,043.23


Total (A + B) 18,703.07
Output per hour = 82.800 sq.m.
Direct Unit Cost (C ÷ D) 225.88

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.45 40.00 18.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.15 44.00 6.60
d. Sand cu.m. 0.1375 850.00 116.88
e. Gravel cu.m. 0.25 650.00 162.50
f. Cement bag 2.38 220.00 523.60
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. m 0.0078 97.00 0.76
i. Grease/Tar L 0.0095 300.00 2.85

Sub - Total for F 840.50


Direct Unit Cost (E + F) 1,066.38
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 95.97
Contractor's Profit (CP) 8% of G 85.31
Value Added Tax (VAT) 5% of (G + H + I) 62.38

461-5
Total Unit Cost (G + H + I + J) 1,310.05

213+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.2.1 PCC Pavement (Plain) - Using Concrete Paver, 250mm thk.
Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
d. Concrete Vibrator 1 0.10 91.25 9.13
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 7,341.10


Total (A + B) 8,000.94
Output per hour = 100.0000 sq.m.
Direct Unit Cost (C ÷ D) 80.01

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.45 40.00 18.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.15 44.00 6.60
d. Ready Mix Concrete, 3500 psi cu.m. 0.25 850.00 212.50
e. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
f. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
g. Grease/Tar L 0.0095 300.00 2.85

Sub - Total for F 249.54


Direct Unit Cost (E + F) 329.55
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 29.66
Contractor's Profit (CP) 8% of G 26.36
Value Added Tax (VAT) 5% of (G + H + I) 19.28

461-5
Total Unit Cost (G + H + I + J) 404.85

215+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.3 PCC Pavement (Plain) - Using Concrete Paver, 280mm thk.
Unit of Measurement : sq.m.
Output per hour : 73.93

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50


b. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
f. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
g. Concrete Vibrator 1 0.10 91.25 9.13
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 18,043.23


Total (A + B) 18,703.07
Output per hour = 73.93 sq.m.
Direct Unit Cost (C ÷ D) 252.98
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.17 44.00 7.48
d. Sand cu.m. 0.154 850.00 130.90
e. Gravel cu.m. 0.28 650.00 182.00
f. Cement bag 2.66 220.00 585.20
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. m 0.0078 97.00 0.76
i. Grease/Tar L 0.0078 300.00 2.34

Sub - Total for F 938.00


Direct Unit Cost (E + F) 1,190.98
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 107.19
Contractor's Profit (CP) 8% of G 95.28
Value Added Tax (VAT) 5% of (G + H + I) 69.67

461-5
Total Unit Cost (G + H + I + J) 1,463.12

217+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.3.1 PCC Pavement (Plain) - Using Concrete Paver, 280mm thk.
Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
d. Concrete Vibrator 1 0.10 91.25 9.13
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 7,341.10


Total (A + B) 8,000.94
Output per hour = 100.0000 sq.m.
Direct Unit Cost (C ÷ D) 80.01
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.17 44.00 7.48
d. Ready Mix Concrete, 3500 psi cu.m. 0.28 850.00 238.00
e. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
f. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
g. Grease/Tar L 0.0078 300.00 2.34

Sub - Total for F 277.41


Direct Unit Cost (E + F) 357.42
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 32.17
Contractor's Profit (CP) 8% of G 28.59
Value Added Tax (VAT) 5% of (G + H + I) 20.91

461-5
Total Unit Cost (G + H + I + J) 439.09

219+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.4 PCC Pavement (Plain) - Using Concrete Paver, 300mm thk.
Unit of Measurement : sq.m.
Output per hour : 69.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50


b. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
f. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
g. Concrete Vibrator 1 0.10 91.25 9.13
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 18,043.23


Total (A + B) 18,703.07
Output per hour = 69.0000 sq.m.
Direct Unit Cost (C ÷ D) 271.06
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Sand cu.m. 0.165 850.00 140.25
e. Gravel cu.m. 0.30 650.00 195.00
f. Cement bag 2.85 220.00 627.00
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. m 0.0094 97.00 0.91
i. Grease/Tar L 0.0094 300.00 2.82

Sub - Total for F 1,005.22


Direct Unit Cost (E + F) 1,276.28
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 114.87
Contractor's Profit (CP) 8% of G 102.10
Value Added Tax (VAT) 5% of (G + H + I) 74.66

461-5
Total Unit Cost (G + H + I + J) 1,567.91

221+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.4.1 PCC Pavement (Plain) - Using Concrete Paver, 300mm thk.
Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
d. Concrete Vibrator 1 0.10 91.25 9.13
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 7,341.10


Total (A + B) 8,000.94
Output per hour = 100.0000 sq.m.
Direct Unit Cost (C ÷ D) 80.01
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Ready Mix Concrete, 3500 psi cu.m. 0.3 850.00 255.00
e. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
f. Pipe Sleeve, 1" dia. m 0.94 34.33 32.27
g. Grease/Tar L 0.94 300.00 282.00

Sub - Total for F 608.51


Direct Unit Cost (E + F) 688.52
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 61.97
Contractor's Profit (CP) 8% of G 55.08
Value Added Tax (VAT) 5% of (G + H + I) 40.28

461-5
Total Unit Cost (G + H + I + J) 845.85

223+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)c PCC Pavement (Plain) - Conventional Method, 150mm thk.
Unit of Measurement : sq.m.
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 8 1.00 50.18 401.44
c. Unskilled Labor 16 1.00 38.97 623.52

Sub - Total for A 1,094.38

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


b. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
c. Concrete Vibrator 2 1.00 91.25 182.50
d. Bar Cutter, Single Phase 1 0.05 219.75 10.99
e. Concrete Saw (7.5 Hp), 14" Blade Ø 1 0.10 32.63 3.26
Minor Tools (5% of Labor Cost ) 54.72

Sub - Total for B 545.97


Total (A + B) 1,640.35
Output per hour = 12.0000 sq.m.
Direct Unit Cost (C ÷ D) 136.70
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.33 40.00 13.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.0825 850.00 70.13
f. Gravel cu.m. 0.15 650.00 97.50
g. Cement bag 1.43 220.00 314.60
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
j. Grease/Tar L 0.0015 300.00 0.45

Sub - Total for F 533.74


Direct Unit Cost (E + F) 670.44
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 60.34
Contractor's Profit (CP) 8% of G 53.64
Value Added Tax (VAT) 5% of (G + H + I) 39.22

461-5
Total Unit Cost (G + H + I + J) 823.63

225+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)c.1 PCC Pavement (Plain) - Conventional Method, 150mm thk.
Unit of Measurement : sq.m.
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 8 1.00 50.18 401.44
c. Unskilled Labor 16 1.00 38.97 623.52

Sub - Total for A 1,094.38

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Saw (7.5 Hp), 14" Blade Ø 1 0.05 32.63 1.63
c. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 54.72

Sub - Total for B 260.83


Total (A + B) 1,355.21
Output per hour = 12 sq.m.
Direct Unit Cost (C ÷ D) 112.93
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 0.33 40.00 13.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.15 850.00 127.50
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
h. Grease/Tar L 0.0015 300.00 0.45

Sub - Total for F 179.02


Direct Unit Cost (E + F) 291.95
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 26.28
Contractor's Profit (CP) 8% of G 23.36
Value Added Tax (VAT) 5% of (G + H + I) 17.08

461-5
Total Unit Cost (G + H + I + J) 358.66

227+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(2) PCC Pavement (Reinforced), 300mm thk.


Unit of Measurement : sq.m.
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Batching Plant (30 cu.m.) 1 0.10 1,759.50 175.95


b. Concrete Screeder (5.5 Hp) 1 0.10 545.00 54.50
c. Transit Mixer (5 cu.m.) 2 0.10 1,318.00 263.60
d. Payloader (1.50 cu.m.), LX80-2C 1 0.10 1,733.00 173.30
e. Water Truck/Pump (16000L) 1 0.10 2,450.00 245.00
f. Concrete Vibrator 1 0.10 91.25 9.13
g. Bar Cutter, Single Phase 1 0.25 219.75 54.94
h. Bar Bender 1 0.25 351.50 87.88
Minor Tools (5% of Labor) 36.89

Sub - Total for B 1,101.18


Total (A + B) 1,838.96
Output per hour = 6.0000 sq.m.
Direct Unit Cost (C ÷ D) 306.49
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 54.21 40.00 2,168.40


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.1650 850.00 140.25
f. Gravel cu.m. 0.30 650.00 195.00
g. Cement bag 2.85 220.00 627.00
h. # 16 GI Tie Wire (2% of RSB) kg. 1.084 47.00 50.95

Sub - Total for F 3,220.64


Direct Unit Cost (E + F) 3,527.13
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 317.44
Contractor's Profit (CP) 8% of G 282.17
Value Added Tax (VAT) 5% of (G + H + I) 206.34

461-5
Total Unit Cost (G + H + I + J) 4,333.08

229+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(2)1 PCC Pavement (Reinforced), 300mm thk.


Unit of Measurement : sq.m.
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Concrete Vibrator 1 0.10 91.25 9.13


b. Concrete Saw (7.5 Hp), 14" Blade Ø 1 0.10 32.63 3.26
c. Bar Cutter, Single Phase 1 0.25 219.75 54.94
d. Bar Bender 1 0.25 351.50 87.88
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 192.09


Total (A + B) 929.87
Output per hour = 6 sq.m.
Direct Unit Cost (C ÷ D) 154.98
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reinforcing Steel Bar kg. 54.21 40.00 2,168.40


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.30 850.00 255.00
f. # 16 GI Tie Wire (2% of RSB) kg. 1.084 47.00 50.95

Sub - Total for F 2,513.39


Direct Unit Cost (E + F) 2,668.37
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 240.15
Contractor's Profit (CP) 8% of G 213.47
Value Added Tax (VAT) 5% of (G + H + I) 156.10

461-5
Total Unit Cost (G + H + I + J) 3,278.09

231+32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 404 Reinforcing Steel Bar, Grade 40 (Minor Structures)


Unit of Measurement : kg.
Output per hour : 180.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 481.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
c. Cargo Truck (9 - 10 mt) 1 0.15 1,212.00 181.80

Sub - Total for B 467.43


C. Total (A + B) 948.97
D. Output per hour = 180.00000 kg.
E. Direct Unit Cost (C ÷ D) 5.27
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Tie Wire (2% of RSB) kg. 0.021 47.00 0.99


b. Reinforcing Steel Bar, Grade 40 kg. 1.05 40.00 42.00
(w/ 5% Wastage)

Sub - Total for F 42.99


G. Direct Unit Cost (E + F) 48.26
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4.34
I. Contractor's Profit (CP) 8% of G 3.86
J. Value Added Tax (VAT) 5% of (G + H + I) 2.82
K. Total Unit Cost (G + H + I + J) 59.29
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 405 Structural Concrete Class A (Minor Structures)


Unit of Measurement : cu.m.
Output per hour : 1.40

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76

Installation/Removal of Formworks
b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
Sub - Total for A 1,094.38

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


b. Concrete Vibrator 1 1.00 91.25 91.25
c. Water Truck/Pump (16000L) 1 0.10 2,450.00 245.00
Minor Tools (5% of Labor) 54.72

Sub - Total for B 562.97


C. Total (A + B) 1,657.35
D. Output per hour = 1.4000 cu.m.
E. Direct Unit Cost (C ÷ D) 1,183.82
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Lumber, Good - 4 uses bd.ft. * 70.0000 40.00 700.00


b. Marine Plywood (1/2" x 4' x 8') - 4 uses pc. * 1.600 700.00 280.00
c. Assorted CWN (1kg./100 bd.ft. of Lumber) kg. * 0.700 68.00 47.60
d. Cement bag 9.50 220.00 2,090.00
e. Sand cu.m. 0.50 850.00 425.00
f. Gravel cu.m. 1.00 650.00 650.00

Note:
*Quantities for lumber, plywood and CWN are
dependent on the type of minor structure.
The above-computed quantities are based on box
culvert.

Sub - Total for F 4,192.60


G. Direct Unit Cost (E + F) 5,376.42
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 483.88
I. Contractor's Profit (CP) 8% of G 430.11
J. Value Added Tax (VAT) 5% of (G + H + I) 314.52
K. Total Unit Cost (G + H + I + J) 6,604.93
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)a Pipe Culverts, 610mm dia. (24" Ø)


Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.44 69.42 30.54


b. Skilled Labor 2 0.44 50.18 44.16
c. Unskilled Labor 4 0.44 38.97 68.59

Sub - Total for A 143.29

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.22 1,537.00 338.14


b. Plate Compactor (5 Hp) 1 0.22 123.00 27.06
Minor Tools (10 % of Labor Cost) 14.33

Sub - Total for B 379.53


C. Total (A + B) 522.82
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 522.82
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 0.774 240.00 185.76


b. Sand cu.m. 0.044 500.00 22.00
c. R.C. Pipes (610mm dia.) pc. 1.00 1,000.00 1,000.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.088 500.00 44.00

Sub - Total for F 1,251.76


G. Direct Unit Cost (E + F) 1,774.58
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 159.71
I. Contractor's Profit (CP) 8% of G 141.97
J. Value Added Tax (VAT) 5% of (G + H + I) 103.81
K. Total Unit Cost (G + H + I + J) 2,180.07
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)b Pipe Culverts, 760mm dia. (30" Ø)


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.50 69.42 34.71


b. Skilled Labor 2 0.50 50.18 50.18
c. Unskilled Labor 4 0.50 38.97 77.94

Sub - Total for A 162.83

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.25 1,537.00 384.25


b. Plate Compactor (5 Hp) 1 0.25 123.00 30.75
Minor Tools (10 % of Labor Cost) 16.28

Sub - Total for B 431.28


C. Total (A + B) 594.11
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 594.11

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 0.918 220.00 201.96


b. Sand cu.m. 0.052 850.00 44.20
c. R.C. Pipes (760mm dia.) pc. 1.00 1,750.00 1,750.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.108 850.00 91.80

Sub - Total for F 2,087.96


G. Direct Unit Cost (E + F) 2,682.07
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 241.39
I. Contractor's Profit (CP) 8% of G 214.57
J. Value Added Tax (VAT) 5% of (G + H + I) 156.90
K. Total Unit Cost (G + H + I + J) 3,294.93
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)c Pipe Culverts, 910mm dia. (36" Ø)


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.57 69.42 39.57


b. Skilled Labor 2 0.57 50.18 57.21
c. Unskilled Labor 4 0.57 38.97 88.85

Sub - Total for A 185.63

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.29 1,537.00 445.73


b. Plate Compactor (5 Hp) 1 0.29 123.00 35.67
Minor Tools (10 % of Labor Cost) 18.56

Sub - Total for B 499.96


C. Total (A + B) 685.59
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 685.59

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 1.080 220.00 237.60


b. Sand cu.m. 0.061 850.00 51.85
c. R.C. Pipes (910mm dia.) pc. 1.00 2,170.00 2,170.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.128 850.00 108.80

Sub - Total for F 2,568.25


G. Direct Unit Cost (E + F) 3,253.84
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 292.85
I. Contractor's Profit (CP) 8% of G 260.31
J. Value Added Tax (VAT) 5% of (G + H + I) 190.35
K. Total Unit Cost (G + H + I + J) 3,997.34
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)d Pipe Culverts, 1070mm dia. (42" Ø)


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.67 69.42 46.51


b. Skilled Labor 2 0.67 50.18 67.24
c. Unskilled Labor 4 0.67 38.97 104.44

Sub - Total for A 218.19

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.33 1,537.00 507.21


b. Plate Compactor (5 Hp) 1 0.33 123.00 40.59
Minor Tools (10 % of Labor Cost) 21.82

Sub - Total for B 569.62


C. Total (A + B) 787.81
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 787.81

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 1.242 220.00 273.24


b. Sand cu.m. 0.070 850.00 59.50
c. R.C. Pipes (1070mm dia.) pc. 1.00 2,900.00 2,900.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.149 850.00 126.65

Sub - Total for F 3,359.39


G. Direct Unit Cost (E + F) 4,147.20
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 373.25
I. Contractor's Profit (CP) 8% of G 331.78
J. Value Added Tax (VAT) 5% of (G + H + I) 242.61
K. Total Unit Cost (G + H + I + J) 5,094.84
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)e Pipe Culverts, 1220mm dia. (48" Ø)


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.80 69.42 55.54


b. Skilled Labor 2 0.80 50.18 80.29
c. Unskilled Labor 4 0.80 38.97 124.70

Sub - Total for A 260.53

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.40 1,537.00 614.80


b. Plate Compactor (5 Hp) 1 0.40 123.00 49.20
Minor Tools (10 % of Labor Cost) 26.05

Sub - Total for B 690.05


C. Total (A + B) 950.58
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 950.58

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 1.404 220.00 308.88


b. Sand cu.m. 0.080 850.00 68.00
c. R.C. Pipes (1220mm dia.) pc. 1.00 3,800.00 3,800.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.170 850.00 144.50

Sub - Total for F 4,321.38


G. Direct Unit Cost (E + F) 5,271.96
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 474.48
I. Contractor's Profit (CP) 8% of G 421.76
J. Value Added Tax (VAT) 5% of (G + H + I) 308.41
K. Total Unit Cost (G + H + I + J) 6,476.60
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)f Pipe Culverts, 1520mm dia. (60" Ø)


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
Minor Tools (10 % of Labor Cost) 32.57

Sub - Total for B 862.57


C. Total (A + B) 1,188.23
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 1,188.23

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 1.710 220.00 376.20


b. Sand cu.m. 0.097 850.00 82.45
c. R.C. Pipes (1520mm dia.) pc. 1.00 6,175.00 6,175.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.210 850.00 178.50

Sub - Total for F 6,812.15


G. Direct Unit Cost (E + F) 8,000.38
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 720.03
I. Contractor's Profit (CP) 8% of G 640.03
J. Value Added Tax (VAT) 5% of (G + H + I) 468.02
K. Total Unit Cost (G + H + I + J) 9,828.46
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(1) Underdrain


Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.80 69.42 55.54


b. Unskilled Labor 4 0.80 38.97 124.70

Sub - Total for A 180.24

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Plate Compactor (5 Hp) 1 0.40 123.00 49.20


Minor Tools (10% of Labor Cost) 18.02

Sub - Total for B 67.22


C. Total (A + B) 247.46
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 247.46

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Coarse Aggregates cu.m. 0.20 900.00 180.00


b. Fine Aggregates cu.m. 0.39 850.00 331.50
c. Filter Cloth sq.m. 2.00 275.00 550.00
d. 150 mm. dia. Concrete Perforated Pipe pc. 1.05 230.00 241.50

Sub - Total for F 1,303.00


G. Direct Unit Cost (E + F) 1,550.46
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 139.54
I. Contractor's Profit (CP) 8% of G 124.04
J. Value Added Tax (VAT) 5% of (G + H + I) 90.70
K. Total Unit Cost (G + H + I + J) 1,904.75
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(2) Blind Drain


Unit of Measurement : m
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 225.30

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Minor Tools (10% of Labor) 22.53

Sub - Total for B 22.53


C. Total (A + B) 247.83
D. Output per hour = 1.25 m.
E. Direct Unit Cost (C ÷ D) 198.26

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Coarse Aggregates cu.m. 0.22 900.00 198.00


b. Fine Aggregates cu.m. 0.39 850.00 331.50
c. Filter Cloth sq.m. 2.00 275.00 550.00

Sub - Total for F 1,079.50


G. Direct Unit Cost (E + F) 1,277.76
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 115.00
I. Contractor's Profit (CP) 8% of G 102.22
J. Value Added Tax (VAT) 5% of (G + H + I) 74.75
K. Total Unit Cost (G + H + I + J) 1,569.73
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(3) Granular Backfill filter material for Underdrains


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 225.30

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Plate Compactor (5 Hp) 1 1.00 123.00 123.00


Minor Tools (10% of Labor) 22.53

Sub - Total for B 145.53


C. Total (A + B) 370.83
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 296.66

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Coarse Aggregates (Granular Backfill Materials) cu.m. 1.15 900.00 1,035.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 1,035.00


G. Direct Unit Cost (E + F) 1,331.66
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 119.85
I. Contractor's Profit (CP) 8% of G 106.53
J. Value Added Tax (VAT) 5% of (G + H + I) 77.90
K. Total Unit Cost (G + H + I + J) 1,635.95
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502 Manhole/Catch Basin/Inlet


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
Item No. Description
502(1)a Manhole (610mm dia RCPC)
502(1)b Manhole (760mm dia RCPC)
502(1)c Manhole (910mm dia RCPC)
502(1)d Manhole (1070mm dia RCPC)
502(1)e Manhole (1220mm dia RCPC)
502(2)a Inlet, Type I
502(2)b Inlet, Type I-A
502(3)a.1 Catch Basin (Single Barrel 610 mm dia RCPC)
502(3)a.2 Catch Basin (Single Barrel 760 mm dia RCPC)
502(3)a.3 Catch Basin (Single Barrel 910 mm dia RCPC)
502(3)a.4 SubCatch
- Total for(Single
Basin A Barrel 1070mm dia RCPC)
502(3)a.5 Catch Basin (Single Barrel 1220mm dia RCPC)
NameCatch
502(3)b.1 and Basin
Capacity
(Double Barrel 610 mm diaNo of Units
RCPC) No. of Hours Hourly Rate Amount
502(3)b.2 Catch Basin (Double Barrel 910 mm dia RCPC)
B. Equipment
502(3)b.3 Catch Basin (DoubleBarrel 1220 mm dia RCPC)
502(7) Adjusting Manhole, Type I-A
502(8) Adjusting Inlet, Type I and Type I-A
502(9)a Adjusting Catch Basin (Single Barrel, 610mm dia.)
502(9)b Adjusting Catch Basin (Double Barrel, 610mm dia.)

These pay items are variable in dimensions based on the actual consdition which combines component items , hence
standard estimate should be based on the standard Detailed unit Analysis (DUPA).
Further, these items with unit of measure as "each" in the Blue Book is recommended to be broken down seperately by
component items such as Items 103(3) - Foundation Fill, 404 - Reinforcing Steel Bar and 405 - Structural Concrete Class A
(Minor Structures) in the Summarry of quantities in the preparation of design plans

Sub - Total for B


C. Total (A + B)
D. Output = 1.0000 ea.
E. Direct Unit Cost (C ÷ D)
Direct Unit
Name and Specification Unit Quantity Direct Cost
Cost
F. Materials/Processed Component Pay Item

a. 103(3) - Foundation Fill cu.m.


b. 404 - Reinforcing Steel Bar kg.
c. 405 - Structural Concrete cu.m.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(4) Concrete Covers


Unit of Measurement : ea.
Output : 5.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 0.50 172.00 86.00


b. Bar Cutter 1 0.50 219.75 109.88
c. Concrete Vibrator 1 0.50 148.88 74.44
c. Welding Machine (300 A, Gas/Diesel Driven 1 0.25 371.00 92.75
c. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
Minor Tools (10% of Labor Cost) 32.57

Sub - Total for B 518.13


C. Total (A + B) 843.79
D. Output = 5.0000 ea.
E. Direct Unit Cost (C ÷ D) 168.76
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Dimension: 1.29m x 0.57m x 0.20m w/ Flat Bar Frame


a. Portland Cement bag 1.43 220.00 314.60
b. Sand cu.m. 0.075 850.00 63.75
c. Gravel cu.m. 0.15 650.00 97.50
d. Reinforcing Steel Bar kg. 46.46 40.00 1,858.40
e. #16 GI Tie Wire (2% of RSB) kg. 0.93 47.00 43.71
f. 6mm thk. Steel Plate kg. 73.58 48.00 3,531.84
g. 16mm thk. Steel Plate kg. 2.97 48.00 71.28
h. 1/2" Ordinary Plywood - 2 uses pc. 0.33 620.00 102.30
i. 16mm dia. U-bolt & Knot set 2.00 250.00 250.00
j. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.04 90.00 1.80

Sub - Total for F 6,335.18


G. Direct Unit Cost (E + F) 6,503.94
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 585.35
I. Contractor's Profit (CP) 8% of G 520.32
J. Value Added Tax (VAT) 5% of (G + H + I) 380.48
K. Total Unit Cost (G + H + I + J) 7,990.09
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(5) Metal Frames and Gratings


Unit of Measurement : pair
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.50 69.42 34.71


b. Skilled Labor 1 0.50 50.18 25.09
c. Unskilled Labor 1 0.50 38.97 19.49

Sub - Total for A 79.29

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Minor Tools (10% of Labor Cost) 7.93

Sub - Total for B 7.93


C. Total (A + B) 87.21
D. Output = 1.0000 pair
E. Direct Unit Cost (C ÷ D) 87.21
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. 410mmx660mmx60mm, C.I. Cover with Frame set 1.00 4,700.00 4,700.00

Sub - Total for F 4,700.00


G. Direct Unit Cost (E + F) 4,787.21
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 430.85
I. Contractor's Profit (CP) 8% of G 382.98
J. Value Added Tax (VAT) 5% of (G + H + I) 280.05
K. Total Unit Cost (G + H + I + J) 5,881.09
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(6) Metal Frames and Covers (Circular)


Unit of Measurement : pair
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.50 69.42 34.71


b. Skilled Labor 1 0.50 50.18 25.09
c. Unskilled Labor 1 0.50 38.97 19.49

Sub - Total for A 79.29

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Minor Tools (10% of Labor Cost) 7.93

Sub - Total for B 7.93


C. Total (A + B) 87.21
D. Output = 1.0000 pair
E. Direct Unit Cost (C ÷ D) 87.21
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. 580mm dia. C.I. Manhole Cover with Frame set 1.00 5,700.00 5,700.00

Sub - Total for F 5,700.00


G. Direct Unit Cost (E + F) 5,787.21
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 520.85
I. Contractor's Profit (CP) 8% of G 462.98
J. Value Added Tax (VAT) 5% of (G + H + I) 338.55
K. Total Unit Cost (G + H + I + J) 7,109.59
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 503(a) Drainage Steel Grating with Frame (675mm x 975mm Sump Grating)
Unit of Measurement : set
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 4.00 69.42 277.68


b. Skilled Labor 1 4.00 50.18 200.72
c. Unskilled Labor 1 4.00 38.97 155.88

Sub - Total for A 634.28

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Bar Cutter 1 2.00 219.75 439.50


b. Welding Machine (300 A, Gas/Diesel Driven 1 4.00 371.00 1,484.00

Sub - Total for B 1,923.50


C. Total (A + B) 2,557.78
D. Output per hour = 1.0000 set
E. Direct Unit Cost (C ÷ D) 2,557.78
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. 65mm x 5mm Flat Bar kg. 62.557 48.00 3,002.74


b. 6mm dia. x 975mm Twisted Cross Rod kg. 1.244 48.00 59.71
c. 75mm x 75mm x 9mm Angle Bar kg. 38.36 48.00 1,841.28
d. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.051 90.00 4.59

Sub - Total for F 4,908.32


G. Direct Unit Cost (E + F) 7,466.10
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 671.95
I. Contractor's Profit (CP) 8% of G 597.29
J. Value Added Tax (VAT) 5% of (G + H + I) 436.77
K. Total Unit Cost (G + H + I + J) 9,172.10
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 503(b) Drainage Steel Grating with Frame (715mm x 2000mm Trench Grating)
Unit of Measurement : set
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 8.00 69.42 555.36


b. Skilled Labor 1 8.00 50.18 401.44
c. Unskilled Labor 1 8.00 38.97 311.76

Sub - Total for A 1,268.56

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Bar Cutter 1 4.00 219.75 879.00


b. Welding Machine (300 A, Gas/Diesel Driven 1 8.00 371.00 2,968.00

Sub - Total for B 3,847.00


C. Total (A + B) 5,115.56
D. Output per hour = 1.0000 set
E. Direct Unit Cost (C ÷ D) 5,115.56
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. 65mm x 5mm Flat Bar kg. 127.066 48.00 6,099.17


b. 6mm dia. x 975mm Twisted Cross Rod kg. 3.174 48.00 152.35
c. 75mm x 75mm x 9mm Angle Bar kg. 41.64 48.00 1,998.72
d. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.086 90.00 7.74

Sub - Total for F 8,257.98


G. Direct Unit Cost (E + F) 13,373.54
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1,203.62
I. Contractor's Profit (CP) 8% of G 1,069.88
J. Value Added Tax (VAT) 5% of (G + H + I) 782.35
K. Total Unit Cost (G + H + I + J) 16,429.39
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)a Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (24" dia) - 610mm
Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.33 69.42 22.91


b. Skilled Labor 2 0.33 50.18 33.12
c. Unskilled Labor 4 0.33 38.97 51.44

Sub - Total for A 107.47

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.17 1,537.00 261.29


b. Boom Truck (2 - 5 mt) 1 0.17 1,017.90 173.04
c. Water Truck/Pump (16000L) 1 0.08 2,450.00 196.00
Minor Tools (10% of Labor Cost) 10.75

Sub - Total for B 641.08


C. Total (A + B) 748.55
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 748.55
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 748.55
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 67.37
I. Contractor's Profit (CP) 8% of G 59.88
J. Value Added Tax (VAT) 5% of (G + H + I) 43.79
K. Total Unit Cost (G + H + I + J) 919.59
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)b Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" dia.) - 760mm
Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.40 69.42 27.77


b. Skilled Labor 2 0.40 50.18 40.14
c. Unskilled Labor 4 0.40 38.97 62.35

Sub - Total for A 130.26

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.20 1,537.00 307.40


b. Boom Truck (2 - 5 mt) 1 0.20 1,017.90 203.58
c. Water Truck/Pump (16000L) 1 0.10 2,450.00 245.00
Minor Tools (10% of Labor) 13.03

Sub - Total for B 769.01


C. Total (A + B) 899.27
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 899.27
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 899.27
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 80.93
I. Contractor's Profit (CP) 8% of G 71.94
J. Value Added Tax (VAT) 5% of (G + H + I) 52.61
K. Total Unit Cost (G + H + I + J) 1,104.75
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)c Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" dia.) - 910mm
Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.50 69.42 34.71


b. Skilled Labor 2 0.50 50.18 50.18
c. Unskilled Labor 4 0.50 38.97 77.94

Sub - Total for A 162.83

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.25 1,537.00 384.25


b. Boom Truck (2 - 5 mt) 1 0.25 1,017.90 254.48
c. Water Truck/Pump (16000L) 1 0.13 2,450.00 318.50
Minor Tools (10% of Labor) 16.28

Sub - Total for B 973.51


C. Total (A + B) 1,136.34
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 1,136.34
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 1,136.34
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 102.27
I. Contractor's Profit (CP) 8% of G 90.91
J. Value Added Tax (VAT) 5% of (G + H + I) 66.48
K. Total Unit Cost (G + H + I + J) 1,395.99
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)d Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" dia.) - 1070mm
Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.50 69.42 34.71


b. Skilled Labor 2 0.50 50.18 50.18
c. Unskilled Labor 4 0.50 38.97 77.94

Sub - Total for A 162.83

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.25 1,537.00 384.25


b. Boom Truck (2 - 5 mt) 1 0.25 1,017.90 254.48
c. Water Truck/Pump (16000L) 1 0.13 2,450.00 318.50
Minor Tools (10% of Labor) 16.28

Sub - Total for B 973.51


C. Total (A + B) 1,136.34
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 1,136.34
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 1,136.34
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 102.27
I. Contractor's Profit (CP) 8% of G 90.91
J. Value Added Tax (VAT) 5% of (G + H + I) 66.48
K. Total Unit Cost (G + H + I + J) 1,395.99
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)e Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" dia.) - 1220mm
Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.67 69.42 46.51


b. Skilled Labor 2 0.67 50.18 67.24
c. Unskilled Labor 4 0.67 38.97 104.44

Sub - Total for A 218.19

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.33 1,537.00 507.21


b. Boom Truck (2 - 5 mt) 1 0.33 1,017.90 335.91
c. Water Truck/Pump (16000L) 1 0.17 2,450.00 416.50
Minor Tools (10% of Labor) 21.82

Sub - Total for B 1,281.44


C. Total (A + B) 1,499.63
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 1,499.63
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 1,499.63
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 134.97
I. Contractor's Profit (CP) 8% of G 119.97
J. Value Added Tax (VAT) 5% of (G + H + I) 87.73
K. Total Unit Cost (G + H + I + J) 1,842.29
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)a Removing, Cleaning and Re-laying Salvaged Culvert Pipe (24" dia.) - 610mm
Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.67 69.42 46.51


b. Skilled Labor 2 0.67 50.18 67.24
c. Unskilled Labor 4 0.67 38.97 104.44

Sub - Total for A 218.19

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.40 1,537.00 614.80


b. Plate Compactor (5 Hp) 1 0.33 123.00 40.59
c. Water Truck/Pump (16000L) 1 0.10 2,450.00 245.00
Minor Tools (10 % of Labor) 21.82

Sub - Total for B 922.21


C. Total (A + B) 1,140.40
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 1,140.40
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 0.774 220.00 170.28


b. Sand cu.m. 0.044 850.00 37.40
c. Sand Bedding cu.m. 0.088 850.00 74.80

Sub - Total for F 282.48


G. Direct Unit Cost (E + F) 1,422.88
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 128.06
I. Contractor's Profit (CP) 8% of G 113.83
J. Value Added Tax (VAT) 5% of (G + H + I) 83.24
K. Total Unit Cost (G + H + I + J) 1,748.01
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)b Removing, Cleaning and Re-laying Salvaged Culvert Pipe (30" dia.) - 760mm
Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.80 69.42 55.54


b. Skilled Labor 2 0.80 50.18 80.29
c. Unskilled Labor 4 0.80 38.97 124.70

Sub - Total for A 260.53

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.48 1,537.00 737.76


b. Plate Compactor (5 Hp) 1 0.40 123.00 49.20
c. Water Truck/Pump (16000L) 1 0.12 2,450.00 294.00
Minor Tools (10 % of Labor) 26.05

Sub - Total for B 1,107.01


C. Total (A + B) 1,367.54
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 1,367.54
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 0.918 220.00 201.96


b. Sand cu.m. 0.052 850.00 44.20
c. Sand Bedding cu.m. 0.108 850.00 91.80

Sub - Total for F 337.96


G. Direct Unit Cost (E + F) 1,705.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 153.50
I. Contractor's Profit (CP) 8% of G 136.44
J. Value Added Tax (VAT) 5% of (G + H + I) 99.77
K. Total Unit Cost (G + H + I + J) 2,095.21
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)c Removing, Cleaning and Re-laying Salvaged Culvert Pipe (36" dia.) - 910mm
Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00 922.20


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
c. Water Truck/Pump (16000L) 1 0.15 2,450.00 367.50
Minor Tools (10 % of Labor) 32.57

Sub - Total for B 1,383.77


C. Total (A + B) 1,709.43
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 1,709.43
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 1.080 220.00 237.60


b. Sand cu.m. 0.061 850.00 51.85
c. Sand Bedding cu.m. 0.128 850.00 108.80

Sub - Total for F 398.25


G. Direct Unit Cost (E + F) 2,107.68
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 189.69
I. Contractor's Profit (CP) 8% of G 168.61
J. Value Added Tax (VAT) 5% of (G + H + I) 123.30
K. Total Unit Cost (G + H + I + J) 2,589.28
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)d Removing, Cleaning and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070mm
Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00 922.20


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
c. Water Truck/Pump (16000L) 1 0.15 2,450.00 367.50
Minor Tools (10 % of Labor) 32.57

Sub - Total for B 1,383.77


C. Total (A + B) 1,709.43
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 1,709.43
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 1.242 220.00 273.24


b. Sand cu.m. 0.070 850.00 59.50
c. Sand Bedding cu.m. 0.149 850.00 126.65

Sub - Total for F 459.39


G. Direct Unit Cost (E + F) 2,168.82
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 195.19
I. Contractor's Profit (CP) 8% of G 173.51
J. Value Added Tax (VAT) 5% of (G + H + I) 126.88
K. Total Unit Cost (G + H + I + J) 2,664.39
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)e Removing, Cleaning and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220mm
Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.33 69.42 92.33


b. Skilled Labor 2 1.33 50.18 133.48
c. Unskilled Labor 4 1.33 38.97 207.32

Sub - Total for A 433.13

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.80 1,537.00 1,229.60


b. Plate Compactor (5 Hp) 1 0.67 123.00 82.41
c. Water Truck/Pump (16000L) 1 0.20 2,450.00 490.00
Minor Tools (10 % of Labor) 43.31

Sub - Total for B 1,845.32


C. Total (A + B) 2,278.45
D. Output per hour = 1.0000 m.
E. Direct Unit Cost (C ÷ D) 2,278.45
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Portland Cement bag 1.404 220.00 308.88


b. Sand cu.m. 0.080 850.00 68.00
c. Sand Bedding cu.m. 0.170 850.00 144.50

Sub - Total for F 521.38


G. Direct Unit Cost (E + F) 2,799.83
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 251.98
I. Contractor's Profit (CP) 8% of G 223.99
J. Value Added Tax (VAT) 5% of (G + H + I) 163.79
K. Total Unit Cost (G + H + I + J) 3,439.59
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)a Cleaning Culvert Pipe in place (610mm dia.) - Half Silted
Unit of Measurement : m
Output per hour : 8.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Cargo Truck (2 - 5 mt) 1 1.00 783.00 783.00


b. Steel Wheel w/ Nylon Rope 1 1.00 300.00 300.00
c. Improvised Bamboo with Bucket 1 1.00 200.00 200.00
Minor Tools (10% of Labor) 32.57

Sub - Total for B 1,315.57


C. Total (A + B) 1,641.23
D. Output per hour = 8.0000 m.
E. Direct Unit Cost (C ÷ D) 205.15
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 205.15
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 18.46
I. Contractor's Profit (CP) 8% of G 16.41
J. Value Added Tax (VAT) 5% of (G + H + I) 12.00
K. Total Unit Cost (G + H + I + J) 252.03
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)b Cleaning Culvert Pipe in place (760mm dia.) - Half Silted
Unit of Measurement : m
Output per hour : 5.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

c. Cargo Truck (9 - 10 mt) 1 1.00 1,212.00 1,212.00


b. Steel Wheel w/ Nylon Rope 1 1.00 300.00 300.00
c. Improvised Bamboo with Bucket 1 1.00 200.00 200.00
Minor Tools (10% of Labor) 32.57

Sub - Total for B 1,744.57


C. Total (A + B) 2,070.23
D. Output per hour = 5.2500 m.
E. Direct Unit Cost (C ÷ D) 394.33
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 394.33
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 35.49
I. Contractor's Profit (CP) 8% of G 31.55
J. Value Added Tax (VAT) 5% of (G + H + I) 23.07
K. Total Unit Cost (G + H + I + J) 484.43
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)c Cleaning Culvert Pipe in place (910mm dia.) - Half Silted
Unit of Measurement : m
Output per hour : 3.75

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

c. Cargo Truck (9 - 10 mt) 1 1.00 1,212.00 1,212.00


Minor Tools (10% of Labor) 32.57

Sub - Total for B 1,244.57


C. Total (A + B) 1,570.23
D. Output per hour = 3.7500 m.
E. Direct Unit Cost (C ÷ D) 418.73
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 418.73
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 37.69
I. Contractor's Profit (CP) 8% of G 33.50
J. Value Added Tax (VAT) 5% of (G + H + I) 24.50
K. Total Unit Cost (G + H + I + J) 514.41
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)d Cleaning Culvert Pipe in place (1070mm dia.) - Half Silted
Unit of Measurement : m
Output per hour : 2.75

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

c. Cargo Truck (9 - 10 mt) 1 1.00 1,212.00 1,212.00


Minor Tools (10% of Labor) 32.57

Sub - Total for B 1,244.57


C. Total (A + B) 1,570.23
D. Output per hour = 2.75 m.
E. Direct Unit Cost (C ÷ D) 570.99

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 570.99
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 51.39
I. Contractor's Profit (CP) 8% of G 45.68
J. Value Added Tax (VAT) 5% of (G + H + I) 33.40
K. Total Unit Cost (G + H + I + J) 701.46
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)e Cleaning Culvert Pipe in place (1220mm dia.) - Half Silted
Unit of Measurement : m
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

c. Cargo Truck (9 - 10 mt) 1 1.00 1,212.00 1,212.00


Minor Tools (10% of Labor) 32.57

Sub - Total for B 1,244.57


C. Total (A + B) 1,570.23
D. Output per hour = 2.0000 m.
E. Direct Unit Cost (C ÷ D) 785.11

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 785.11
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 70.66
I. Contractor's Profit (CP) 8% of G 62.81
J. Value Added Tax (VAT) 5% of (G + H + I) 45.93
K. Total Unit Cost (G + H + I + J) 964.51
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)f Cleaning Culvert Pipe in place (1520mm dia.) - Half Silted
Unit of Measurement : m
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

c. Cargo Truck (9 - 10 mt) 1 1.00 1,212.00 1,212.00


Minor Tools (10% of Labor) 32.57

Sub - Total for B 1,244.57


C. Total (A + B) 1,570.23
D. Output per hour = 1.5000 m.
E. Direct Unit Cost (C ÷ D) 1,046.82

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 1,046.82
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 94.21
I. Contractor's Profit (CP) 8% of G 83.75
J. Value Added Tax (VAT) 5% of (G + H + I) 61.24
K. Total Unit Cost (G + H + I + J) 1,286.02
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(4) Reconditioning Drainage Structures


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 0.50 69.42 34.71


b. Skilled Labor 1 0.50 50.18 25.09
c. Unskilled Labor 2 0.50 38.97 38.97

Sub - Total for A 98.77

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

c. Cargo Truck (9 - 10 mt) 1 0.25 1,212.00 303.00


b. Bamboo with Bucket - 4 uses 1 0.50 200.00 25.00
Minor Tools (10% of Labor) 9.88

Sub - Total for B 337.88


C. Total (A + B) 436.65
D. Output = 1.000 ea.
E. Direct Unit Cost (C ÷ D) 436.65

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

* If some repair is needed, component materials


required and corresponding man-hour will be
added to DUPA

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 436.65
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 39.30
I. Contractor's Profit (CP) 8% of G 34.93
J. Value Added Tax (VAT) 5% of (G + H + I) 25.54
K. Total Unit Cost (G + H + I + J) 536.42
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(1) Riprap (Class A)


Unit of Measurement : cu.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 481.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Minor Tools (5% of Labor Cost) 24.08

Sub - Total for B 24.08


C. Total (A + B) 505.62
D. Output per hour = 1.50 cu.m.
E. Direct Unit Cost (C ÷ D) 337.08

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Boulders (15 - 25 kg.) cu.m. 1.05 920.00 966.00


Miscellaneous (1% of Materials Cost) 9.66

Sub - Total for F 975.66


G. Direct Unit Cost (E + F) 1,312.74
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 118.15
I. Contractor's Profit (CP) 8% of G 105.02
J. Value Added Tax (VAT) 5% of (G + H + I) 76.80
K. Total Unit Cost (G + H + I + J) 1,612.70
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(2) Riprap (Class B)


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) 1 0.50 922.00 461.00


Minor Tools (5% of Labor) 16.28

Sub - Total for B 477.28


C. Total (A + B) 802.94
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 642.35

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Boulders (30 - 70 kg.) cu.m. 1.05 810.00 850.50


Miscellaneous (1% of Materials Cost) 8.51

Sub - Total for F 859.01


G. Direct Unit Cost (E + F) 1,501.36
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 135.12
I. Contractor's Profit (CP) 8% of G 120.11
J. Value Added Tax (VAT) 5% of (G + H + I) 87.83
K. Total Unit Cost (G + H + I + J) 1,844.42
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(3) Riprap (Class C)


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) 1 0.75 922.00 691.50


Minor Tools (5% of Labor Cost) 16.28

Sub - Total for B 707.78


C. Total (A + B) 1,033.44
D. Output per hour = 1.000 cu.m.
E. Direct Unit Cost (C ÷ D) 1,033.44

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Boulders (50 - 100 kg.) cu.m. 1.05 740.00 777.00


Miscellaneous (1% of Materials Cost) 7.77

Sub - Total for F 784.77


G. Direct Unit Cost (E + F) 1,818.21
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 163.64
I. Contractor's Profit (CP) 8% of G 145.46
J. Value Added Tax (VAT) 5% of (G + H + I) 106.37
K. Total Unit Cost (G + H + I + J) 2,233.67
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(4) Riprap (Class D)


Unit of Measurement : cu.m.
Output per hour : 0.75

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) 1 1.00 922.00 922.00


Minor Tools (5% of Labor) 16.28

Sub - Total for B 938.28


C. Total (A + B) 1,263.94
D. Output per hour = 0.75 cu.m.
E. Direct Unit Cost (C ÷ D) 1,685.26

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Boulders (100 - 200 kg.) cu.m. 1.05 650.00 682.50


Miscellaneous (1% of Materials Cost) 6.83

Sub - Total for F 689.33


G. Direct Unit Cost (E + F) 2,374.58
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 213.71
I. Contractor's Profit (CP) 8% of G 189.97
J. Value Added Tax (VAT) 5% of (G + H + I) 138.91
K. Total Unit Cost (G + H + I + J) 2,917.17
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(5) Grouted Riprap (Class A)


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 481.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


c. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
Minor Tools (5% of Labor) 24.08

Sub - Total for B 318.58


C. Total (A + B) 800.12
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 640.09
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 3.00 220.00 660.00


b. Sand cu.m. 0.25 850.00 212.50
c. Gravel Fill cu.m. 0.015 650.00 9.75
d. Weep Holes (PVC) m 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders (15 - 25 kg.) cu.m. 1.05 920.00 966.00
Miscellaneous (1% of Materials Cost) 18.96

Sub - Total for F 1,914.73


G. Direct Unit Cost (E + F) 2,554.83
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 229.93
I. Contractor's Profit (CP) 8% of G 204.39
J. Value Added Tax (VAT) 5% of (G + H + I) 149.46
K. Total Unit Cost (G + H + I + J) 3,138.61
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(6) Grouted Riprap (Class B)


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


b. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.50 922.00 461.00
Minor Tools (5% of Labor Cost) 16.28

Sub - Total for B 771.78


C. Total (A + B) 1,097.44
D. Output per hour = 1.000 cu.m.
E. Direct Unit Cost (C ÷ D) 1,097.44
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 2.50 220.00 550.00


b. Sand cu.m. 0.21 850.00 178.50
c. Gravel Fill cu.m. 0.015 650.00 9.75
d. Weep Holes (PVC) m 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders (30 - 70 kg.) cu.m. 1.05 810.00 850.50
Miscellaneous (1% of Materials Cost) 16.36

Sub - Total for F 1,652.64


G. Direct Unit Cost (E + F) 2,750.08
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 247.51
I. Contractor's Profit (CP) 8% of G 220.01
J. Value Added Tax (VAT) 5% of (G + H + I) 160.88
K. Total Unit Cost (G + H + I + J) 3,378.48
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(7) Grouted Riprap (Class C)


Unit of Measurement : cu.m.
Output per hour : 0.75

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


b. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.75 922.00 691.50
Minor Tools (5% of Labor) 16.28

Sub - Total for B 1,002.28


C. Total (A + B) 1,327.94
D. Output per hour = 0.75 cu.m.
E. Direct Unit Cost (C ÷ D) 1,770.59
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 2.20 220.00 484.00


b. Sand cu.m. 0.18 850.00 153.00
c. Gravel Fill cu.m. 0.015 650.00 9.75
d. Weep Holes (PVC) m 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders (60 - 100 kg.) cu.m. 1.05 730.00 766.50
Miscellaneous (1% of Materials) 14.61

Sub - Total for F 1,475.38


G. Direct Unit Cost (E + F) 3,245.97
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 292.14
I. Contractor's Profit (CP) 8% of G 259.68
J. Value Added Tax (VAT) 5% of (G + H + I) 189.89
K. Total Unit Cost (G + H + I + J) 3,987.68
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(8) Grouted Riprap (Class D)


Unit of Measurement : cu.m.
Output per hour : 0.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


b. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
c. Backhoe (Wheel Type 0.28 cu.m.) 1 1.00 922.00 922.00
Minor Tools (5% of Labor) 16.28

Sub - Total for B 1,232.78


C. Total (A + B) 1,558.44
D. Output per hour = 0.50 cu.m.
E. Direct Unit Cost (C ÷ D) 3,116.89
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 1.80 220.00 396.00


b. Sand cu.m. 0.15 850.00 127.50
c. Gravel Fill cu.m. 0.015 650.00 9.75
d. Weep Holes (PVC) m 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders (100 - 200 kg.) cu.m. 1.05 650.00 682.50
Miscellaneous (1% of Materials) 12.63

Sub - Total for F 1,275.91


G. Direct Unit Cost (E + F) 4,392.79
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 395.35
I. Contractor's Profit (CP) 8% of G 351.42
J. Value Added Tax (VAT) 5% of (G + H + I) 256.98
K. Total Unit Cost (G + H + I + J) 5,396.55
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(9) Filter Layer of Granular Material


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Minor Tools (10% of Labor Cost) 19.75

Sub - Total for B 19.75


C. Total (A + B) 217.29
D. Output per hour = 1.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 217.29
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Granular Materials cu.m. 1.05 900.00 945.00

Sub - Total for F 945.00


G. Direct Unit Cost (E + F) 1,162.29
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 104.61
I. Contractor's Profit (CP) 8% of G 92.98
J. Value Added Tax (VAT) 5% of (G + H + I) 67.99
K. Total Unit Cost (G + H + I + J) 1,427.88
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 506 Stone Masonry


Unit of Measurement : cu.m.
Output per hour : 1.60

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 481.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


b. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 922.00 92.20
Minor Tools (10% Labor Cost) 48.15

Sub - Total for B 434.85


C. Total (A + B) 916.39
D. Output per hour =1.6000 cu.m.
E. Direct Unit Cost (C ÷ D) 572.75
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 5.50 240.00 1,320.00


b. Sand cu.m. 0.30 500.00 150.00
c. Gravel Fill cu.m. 0.02 600.00 12.00
d. Weep Holes (PVC) m 0.30 195.00 58.50
e. Filter Cloth sq.m. 0.015 160.00 2.40
f. Boulders cu.m. 1.05 560.00 588.00
Miscellaneous (1% of Materials Cost) 21.31

Sub - Total for F 2,152.21


G. Direct Unit Cost (E + F) 2,724.96
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 245.25
I. Contractor's Profit (CP) 8% of G 218.00
J. Value Added Tax (VAT) 5% of (G + H + I) 159.41
K. Total Unit Cost (G + H + I + J) 3,347.61
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 507 Rubble Concrete


Unit of Measurement : cu.m.
Output per hour : 1.40

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 481.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


b. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 922.00 92.20
Minor Tools (10% Labor Cost) 48.15

Sub - Total for B 434.85


C. Total (A + B) 916.39
D. Output per hour = 1.400 cu.m.
E. Direct Unit Cost (C ÷ D) 654.57
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 4.20 220.00 924.00


b. Sand cu.m. 0.2625 850.00 223.13
c. Gravel Fill cu.m. 0.02 650.00 13.00
d. Weep Holes (PVC) m 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders cu.m. 0.63 810.00 510.30
g. Gravel cu.m. 0.525 650.00 341.25
Miscellaneous (2% of Materials) 36.72
Note:
60% Boulder
50% Class "B" Concrete (w/ side forms only)

Sub - Total for F 2,095.92


G. Direct Unit Cost (E + F) 2,750.49
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 247.54
I. Contractor's Profit (CP) 8% of G 220.04
J. Value Added Tax (VAT) 5% of (G + H + I) 160.90
K. Total Unit Cost (G + H + I + J) 3,378.98
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 508 Hand Laid Rock Embankment


Unit of Measurement : cu.m.
Output per hour : 3.125

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 481.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Minor Tools (10% of Labor Cost) 48.15

Sub - Total for B 48.15


C. Total (A + B) 529.69
D. Output per hour = 3.125 cu.m.
E. Direct Unit Cost (C ÷ D) 169.50
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Boulders cu.m. 1.05 920.00 966.00

Sub - Total for F 966.00


G. Direct Unit Cost (E + F) 1,135.50
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 102.20
I. Contractor's Profit (CP) 8% of G 90.84
J. Value Added Tax (VAT) 5% of (G + H + I) 66.43
K. Total Unit Cost (G + H + I + J) 1,394.96
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(a) Timber Sheet Pile


Unit of Measurement : m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 1.00 2,606.00 2,606.00


b. Drop Hammer (15 T) 1 1.00 200.00 200.00
Minor Tools (10% of Labor Cost) 19.75

Sub - Total for B 2,825.75


C. Total (A + B) 3,023.29
D. Output per hour = 4.0000 m.
E. Direct Unit Cost (C ÷ D) 755.82
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Timber Sheet Piles, ave. dia. 395mm bd.ft. 52.25 40.00 2,090.00
b. Coco Log - 2 uses m. 1.00 350.00 175.00
c. Lumber (Falsework) - 4 uses bd.ft. 16.00 40.00 160.00
d. Nail/Spike (1 kg./100 bd.ft. of Lumber) kg. 0.16 68.00 10.88

Sub - Total for F 2,435.88


G. Direct Unit Cost (E + F) 3,191.70
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 287.25
I. Contractor's Profit (CP) 8% of G 255.34
J. Value Added Tax (VAT) 5% of (G + H + I) 186.71
K. Total Unit Cost (G + H + I + J) 3,921.01
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(b) Steel Sheet Pile (Slope Protection)


Unit of Measurement : m
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Crawler Crane (36 - 40 T) 1 1.00 1,902.00 1,902.00


b. Vibro Hammer (Hydraulic Operated) 1 1.00 2,123.00 2,123.00
c. Welding Machine (300 A, Gas/Diesel Driven 1 0.25 371.00 92.75
d. Cutting Outfit 1 0.25 45.45 11.36

Sub - Total for B 4,129.11


C. Total (A + B) 4,454.77
D. Output per hour = 10.0000 m.
E. Direct Unit Cost (C ÷ D) 445.48
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Steel Sheet Piles (48 kg./m.) kg. 48.00 48.00 2,304.00


Miscellaneous (3% of Materials Cost) 69.12

Sub - Total for F 2,373.12


G. Direct Unit Cost (E + F) 2,818.60
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 253.67
I. Contractor's Profit (CP) 8% of G 225.49
J. Value Added Tax (VAT) 5% of (G + H + I) 164.89
K. Total Unit Cost (G + H + I + J) 3,462.65
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(c) Concrete Sheet Pile, furnished and driven - 0.50 m x 0.35 m
Unit of Measurement : m
Output per hour : 1.38

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 6 1.00 50.18 301.08
c. Unskilled Labor 6 1.00 38.97 233.82

Sub - Total for A 604.32

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.23 2,606.00 599.38


b. Diesel Hammer (K25 or equivalent) 1 0.13 150.00 19.50
c. One Bagger Mixer 1 0.15 172.00 25.80
d. Concrete Vibrator 1 0.15 91.25 13.69
e. Water Truck/Pump (16000L) 1 0.01 2,450.00 24.50
f. Bar Cutter, Single Phase 1 0.20 219.75 43.95
f. Bar Bender 1 0.20 351.50 70.30
g. Drop Hammer 1 0.13 200.00 26.00
h. Jack Hammer 2 0.01 150.00 3.00
i. Air Compressor (356 - 450 cfm) 1 0.01 965.00 9.65
j. Plate Compactor (5 Hp) 1 0.01 123.00 1.23
Minor Tools (5% of Labor) 30.22

Sub - Total for B 867.21


C. Total (A + B) 1,471.53
D. Output per hour = 1.3800 m.
E. Direct Unit Cost (C ÷ D) 1,066.33
Name and Specification Unit Quantity Unit Cost Amount

F. Materials
a. Coco Log kg. 0.71 40.00 28.40
b. Reinforcing Steel Bar bag 41.64 220.00 9,160.80
c. Cement cu.m. 1.66 850.00 1,411.00
d. Sand cu.m. 0.09 650.00 58.50
e. Gravel pc. 0.18 700.00 126.00
f. Marine Plywood, 1/2" x 4' x 8' - 4 uses pc. 0.24 700.00 42.00
g. Lumber, 2' x 2' - 4 uses bd.ft. 18.59 40.00 185.90
h. # 16 GI Tie Wire (2% of RSB) kg. 0.83 47.00 39.01
i. Spike (1 kg/100 bd.ft of Lumber kg. 0.06 68.00 4.08
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.19 68.00 12.92
Casting Bed
a. Ready Mix Concrete cu.m 0.03 2,840.00 85.20
b. Coco Lumber - 4 uses bd.ft. 1.50 20.00 7.50
c. Base Course cu.m 0.03 530.00 15.90
Sub - Total for F 11,161.31
G. Direct Unit Cost (E + F) 12,227.64
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1,100.49
I. Contractor's Profit (CP) 8% of G 978.21
J. Value Added Tax (VAT) 5% of (G + H + I) 715.32
K. Total Unit Cost (G + H + I + J) 15,021.65
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 510(1) Bed Course Granular Material


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 225.30

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Plate Compactor 1 1.00 123.00 123.00


Minor Tools (10% of Labor) 22.53

Sub - Total for B 145.53


C. Total (A + B) 370.83
D. Output per hour = 1.2500 cu.m.
E. Direct Unit Cost (C ÷ D) 296.66
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Aggregate Subbase Course cu.m. 1.15 580.00 667.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 667.00


G. Direct Unit Cost (E + F) 963.66
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 86.73
I. Contractor's Profit (CP) 8% of G 77.09
J. Value Added Tax (VAT) 5% of (G + H + I) 56.37
K. Total Unit Cost (G + H + I + J) 1,183.86
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 510(2) Concrete Slope Protection


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
Installation of Formworks & Rebars
b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 838.14

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


c. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
a. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 922.00 92.20
b. Concrete Vibrator 1 0.50 91.25 45.63
h. Bar Cutter, Single Phase 1 0.05 219.75 10.99
b. Bar Bender 1 0.05 351.50 17.58
Minor Tools (10% Labor) 83.81

Sub - Total for B 544.70


C. Total (A + B) 1,382.84
D. Output per hour = 1.0000 cu.m.
E. Direct Unit Cost (C ÷ D) 1,382.84

Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cement bag 8.40 220.00 1,848.00


b. Sand cu.m. 0.50 850.00 425.00
c. Weep Holes (PVC) m 0.21 144.67 30.38
d. Filter Cloth sq.m. 0.015 275.00 4.13
e. Gravel cu.m. 1.00 650.00 650.00
f. Granular Filter cu.m. 0.016 650.00 10.40
f. Reinforcing Steel Bar kg. * 26.03 40.00 1,041.20
g. Marine Plywood 1/2" x 4' x 8' - 4 uses pc. 0.48 700.00 84.00
h. Lumber - 4 uses bd.ft. 18.76 40.00 187.60
i. #16 GI Tie Wire (2% of RSB) kg. 0.521 47.00 24.49
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.188 68.00 12.78

Sub - Total for F 4,317.98


G. Direct Unit Cost (E + F) 5,700.82
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 513.07
I. Contractor's Profit (CP) 8% of G 456.07
J. Value Added Tax (VAT) 5% of (G + H + I) 333.50
K. Total Unit Cost (G + H + I + J) 7,003.46
* Note: RSB quantity is variable based on approved plan.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(1) Gabions


Unit of Measurement : cu.m.
Output per hour : 2.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 481.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be separate as the
quantity is variable.

Sub - Total for B 0.00


C. Total (A + B) 481.54
D. Output per hour = 2.500 cu.m.
E. Direct Unit Cost (C ÷ D) 192.62
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Gabion Wire Mesh (1 x 1 x 2) pc. 0.50 2,900.00 1,450.00


(w/ complete accessories)
b. Boulders cu.m. 1.05 920.00 966.00

Sub - Total for F 2,416.00


G. Direct Unit Cost (E + F) 2,608.62
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 234.78
I. Contractor's Profit (CP) 8% of G 208.69
J. Value Added Tax (VAT) 5% of (G + H + I) 152.60
K. Total Unit Cost (G + H + I + J) 3,204.68
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(2) Mattresses


Unit of Measurement : cu.m.
Output per hour : 3.125

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 481.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be separate as the
quantity is variable.

Sub - Total for B 0.00


C. Total (A + B) 481.54
D. Output per hour = 3.125 cu.m.
E. Direct Unit Cost (C ÷ D) 154.09
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Mattresses (6 x 2 x 0.3 ) pc. 0.28 5,000.00 1,400.00


(w/ complete accessories)
b. Boulders cu.m. 1.05 920.00 966.00

Sub - Total for F 2,366.00


G. Direct Unit Cost (E + F) 2,520.09
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 226.81
I. Contractor's Profit (CP) 8% of G 201.61
J. Value Added Tax (VAT) 5% of (G + H + I) 147.43
K. Total Unit Cost (G + H + I + J) 3,095.93
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(3) Filter Cloth


Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 481.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Cargo Truck (9 - 10 mt) 1 0.25 1,212.00 303.00

Sub - Total for B 303.00


C. Total (A + B) 784.54
D. Output per hour = 100.0000 sq.m.
E. Direct Unit Cost (C ÷ D) 7.85
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Filter Cloth sq.m. 1.05 275.00 288.75


Miscellaneous (5% of Materials Cost) 14.44

Sub - Total for F 303.19


G. Direct Unit Cost (E + F) 311.03
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 27.99
I. Contractor's Profit (CP) 8% of G 24.88
J. Value Added Tax (VAT) 5% of (G + H + I) 18.20
K. Total Unit Cost (G + H + I + J) 382.10
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(1) Concrete Curb (Cast in place) - 0.45m x 0.15/0.20m Item
Unit of Measurement : m. Unit
Output per hour : 17.50 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 581.90

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Concrete Vibrator 1 1.00 91.25 91.25


b. One Bagger Mixer 1 1.00 172.00 172.00
c. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 443.94


C. Total (A + B) 1,025.84 C.
D. Output per hour = 17.500 m. D.
E. Direct Unit Cost (C ÷ D) 58.62 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Cement bag 0.72 220.00 158.40


b. Sand cu.m. 0.04 850.00 34.00
c. Gravel cu.m. 0.08 650.00 52.00
d. Plywood Marine, 1/2" thk. x 4' x 8 - 4 uses pc. 0.28 700.00 49.00
e. Form Lumber - 4 uses bd.ft. 12.16 40.00 121.60
f. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.12 68.00 8.16

Sub - Total for F 423.16


G. Direct Unit Cost (E + F) 481.78 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 43.36 H.
I. Contractor's Profit (CP) 8% of G 38.54 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 28.18 J.
K. Total Unit Cost (G + H + I + J) 591.87 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(2) Concrete Gutter (Cast in place) - 0.50m x 0.15m Item
Unit of Measurement : m. Unit
Output per hour : 17.50 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 581.90

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Concrete Vibrator 1 1.00 91.25 91.25


b. One Bagger Mixer 1 1.00 172.00 172.00
c. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 443.94


C. Total (A + B) 1,025.84 C.
D. Output per hour = 17.500 m. D.
E. Direct Unit Cost (C ÷ D) 58.62 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Cement bag 0.72 220.00 158.40


b. Sand cu.m. 0.04 850.00 34.00
c. Gravel cu.m. 0.08 650.00 52.00
d. Good Lumber - 4 uses bd.ft. 3.28 40.00 32.80
e. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.03 68.00 2.04
f. Reinforcing Steel Bar kg. 0.84 37.00 31.08

Sub - Total for F 310.32


G. Direct Unit Cost (E + F) 368.94 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 33.20 H.
I. Contractor's Profit (CP) 8% of G 29.52 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 21.58 J.
K. Total Unit Cost (G + H + I + J) 453.24 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(3) Concrete Curb and Gutter, Type A (Cast in place) - National Road Item
Unit of Measurement : m Unit
Output per hour : 10.30 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 581.90

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Concrete Vibrator 1 1.00 91.25 91.25


b. One Bagger Mixer 1 1.00 172.00 172.00
c. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 443.94


C. Total (A + B) 1,025.84 C.
D. Output per hour = 10.300 m. D.
E. Direct Unit Cost (C ÷ D) 99.60 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Cement bag 1.29 220.00 283.80


b. Sand cu.m. 0.07 850.00 59.50
c. Gravel cu.m. 0.14 650.00 91.00
d. Plywood Marine, 1/2" thk. x 4' x 8 - 4 uses pc. 0.24 700.00 42.00
e. Form Lumber - 4 uses bd.ft. 11.47 40.00 114.70
f. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.11 68.00 7.48
Miscellaneous (2% of Materials) 11.97

Sub - Total for F 610.45


G. Direct Unit Cost (E + F) 710.05 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 63.90 H.
I. Contractor's Profit (CP) 8% of G 56.80 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 41.54 J.
K. Total Unit Cost (G + H + I + J) 872.29 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(4) Concrete Curb (Precast) Item


Unit of Measurement : pc. Unit
Output per hour : 4.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 1 1.00 38.97 38.97

Sub - Total for A 158.57

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

b. Boom Truck (2 - 5 mt) 1 0.50 1,017.90 508.95


Minor Tools (10% of Labor) 15.86

Sub - Total for B 524.81


C. Total (A + B) 683.38 C.
D. Output per hour = 4.0000 pc. D.
E. Direct Unit Cost (C ÷ D) 170.84 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Fabricated Concrete Curb m 1.00 690.00 690.00


Miscellaneous (5% of materials) 34.50

Sub - Total for F 724.50


G. Direct Unit Cost (E + F) 895.34 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 80.58 H.
I. Contractor's Profit (CP) 8% of G 71.63 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 52.38 J.
K. Total Unit Cost (G + H + I + J) 1,099.93 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(5) Concrete Gutter (Precast) Item


Unit of Measurement : pc. Unit
Output per hour : 4.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 1 1.00 38.97 38.97

Sub - Total for A 158.57

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

b. Boom Truck (2 - 5 mt) 1 0.50 1,017.90 508.95


Minor Tools (10% of Labor) 15.86

Sub - Total for B 524.81


C. Total (A + B) 683.38 C.
D. Output per hour = 4.0000 pc. D.
E. Direct Unit Cost (C ÷ D) 170.84 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Fabricated Concrete Gutter m 1.00 680.00 680.00


Miscellaneous (5% of materials) 34.00

Sub - Total for F 714.00


G. Direct Unit Cost (E + F) 884.84 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 79.64 H.
I. Contractor's Profit (CP) 8% of G 70.79 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 51.76 J.
K. Total Unit Cost (G + H + I + J) 1,087.03 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(6) Concrete Curb and Gutter (Precast) Item


Unit of Measurement : pc. Unit
Output per hour : 3.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 1 1.00 38.97 38.97

Sub - Total for A 158.57

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

b. Boom Truck (2 - 5 mt) 1 0.50 1,017.90 508.95


Minor Tools (10% of Labor) 15.86

Sub - Total for B 524.81


C. Total (A + B) 683.38 C.
D. Output per hour = 3.0000 pc. D.
E. Direct Unit Cost (C ÷ D) 227.79 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Fabricated Concrete Curb and Gutter m 1.00 1,750.00 1,750.00


Miscellaneous (5% of materials) 87.50

Sub - Total for F 1,837.50


G. Direct Unit Cost (E + F) 2,065.29 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 185.88 H.
I. Contractor's Profit (CP) 8% of G 165.22 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 120.82 J.
K. Total Unit Cost (G + H + I + J) 2,537.21 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 601(a) Sidewalk (100mm thk.) Item


Unit of Measurement : sq.m. Unit
Output per hour : 161.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00


b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
Minor Tools (5% of Labor) 36.89

Sub - Total for B 12,011.52


C. Total (A + B) 12,749.30 C.
D. Output per hour = 161.0000 sq.m. D.
E. Direct Unit Cost (C ÷ D) 79.19 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Curing Compound L 0.29 28.00 8.12


b. Asphalt Sealant L 0.12 44.00 5.28
c. Forms m 0.46 250.00 115.00
d. Sand cu.m. 0.055 850.00 46.75
e. Gravel cu.m. 0.10 650.00 65.00
f. Cement bag 0.95 220.00 209.00

Note : Bed Course excluded

Sub - Total for F 449.15


G. Direct Unit Cost (E + F) 528.34 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 47.55 H.
I. Contractor's Profit (CP) 8% of G 42.27 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 30.91 J.
K. Total Unit Cost (G + H + I + J) 649.06 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 601(b) Sidewalk (100mm thk.) Item


Unit of Measurement : sq.m. Unit
Output per hour : 20.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. One Bagger Mixer 1 1.00 172.00 172.00


b. Water Truck/Pump (16000L) 2 1.00 2,450.00 4,900.00
c. Concrete Vibrator 1 0.125 91.25 11.41
d. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 5,152.93


C. Total (A + B) 5,890.71 C.
D. Output per hour = 20.0000 sq.m. D.
E. Direct Unit Cost (C ÷ D) 294.54 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Curing Compound L 0.29 28.00 8.12


b. Asphalt Sealant L 0.12 44.00 5.28
c. Forms m 0.46 250.00 115.00
d. Sand cu.m. 0.055 850.00 46.75
e. Gravel cu.m. 0.10 650.00 65.00
f. Cement bag 0.95 220.00 209.00

Note : Bed Course excluded

Sub - Total for F 449.15


G. Direct Unit Cost (E + F) 743.69 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 66.93 H.
I. Contractor's Profit (CP) 8% of G 59.49 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 43.51 J.
K. Total Unit Cost (G + H + I + J) 913.62 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(1)a Right-of-Way Monument Item


Unit of Measurement : ea. Unit
Output per hour : 2.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Concrete Vibrator 1 0.20 91.25 18.25


b. Cargo Truck (9 - 10 mt) 1 0.05 1,212.00 60.60
Minor Tools (10% of Labor) 19.75

Sub - Total for B 98.60


C. Total (A + B) 296.14 C.
D. Output per hour = 2.0000 ea. D.
E. Direct Unit Cost (C ÷ D) 148.07 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Concrete Class "A" cu.m. 0.03 3,538.78 106.16


b. Reinforcing Steel Bar, Grade 40 kg. 7.15 40.00 286.00
c. Plywood, 1/2" x 4' x 8' - 4 uses pc. 0.22 700.00 38.50
d. Form Lumber, Good - 4 uses bd.ft. 13.53 40.00 135.30
e. Reflectorized Paint, Marker L 0.10 475.00 47.50
f. # 16 Tie Wire (2% of RSB) kg. 0.14 47.00 6.58
g. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.14 68.00 9.52

Sub - Total for F 629.56


G. Direct Unit Cost (E + F) 777.64 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 69.99 H.
I. Contractor's Profit (CP) 8% of G 62.21 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 45.49 J.
K. Total Unit Cost (G + H + I + J) 955.33 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(1)b Right-of-Way Monument (Precast) Item


Unit of Measurement : ea. Unit
Output per hour : 4.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

b. Cargo Truck (9 - 10 mt) 1 0.05 1,212.00 60.60


Minor Tools (10% of Labor) 19.75

Sub - Total for B 80.35


C. Total (A + B) 277.89 C.
D. Output per hour = 4.0000 ea. D.
E. Direct Unit Cost (C ÷ D) 69.47 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Fabricated Right-of-Way Monument ea. 1.00 3,320.00 3,320.00


(delivered at site)

Sub - Total for F 3,320.00


G. Direct Unit Cost (E + F) 3,389.47 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 305.05 H.
I. Contractor's Profit (CP) 8% of G 271.16 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 198.28 J.
K. Total Unit Cost (G + H + I + J) 4,163.97 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(2)a Maintenance Marker Post Item


Unit of Measurement : ea. Unit
Output per hour : 2.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Concrete Vibrator 1 0.20 91.25 18.25


b. Cargo Truck (9 - 10 mt) 1 0.05 1,212.00 60.60
Minor Tools (10% of Labor) 19.75

Sub - Total for B 98.60


C. Total (A + B) 296.14 C.
D. Output per hour = 2.0000 ea. D.
E. Direct Unit Cost (C ÷ D) 148.07 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Concrete Class "A" cu.m. 0.03 3,400.00 102.00


b. Reinforcing Steel Bar, Grade 40 kg. 7.15 40.00 286.00
c. Plywood, 1/2" x 4' x 8' - 4 uses pc. 0.22 700.00 38.50
d. Form Lumber, Good - 4 uses bd.ft. 13.53 40.00 135.30
e. Reflectorized Paint, Marker L 0.10 475.00 47.50
f. # 16 Tie Wire (2% of RSB) kg. 0.14 47.00 6.58
g. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.14 68.00 9.52

Sub - Total for F 625.40


G. Direct Unit Cost (E + F) 773.47 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 69.61 H.
I. Contractor's Profit (CP) 8% of G 61.88 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 45.25 J.
K. Total Unit Cost (G + H + I + J) 950.21 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(2)b Maintenance Marker Post (Precast) Item


Unit of Measurement : ea. Unit
Output per hour : 4.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

b. Cargo Truck (9 - 10 mt) 1 0.05 1,212.00 60.60


Minor Tools (10% of Labor) 19.75

Sub - Total for B 80.35


C. Total (A + B) 277.89 C.
D. Output per hour = 4.0000 ea. D.
E. Direct Unit Cost (C ÷ D) 69.47 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Fabricated Maintenance Marker Post ea. 1.00 1,650.00 1,650.00


(delivered at site)

Sub - Total for F 1,650.00


G. Direct Unit Cost (E + F) 1,719.47 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 154.75 H.
I. Contractor's Profit (CP) 8% of G 137.56 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 100.59 J.
K. Total Unit Cost (G + H + I + J) 2,112.37 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(3)a Kilometer Post Item


Unit of Measurement : ea. Unit
Output : 1.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.50 69.42 104.13


b. Skilled Labor 1 1.50 50.18 75.27
c. Unskilled Labor 2 1.50 38.97 116.91

Sub - Total for A 296.31

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Cargo Truck (9 - 10 mt) 1 0.50 1,212.00 606.00


b. Concrete Vibrator 1 0.10 91.25 9.13
Minor Tools (10% of Labor) 29.63

Sub - Total for B 644.76


C. Total (A + B) 941.07 C.
D. Output = 1.0000 ea. D.
E. Direct Unit Cost (C ÷ D) 941.07 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Concrete Class "A" cu.m. 0.184 3,400.00 625.60


b. Reinforcing Steel Bar kg. 7.59 40.00 303.60
c. Plywood 1/2" x 4' x 8' - 2 uses pc. 0.604 700.00 211.40
d. Lumber - 2 uses bd.ft. 7.15 20.00 71.50
e. Portland Cement bag 0.775 220.00 170.50
f. Pebble cu.m. 0.044 900.00 39.60
g. Reflectorized Paint, Marker L 0.20 475.00 95.00
h. # 16 Tie Wire (2% of RSB) kg. 0.14 47.00 6.58
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.07 68.00 4.76

Sub - Total for F 1,528.54


G. Direct Unit Cost (E + F) 2,469.61 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 222.26 H.
I. Contractor's Profit (CP) 8% of G 197.57 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 144.47 J.
K. Total Unit Cost (G + H + I + J) 3,033.91 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(3)b Kilometer Post (Precast) Item


Unit of Measurement : ea. Unit
Output : 2.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.50 69.42 104.13


b. Skilled Labor 1 1.50 50.18 75.27
c. Unskilled Labor 2 1.50 38.97 116.91

Sub - Total for A 296.31

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Cargo Truck (9 - 10 mt) 1 0.50 1,212.00 606.00


b. Concrete Vibrator 1 0.05 91.25 4.56
Minor Tools (10% of Labor) 29.63

Sub - Total for B 640.19


C. Total (A + B) 936.50 C.
D. Output = 2.0000 ea. D.
E. Direct Unit Cost (C ÷ D) 468.25 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Fabricated Kilometer Post ea. 1.00 4,150.00 4,150.00


b. Concrete Class "A" cu.m. 0.095 3,400.00 323.00
c. Reflectorized Paint, Marker lit. 0.20 475.00 95.00

Sub - Total for F 4,568.00


G. Direct Unit Cost (E + F) 5,036.25 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 453.26 H.
I. Contractor's Profit (CP) 8% of G 402.90 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 294.62 J.
K. Total Unit Cost (G + H + I + J) 6,187.04 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(4) Guide Post Item


Unit of Measurement : ea. Unit
Output per hour : 50.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

Minor Tools (10% of Labor) 14.74

Sub - Total for B 14.74


C. Total (A + B) 162.10 C.
D. Output per hour = 50.0000 ea. D.
E. Direct Unit Cost (C ÷ D) 3.24 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Guide Post (Portable) ea. 1.00 1,240.00 1,240.00


b. Post Reflector ea. 1.00 85.00 85.00
Miscellaneous (5% of Materials) 66.25

Sub - Total for F 1,391.25


G. Direct Unit Cost (E + F) 1,394.49 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 125.50 H.
I. Contractor's Profit (CP) 8% of G 111.56 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 81.58 J.
K. Total Unit Cost (G + H + I + J) 1,713.13 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(1) Cable Wire Guardrail Item


Unit of Measurement : m Unit
Output per hour : 1.15 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 481.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. One Bagger Mixer 1 1.00 172.00 172.00


b. Concrete Vibrator 1 0.25 91.25 22.81
c. Water Truck/Pump (16000L) 1 0.10 2,450.00 245.00
d. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
Minor Tools (10% of Labor) 48.15

Sub - Total for B 683.72


C. Total (A + B) 1,165.26 C.
D. Output per hour = 1.15 m. D.
E. Direct Unit Cost (C ÷ D) 1,013.27 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Cement bag 4.18 220.00 919.60


b. Sand cu.m. 0.22 850.00 187.00
c. Gravel cu.m. 0.43 650.00 279.50
d. Guardrail Post set 0.27 *1,800.00 486.00
e. Galvanized Wire Rope (1.21 kg./m) kg. 4.92 186.44 917.28
f. Check Rope set 0.22 *750.00 165.00
g. Hook Bolt ea. 0.33 *350.00 115.50
h. Anchor Bracket unit 0.11 *1,200.00 132.00
i. Wire Mesh sq.m. 0.11 *295.00 32.45
j. Tension Fittings set 0.65 *1,000.00 650.00
Miscellaneous (5% of Materials) 194.22

Sub - Total for F 4,078.55


G. Direct Unit Cost (E + F) 5,091.82
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 458.26 G.
I. Contractor's Profit (CP) 8% of G 407.35 H.
J. Value Added Tax (VAT) 5% of (G + H + I) 297.87 I.
K. Total Unit Cost (G + H + I + J) 6,255.30 J.
* Tentative Canvass Price K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(3)a Metal Guardrails (Metal Beam) including Concrete Post Item
Unit of Measurement : m Unit
Output per hour : 4.20 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. One Bagger Mixer 1 0.50 172.00 86.00


b. Concrete Vibrator 1 0.50 91.25 45.63
c. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
d. Cargo Truck (9 - 10 mt) 1 0.25 1,212.00 303.00
Minor Tools (5 % of Labor Cost) 16.28

Sub - Total for B 573.41


C. Total (A + B) 899.07 C.
D. Output per hour = 4.2000 m. D.
E. Direct Unit Cost (C ÷ D) 214.06 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Cement bag 0.33 220.00 72.60


b. Sand cu.m. 0.018 850.00 15.30
c. Gravel cu.m. 0.036 650.00 23.40
d. Metal Beam Guardrail m 1.00 1,950.00 1,950.00
e. Plywood Marine, 1/2" thk. x 4' x 8' - 4 uses pc. 0.25 700.00 43.75
f. Lumber - 4 uses bd.ft. 8.00 40.00 80.00
g. Reinforcing Steel Bars, Grade 40 kg. 4.00 40.00 160.00
h. Tie Wire (2% of RSB) kg. 0.08 47.00 3.76
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44
j. Bolt, Nut & Washer 5/8" dia. x 9" pc. 0.50 28.00 14.00
k. Bolt, Nut & Washer 5/8" dia. x 1" pc. 2.00 21.00 42.00

Sub - Total for F 2,410.25


G. Direct Unit Cost (E + F) 2,624.31 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 236.19 H.
I. Contractor's Profit (CP) 8% of G 209.95 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 153.52 J.
K. Total Unit Cost (G + H + I + J) 3,223.97 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(3)b Metal Beam End Piece Item


Unit of Measurement : ea. Unit
Output per hour : 6.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Cargo Truck (9 - 10 mt) 1 1.00 1,212.00 1,212.00


Minor Tools (5% of Labor) 9.88

Sub - Total for B 1,221.88


C. Total (A + B) 1,419.42 C.
D. Output per hour = 6.00000 ea. D.
E. Direct Unit Cost (C ÷ D) 236.57 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Metal Guardrail End Piece ea. 1.00 1,350.00 1,350.00

Sub - Total for F 1,350.00


G. Direct Unit Cost (E + F) 1,586.57 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 142.79 H.
I. Contractor's Profit (CP) 8% of G 126.93 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 92.81 J.
K. Total Unit Cost (G + H + I + J) 1,949.10 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(4) Guardrail (Timber) Item


Unit of Measurement : m Unit
Output per hour : 5.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 4 1.00 38.97 155.88

Sub - Total for A 325.66

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Cargo Truck (9 - 10 mt) 1 0.50 1,212.00 606.00


Minor Tools (10% of Labor) 32.57

Sub - Total for B 638.57


C. Total (A + B) 964.23 C.
D. Output per hour = 5.00000 m. D.
E. Direct Unit Cost (C ÷ D) 192.85 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Lumber, 8" x 8" x 5.5' Treated Post (Tanguile) bd.ft. 14.67 90.00 1,320.30
b. Lumber, 3" x 8" Plank (Tanguile) - Untreated bd.ft. 6.67 55.00 366.85
c. Carriage Bolt, 1/2"Ø x 12" pc. 1.60 350.00 560.00
Miscellaneous (5% of Materials) 112.36

Note: Exclude Excavation Works

Sub - Total for F 2,359.51


G. Direct Unit Cost (E + F) 2,552.35 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 229.71 H.
I. Contractor's Profit (CP) 8% of G 204.19 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 149.31 J.
K. Total Unit Cost (G + H + I + J) 3,135.57 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(1) Fencing (Barbed Wire) Item


Unit of Measurement : m Unit
Output per hour : 18.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Welding Machine (300 A, Gas/Diesel Driven 1 0.10 371.00 37.10


Minor Tools (10% of Labor) 19.75

Sub - Total for B 56.85


C. Total (A + B) 254.39 C.
D. Output per hour = 18.00000 m. D.
E. Direct Unit Cost (C ÷ D) 14.13 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. 3-Strand Galvanized Barbed Wire, Ga 12.5 m 1.00 15.00 15.00


b. 50mmx50mmx6m Angle Bar kg. 0.58 48.00 27.84
c. Ga. 9 Twisted Wire Fastener pc. 0.39 81.15 31.65
Miscellaneous (2% of Materials, Welding Rod & etc.) 1.49

Sub - Total for F 75.98


G. Direct Unit Cost (E + F) 90.11 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 8.11 H.
I. Contractor's Profit (CP) 8% of G 7.21 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 5.27 J.
K. Total Unit Cost (G + H + I + J) 110.70 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(2) Fencing (Chain Link Fence Fabric) - Type I Item
Unit of Measurement : m Unit
Output per hour : 6.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Welding Machine (300 A, Gas/Diesel Driven 1 0.50 371.00 185.50


Minor Tools (10% of Labor) 19.75

Sub - Total for B 205.25


C. Total (A + B) 402.79 C.
D. Output per hour = 6.00000 m. D.
E. Direct Unit Cost (C ÷ D) 67.13 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Cyclone Wire 8' Ga 10 m 1.00 220.00 220.00


b. 38mm x 38mm x 4mm Angle Bar kg 9.25 850.00 7,862.50
c. Welding Rod (1 kg/2000 kf of Steel kg 0.005 650.00 3.01

Sub - Total for F 8,085.51


G. Direct Unit Cost (E + F) 8,152.64 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 733.74 H.
I. Contractor's Profit (CP) 8% of G 652.21 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 476.93 J.
K. Total Unit Cost (G + H + I + J) 10,015.52 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(3) Fencing (Post) - Type I Item


Unit of Measurement : ea. Unit
Output : 1.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.50 69.42 104.13


b. Skilled Labor 2 1.50 50.18 150.54
c. Unskilled Labor 2 1.50 38.97 116.91

Sub - Total for A 371.58

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. One Bagger Mixer 1 0.75 172.00 129.00


b. Bar Cutter, Single Phase 1 0.50 219.75 109.88
c. Bar Bender 1 0.50 351.50 175.75
d. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
Minor Tools (10% of Labor) 37.16

Sub - Total for B 574.28


C. Total (A + B) 945.86 C.
D. Output = 1.00000 ea. D.
E. Direct Unit Cost (C ÷ D) 945.86 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Cement bag 5.68 220.00 1,249.60


b. Sand cu.m. 0.30 850.00 255.00
c. Gravel cu.m. 0.60 650.00 390.00
d. Reinforcing Steel Bar kg. 22.07 40.00 882.80
e. # 16 Tie Wire (2% of RSB) kg. 0.441 47.00 20.73
f. Plywood 1/4' x 4' x 8' - 2 uses pc. 1.94 350.00 339.50
g. Lumber - 2 uses bd.ft. 28.67 20.00 286.70
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.29 68.00 19.72

Sub - Total for F 3,444.05


G. Direct Unit Cost (E + F) 4,389.91 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 395.09 H.
I. Contractor's Profit (CP) 8% of G 351.19 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 256.81 J.
K. Total Unit Cost (G + H + I + J) 5,393.00 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(4) Fencing (Gates) - (Height 3m. & Length 4.24m.) Item
Unit of Measurement : ea. Unit
Output : 1.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Welding Machine (300 A, Gas/Diesel Driven 1 2.00 371.00 742.00


Minor Tools (10% of Labor) 19.75

Sub - Total for B 761.75


C. Total (A + B) 959.29 C.
D. Output = 1.00000 ea. D.
E. Direct Unit Cost (C ÷ D) 959.29 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. 50 mm. Ø G.I. Pipe, Schedule 40 pc. 5.00 1,550.00 7,750.00


b. Cyclone Wire Galvanized 10' Gauge 10 m 4.24 3,300.00 13,992.00
c. 6mm dia. Plain Bar kg. 3.37 40.00 134.80
Miscellaneous (3% of Material Cost, Gate Lock, Hinge & etc.) 656.30

Sub - Total for F 22,533.10


G. Direct Unit Cost (E + F) 23,492.40 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 2,114.32 H.
I. Contractor's Profit (CP) 8% of G 1,879.39 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 1,374.31 J.
K. Total Unit Cost (G + H + I + J) 28,860.41 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(1)a Danger/Warning Signs (60cm Triangle) Item


Unit of Measurement : ea. Unit
Output per hour : 1.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


Minor Tools (10 % of Labor) 19.75

Sub - Total for B 215.50


C. Total (A + B) 413.04 C.
D. Output per hour = 1.00000 ea. D.
E. Direct Unit Cost (C ÷ D) 413.04 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Portland Cement bag 0.48 220.00 105.60


b. Sand cu.m. 0.025 850.00 21.25
c. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.ft. 8.00 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2.00 48.00 96.00
g. Bolts, 5mm Ø pc. 12.00 10.00 120.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1.00 2,800.00 2,800.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44

Sub - Total for F 4,903.79


G. Direct Unit Cost (E + F) 5,316.83 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 478.52 H.
I. Contractor's Profit (CP) 8% of G 425.35 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 311.03 J.
K. Total Unit Cost (G + H + I + J) 6,531.73 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(1)b Danger/Warning Signs (90cm Triangle) Item


Unit of Measurement : ea. Unit
Output per hour : 1.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


Minor Tools (10 % of Labor) 19.75

Sub - Total for B 215.50


C. Total (A + B) 413.04 C.
D. Output per hour = 1.00000 ea. D.
E. Direct Unit Cost (C ÷ D) 413.04 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Portland Cement bag 0.48 220.00 105.60


b. Sand cu.m. 0.025 850.00 21.25
c. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.ft. 8.00 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2.00 48.00 96.00
g. Bolts, 5mm Ø pc. 12.00 10.00 120.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1.00 4,200.00 4,200.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44

Sub - Total for F 6,303.79


G. Direct Unit Cost (E + F) 6,716.83 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 604.52 H.
I. Contractor's Profit (CP) 8% of G 537.35 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 392.93 J.
K. Total Unit Cost (G + H + I + J) 8,251.63 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)a Regulatory Signs (60cm Triangle) Item


Unit of Measurement : ea. Unit
Output per hour : 1.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


Minor Tools (10 % of Labor) 19.75

Sub - Total for B 215.50


C. Total (A + B) 413.04 C.
D. Output per hour = 1.00000 ea. D.
E. Direct Unit Cost (C ÷ D) 413.04 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Portland Cement bag 0.48 220.00 105.60


b. Sand cu.m. 0.025 850.00 21.25
c. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.ft. 8.00 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2.00 48.00 96.00
g. Bolts, 5mm Ø pc. 12.00 10.00 120.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1.00 2,800.00 2,800.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44

Sub - Total for F 4,903.79


G. Direct Unit Cost (E + F) 5,316.83 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 478.52 H.
I. Contractor's Profit (CP) 8% of G 425.35 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 311.03 J.
K. Total Unit Cost (G + H + I + J) 6,531.73 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)b Regulatory Signs (90cm Triangle) Item


Unit of Measurement : ea. Unit
Output per hour : 1.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment B.

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


Minor Tools (10 % of Labor) 19.75

Sub - Total for B 215.50


C. Total (A + B) 413.04 C.
D. Output per hour = 1.00000 ea. D.
E. Direct Unit Cost (C ÷ D) 413.04 E.
Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

a. Portland Cement bag 0.48 220.00 105.60


b. Sand cu.m. 0.025 850.00 21.25
c. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.ft. 8.00 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2.00 48.00 96.00
g. Bolts, 5mm Ø pc. 12.00 10.00 120.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1.00 4,200.00 4,200.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44

Sub - Total for F 6,303.79


G. Direct Unit Cost (E + F) 6,716.83 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 604.52 H.
I. Contractor's Profit (CP) 8% of G 537.35 I.
J. Value Added Tax (VAT) 5% of (G + H + I) 392.93 J.
K. Total Unit Cost (G + H + I + J) 8,251.63 K.

Item
Unit
Out

A.

B.

C.
D.
E.

F.

G.
H.
I.
J.
K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)c Regulatory Signs (60cm Octagon)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


Minor Tools (10 % of Labor) 19.75

Sub - Total for B 215.50


Total (A + B) 413.04
Output per hour = 1.00000 ea.
Direct Unit Cost (C ÷ D) 413.04
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Portland Cement bag 0.48 220.00 105.60


b. Sand cu.m. 0.025 850.00 21.25
c. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.ft. 8.00 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2.00 70.78 141.56
g. Bolts, 5mm Ø pc. 12.00 10.00 120.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1.00 4,500.00 4,500.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44

Sub - Total for F 6,649.35


Direct Unit Cost (E + F) 7,062.39
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 635.62
Contractor's Profit (CP) 8% of G 564.99
Value Added Tax (VAT) 5% of (G + H + I) 413.15
Total Unit Cost (G + H + I + J) 8,676.15
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)d Regulatory Signs (90cm Octagon)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


Minor Tools (10 % of Labor) 19.75

Sub - Total for B 215.50


Total (A + B) 413.04
Output per hour = 1.00000 ea.
Direct Unit Cost (C ÷ D) 413.04
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Portland Cement bag 0.48 220.00 105.60


b. Sand cu.m. 0.025 850.00 21.25
c. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.ft. 8.00 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2.00 48.00 96.00
g. Bolts, 5mm Ø pc. 12.00 10.00 120.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1.00 7,500.00 7,500.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44

Sub - Total for F 9,603.79


Direct Unit Cost (E + F) 10,016.83
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 901.52
Contractor's Profit (CP) 8% of G 801.35
Value Added Tax (VAT) 5% of (G + H + I) 585.98
Total Unit Cost (G + H + I + J) 12,305.68
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)a Informative Signs (12"x24")


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


Minor Tools (10 % of Labor) 19.75

Sub - Total for B 215.50


Total (A + B) 413.04
Output per hour = 1.00000 ea.
Direct Unit Cost (C ÷ D) 413.04
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Portland Cement bag 1.320 220.00 290.40


b. Sand cu.m. 0.073 850.00 62.05
c. Gravel cu.m. 0.145 650.00 94.25
d. Form Lumber, Good - 4 uses bd.ft. 8.00 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2.00 48.00 96.00
g. Bolts, 5mm Ø pc. 12.00 10.00 120.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1.00 2,750.00 2,750.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44

Sub - Total for F 5,141.14


Direct Unit Cost (E + F) 5,554.18
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 499.88
Contractor's Profit (CP) 8% of G 444.33
Value Added Tax (VAT) 5% of (G + H + I) 324.92
Total Unit Cost (G + H + I + J) 6,823.32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)b Informative Signs (12"x48")


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


Minor Tools (10 % of Labor) 19.75

Sub - Total for B 215.50


Total (A + B) 413.04
Output per hour = 1.00000 ea.
Direct Unit Cost (C ÷ D) 413.04
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Portland Cement bag 1.320 220.00 290.40


b. Sand cu.m. 0.073 850.00 62.05
c. Gravel cu.m. 0.145 650.00 94.25
d. Form Lumber, Good - 4 uses bd.ft. 8.00 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2.00 48.00 96.00
g. Bolts, 5mm Ø pc. 12.00 10.00 120.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1.00 5,450.00 5,450.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44

Sub - Total for F 7,841.14


Direct Unit Cost (E + F) 8,254.18
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 742.88
Contractor's Profit (CP) 8% of G 660.33
Value Added Tax (VAT) 5% of (G + H + I) 482.87
Total Unit Cost (G + H + I + J) 10,140.27
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)c Informative Signs (18"x24")


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


Minor Tools (10 % of Labor) 19.75

Sub - Total for B 215.50


Total (A + B) 413.04
Output per hour = 1.00000 ea.
Direct Unit Cost (C ÷ D) 413.04

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Portland Cement bag 1.320 220.00 290.40


b. Sand cu.m. 0.073 850.00 62.05
c. Gravel cu.m. 0.145 650.00 94.25
d. Form Lumber, Good - 4 uses bd.ft. 8.00 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2.00 48.00 96.00
g. Bolts, 5mm Ø pc. 12.00 10.00 120.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1.00 3,750.00 3,750.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44

Sub - Total for F 6,141.14


Direct Unit Cost (E + F) 6,554.18
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 589.88
Contractor's Profit (CP) 8% of G 524.33
Value Added Tax (VAT) 5% of (G + H + I) 383.42
Total Unit Cost (G + H + I + J) 8,051.82
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)d Informative Signs (18"x48")


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


Minor Tools (10 % of Labor) 19.75

Sub - Total for B 215.50


Total (A + B) 413.04
Output per hour = 1.00000 ea.
Direct Unit Cost (C ÷ D) 413.04

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Portland Cement bag 1.320 220.00 290.40


b. Sand cu.m. 0.073 850.00 62.05
c. Gravel cu.m. 0.145 650.00 94.25
d. Form Lumber, Good - 4 uses bd.ft. 8.00 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2.00 48.00 96.00
g. Bolts, 5mm Ø pc. 12.00 10.00 120.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1.00 8,200.00 8,200.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44

Sub - Total for F 10,591.14


Direct Unit Cost (E + F) 11,004.18
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 990.38
Contractor's Profit (CP) 8% of G 880.33
Value Added Tax (VAT) 5% of (G + H + I) 643.74
Total Unit Cost (G + H + I + J) 13,518.64
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(1) Pavement Marking (Premix Reflectorized)


Unit of Measurement : sq.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (2 - 5 mt) 1 0.05 783.00 39.15


Minor Tools (5% of Labor) 9.88

Sub - Total for B 49.03


Total (A + B) 246.57
Output per hour = 10.00000 sq.m.
Direct Unit Cost (C ÷ D) 24.66

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Pavement Markings (White) L 1.00 450.00 450.00


Miscellaneous (5% of above) 22.50

Sub - Total for F 472.50


Direct Unit Cost (E + F) 497.16
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 44.74
Contractor's Profit (CP) 8% of G 39.77
Value Added Tax (VAT) 5% of (G + H + I) 29.08
Total Unit Cost (G + H + I + J) 610.76
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(2)a Pavement Markings (Reflectorized Traffic Paint - White)


Unit of Measurement : sq.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (2 - 5 mt) 1 0.05 783.00 39.15


Minor Tools (10% of Labor) 19.75

Sub - Total for B 58.90


Total (A + B) 256.44
Output per hour = 10.00000 sq.m.
Direct Unit Cost (C ÷ D) 25.64

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reflectorized Traffic Paint (White) L 1.00 450.00 450.00


Miscellaneous (5% of above) 22.50

Sub - Total for F 472.50


Direct Unit Cost (E + F) 498.14
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 44.83
Contractor's Profit (CP) 8% of G 39.85
Value Added Tax (VAT) 5% of (G + H + I) 29.14
Total Unit Cost (G + H + I + J) 611.97
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(2)b Pavement Markings (Reflectorized Traffic Paint - Yellow)


Unit of Measurement : sq.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (2 - 5 mt) 1 0.05 783.00 39.15


Minor Tools (10% of Labor) 19.75

Sub - Total for B 58.90


Total (A + B) 256.44
Output per hour = 10.00000 sq.m.
Direct Unit Cost (C ÷ D) 25.64

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reflectorized Traffic Paint (Yellow) L 1.00 475.00 475.00


Miscellaneous (5% of above) 23.75

Sub - Total for F 498.75


Direct Unit Cost (E + F) 524.39
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 47.20
Contractor's Profit (CP) 8% of G 41.95
Value Added Tax (VAT) 5% of (G + H + I) 30.68
Total Unit Cost (G + H + I + J) 644.22
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 607(1) Reflective Pavement Studs


Unit of Measurement : ea.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Diamond Drill, CP-8 with attachment 1 1.00 201.25 201.25


b. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
c. Air Compressor (15 - 35 cfm) 1 1.00 205.00 205.00
Minor Tools (5% of Labor) 9.32

Sub - Total for B 611.32


Total (A + B) 797.65
Output per hour = 10.00000 ea.
Direct Unit Cost (C ÷ D) 79.76

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reflective Stud Catcheye Flush Surface pc. 1.00 3,465.00 3,465.00


180mm x 140mm (type depends on the req.)
b. Concrete Epoxy A & B L 0.012 1,200.00 14.40

Sub - Total for F 3,479.40


Direct Unit Cost (E + F) 3,559.16
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 320.32
Contractor's Profit (CP) 8% of G 284.73
Value Added Tax (VAT) 5% of (G + H + I) 208.21
Total Unit Cost (G + H + I + J) 4,372.43
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 607(2) Reflective Pavement Studs (4" RPM)


Unit of Measurement : ea.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Diamond Drill, CP-8 with attachment 1 1.00 201.25 201.25


b. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
c. Air Compressor (15 - 35 cfm) 1 1.00 205.00 205.00
Minor Tools (5% of Labor) 9.32

Sub - Total for B 611.32


Total (A + B) 797.65
Output per hour = 10.00000 ea.
Direct Unit Cost (C ÷ D) 79.76

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Reflective Stud Catcheye Raised Surface pc. 1.00 3,465.00 3,465.00


100mm x 100mm (type depends on the req.)
b. Concrete Epoxy A & B L 0.012 1,200.00 14.40

Sub - Total for F 3,479.40


Direct Unit Cost (E + F) 3,559.16
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 320.32
Contractor's Profit (CP) 8% of G 284.73
Value Added Tax (VAT) 5% of (G + H + I) 208.21
Total Unit Cost (G + H + I + J) 4,372.43
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 608(1) Furnishing and Placing Topsoil


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 247.72

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Plate Compactor (5 hp) 1 1.00 123.00 123.00


Minor Tools (10% of Labor) 24.77

Sub - Total for B 147.77


Total (A + B) 395.49
Output per hour = 1.25 cu.m.
Direct Unit Cost (C ÷ D) 316.39

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Topsoil cu.m. 1.05 490.00 514.50

Sub - Total for F 514.50


Direct Unit Cost (E + F) 830.89
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 74.78
Contractor's Profit (CP) 8% of G 66.47
Value Added Tax (VAT) 5% of (G + H + I) 48.61
Total Unit Cost (G + H + I + J) 1,020.75
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 608(2) Placing Topsoil


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 247.72

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Plate Compactor (5 hp) 1 1.00 123.00 123.00


Minor Tools (10% of Labor) 24.77

Sub - Total for B 147.77


Total (A + B) 395.49
Output per hour = 1.25 cu.m.
Direct Unit Cost (C ÷ D) 316.39

Name and Specification Unit Quantity Unit Cost Amount

Materials

Sub - Total for F 0.00


Direct Unit Cost (E + F) 316.39
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 28.48
Contractor's Profit (CP) 8% of G 25.31
Value Added Tax (VAT) 5% of (G + H + I) 18.51
Total Unit Cost (G + H + I + J) 388.69
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 609 Sprigging


Unit of Measurement : sq.m.
Output per hour : 35.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 247.72

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50


Minor Tools (10% of Labor) 24.77

Sub - Total for B 637.27


Total (A + B) 884.99
Output per hour = 35.00000 sq.m.
Direct Unit Cost (C ÷ D) 25.29
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Sprigs sq.m. 1.05 89.00 93.45


b. Fertilizer kg. 0.10 26.00 2.60

Sub - Total for F 96.05


Direct Unit Cost (E + F) 121.34
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 10.92
Contractor's Profit (CP) 8% of G 9.71
Value Added Tax (VAT) 5% of (G + H + I) 7.10
Total Unit Cost (G + H + I + J) 149.06
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 610 Sodding


Unit of Measurement : sq.m.
Output per hour : 25.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 381.18

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Water Truck/Pump (16000L) 1 0.50 2,450.00 1,225.00


Minor Tools (10% of Labor) 38.12

Sub - Total for B 1,263.12


Total (A + B) 1,644.30
Output per hour = 25.00000 sq.m.
Direct Unit Cost (C ÷ D) 65.77
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Sods sq.m. 1.05 89.00 93.45

Sub - Total for F 93.45


Direct Unit Cost (E + F) 159.22
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 14.33
Contractor's Profit (CP) 8% of G 12.74
Value Added Tax (VAT) 5% of (G + H + I) 9.31
Total Unit Cost (G + H + I + J) 195.60
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 611(1) Trees (Furnishing and Transplanting), 150mm dia. or less
Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (9 - 10 mt) 1 1.00 1,212.00 1,212.00


b. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00
c. Water Truck/Pump (16000L) 1 0.50 2,450.00 1,225.00
Minor Tools (10% of Labor) 19.75

Note: Includes watering for three (3) months

Sub - Total for B 3,993.75


Total (A + B) 4,191.29
Output per hour = 1.00000 ea.
Direct Unit Cost (C ÷ D) 4,191.29
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Trees (Delivered at Site) pc. 1.00 400.00 400.00


b. Fertilizers kg. 3.00 26.00 78.00
c. Bamboo Pole pc. 3.00 50.00 150.00
d. Polyethylene Sheets sq.m. 3.00 10.00 30.00
e. Tie Wire kg. 0.25 46.67 11.67

Sub - Total for F 669.67


Direct Unit Cost (E + F) 4,860.96
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 437.49
Contractor's Profit (CP) 8% of G 388.88
Value Added Tax (VAT) 5% of (G + H + I) 284.37
Total Unit Cost (G + H + I + J) 5,971.69
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 611(2) Trees (Transplanting), 150mm dia. or less


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (9 - 10 mt) 1 1.00 1,212.00 1,212.00


b. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00
c. Water Truck/Pump (16000L) 1 0.50 2,450.00 1,225.00
Minor Tools (10% of Labor) 19.75

Sub - Total for B 3,993.75


Total (A + B) 4,191.29
Output per hour = 1.00000 ea.
Direct Unit Cost (C ÷ D) 4,191.29
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Fertilizers kg. 3.00 26.00 78.00


b. Bamboo Pole pc. 3.00 50.00 150.00
c. Polyethylene Sheets sq.m. 3.00 10.00 30.00
d. Tie Wire kg. 0.25 46.67 11.67

Sub - Total for F 269.67


Direct Unit Cost (E + F) 4,460.96
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 401.49
Contractor's Profit (CP) 8% of G 356.88
Value Added Tax (VAT) 5% of (G + H + I) 260.97
Total Unit Cost (G + H + I + J) 5,480.29
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 612(1) Reflectorized Thermoplastic Pavement Markings (White)


Unit of Measurement : sq.m.
Output per hour : 25.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 6 1.00 38.97 233.82

Sub - Total for A 403.60

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

b. Cargo Truck/Delivery Truck(2 - 5 mt) 1 1.00 783.00 783.00


b. Applicator Machine 1 1.00 93.75 93.75
c. Kneading Machine 1 1.00 187.50 187.50
Minor Tools (10 % of Labor Cost) 40.36

Sub - Total for B 1,104.61


Total (A + B) 1,508.21
Output per hour = 25.00000 sq.m.
Direct Unit Cost (C ÷ D) 60.33
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Thermoplastic Paint (White) bag 0.325 1,565.00 508.63


b. Glass Beads bag 0.033 650.00 21.45
c. Primer L 0.120 160.00 19.20
d. LPG (50 kg.) cyl. 0.004 3,800.00 15.20
e. LPG (12 kg.) cyl. 0.002 735.00 1.47
f. Calsumine kg. 0.125 3.00 0.38
Miscellaneous (5% of Materials) 28.32

Sub - Total for F 594.64


Direct Unit Cost (E + F) 654.96
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 58.95
Contractor's Profit (CP) 8% of G 52.40
Value Added Tax (VAT) 5% of (G + H + I) 38.32
Total Unit Cost (G + H + I + J) 804.62
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 612(2) Reflectorized Thermoplastic Pavement Markings (Yellow)


Unit of Measurement : sq.m.
Output per hour : 25.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 2 1.00 50.18 100.36
c. Unskilled Labor 6 1.00 38.97 233.82

Sub - Total for A 403.60

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

b. Cargo Truck/Delivery Truck(2 - 5 mt) 1 1.00 783.00 783.00


b. Applicator Machine 1 1.00 93.75 93.75
c. Kneading Machine 1 1.00 187.50 187.50
Minor Tools (10 % of Labor Cost) 40.36

Sub - Total for B 1,104.61


Total (A + B) 1,508.21
Output per hour = 25.00000 sq.m.
Direct Unit Cost (C ÷ D) 60.33
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Thermoplastic Paint (Yellow)) bag 0.325 1,780.00 578.50


b. Glass Beads bag 0.033 650.00 21.45
c. Primer L 0.120 175.00 21.00
d. LPG (50 kg.) cyl. 0.004 3,800.00 15.20
e. LPG (12 kg.) cyl. 0.002 735.00 1.47
f. Calsumine kg. 0.125 3.00 0.38
Miscellaneous (5% of Materials) 31.90

Sub - Total for F 669.89


Direct Unit Cost (E + F) 730.22
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 65.72
Contractor's Profit (CP) 8% of G 58.42
Value Added Tax (VAT) 5% of (G + H + I) 42.72
Total Unit Cost (G + H + I + J) 897.08
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 613 Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types)
Unit of Measurement : kg.
Output per hour : 20.00
.

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 6 1.00 38.97 233.82

Sub - Total for A 303.24

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Asphalt Kettle/Drum 1 1.00 10.00 10.00


Minor Tools (5% of Labor) 15.16

Sub - Total for B 25.16


Total (A + B) 328.40
Output per hour = 20.0000 kg.
Direct Unit Cost (C ÷ D) 16.42
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Blown Asphalt kg. 1.05 250.00 262.50


Miscellaneous (5% of Materials) 13.13

Sub - Total for F 275.63


Direct Unit Cost (E + F) 292.05
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 26.28
Contractor's Profit (CP) 8% of G 23.36
Value Added Tax (VAT) 5% of (G + H + I) 17.08
Total Unit Cost (G + H + I + J) 358.78
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 620(a) Chevron Signs (450mmx600mm)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


Minor Tools (10 % of Labor) 19.75

Sub - Total for B 215.50


Total (A + B) 413.04
Output per hour = 1.00000 ea.
Direct Unit Cost (C ÷ D) 413.04
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Portland Cement bag 0.48 220.00 105.60


b. Sand cu.m. 0.025 850.00 21.25
c. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.ft. 8.00 40.00 80.00
e. 75mm Ø G.I. Pipe m. 3.25 530.00 1,722.50
f. G.I. Flat Bar, 1 1/2"x1/8" kg. 5.00 48.00 240.00
g. G.I. Bolts w/ Nuts & Washer, 5mm Ø pc. 3.00 10.00 30.00
h. G.I. Bolts w/ Nuts & Washer, 2mm Ø pc. 12.00 10.00 120.00
i. Sign Face, 3mm thk. Aluminum Sheet pc. 2.00 3,750.00 7,500.00
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44
Miscellaneous (0.3% of Materials) 29.57

Sub - Total for F 9,886.86


Direct Unit Cost (E + F) 10,299.91
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 926.99
Contractor's Profit (CP) 8% of G 823.99
Value Added Tax (VAT) 5% of (G + H + I) 602.54
Total Unit Cost (G + H + I + J) 12,653.43
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 620(b) Chevron Signs (600mmx800mm)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 197.54

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


Minor Tools (10 % of Labor) 19.75

Sub - Total for B 215.50


Total (A + B) 413.04
Output per hour = 1.00000 ea.
Direct Unit Cost (C ÷ D) 413.04
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Portland Cement bag 0.48 220.00 105.60


b. Sand cu.m. 0.025 850.00 21.25
c. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.ft. 8.00 40.00 80.00
e. 75mm Ø G.I. Pipe m. 3.45 530.00 1,828.50
f. G.I. Flat Bar, 1 1/2"x1/8" kg. 5.00 48.00 240.00
g. G.I. Bolts w/ Nuts & Washer, 5mm Ø pc. 3.00 10.00 30.00
h. G.I. Bolts w/ Nuts & Washer, 2mm Ø pc. 12.00 10.00 120.00
i. Sign Face, 3mm thk. Aluminum Sheet pc. 2.00 7,500.00 15,000.00
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00 5.44
Miscellaneous (0.2% of Materials) 34.93

Sub - Total for F 17,498.22


Direct Unit Cost (E + F) 17,911.26
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 1,612.01
Contractor's Profit (CP) 8% of G 1,432.90
Value Added Tax (VAT) 5% of (G + H + I) 1,047.81
Total Unit Cost (G + H + I + J) 22,003.98
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(1)a Bio-Engineering Solutions (Coco-net)


Unit of Measurement : sq.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 381.18

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50


Minor Tools (10% of Labor) 38.12

Sub - Total for B 650.62


Total (A + B) 1,031.80
Output per hour = 50.0000 sq.m.
Direct Unit Cost (C ÷ D) 20.64
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Erosion Control Net CGN 400 w/ 5 % wastage sq.m. 1.05 110.00 115.50
(Price includes bamboo pegs)

Sub - Total for F 115.50


Direct Unit Cost (E + F) 136.14
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 12.25
Contractor's Profit (CP) 8% of G 10.89
Value Added Tax (VAT) 5% of (G + H + I) 7.96
Total Unit Cost (G + H + I + J) 167.24
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(1)b Bio-Engineering Solutions (Coco-net)


Unit of Measurement : sq.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 381.18

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50


Minor Tools (10% of Labor) 38.12

Sub - Total for B 650.62


Total (A + B) 1,031.80
Output per hour = 50.0000 sq.m.
Direct Unit Cost (C ÷ D) 20.64
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Erosion Control Net CGN 700 w/ 5 % wastage sq.m. 1.05 156.00 163.80
(Price includes bamboo pegs)

Sub - Total for F 163.80


Direct Unit Cost (E + F) 184.44
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 16.60
Contractor's Profit (CP) 8% of G 14.75
Value Added Tax (VAT) 5% of (G + H + I) 10.79
Total Unit Cost (G + H + I + J) 226.58
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(2)a Bio-Engineering Solutions (Coco-logs/Fascine)


Unit of Measurement : m
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

Minor Tools (10% of Labor) 14.74

Sub - Total for B 14.74


Total (A + B) 162.10
Output per hour = 15.0000 m.
Direct Unit Cost (C ÷ D) 10.81
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Coco Fiber Roll (CGR 200) m 1.05 388.00 407.40


(Price includes nylon ropes and live stakes)

Sub - Total for F 407.40


Direct Unit Cost (E + F) 418.21
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 37.64
Contractor's Profit (CP) 8% of G 33.46
Value Added Tax (VAT) 5% of (G + H + I) 24.47
Total Unit Cost (G + H + I + J) 513.77
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(2)b Bio-Engineering Solutions (Coco-logs/Fascine)


Unit of Measurement : m
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 381.18

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

Minor Tools (10% of Labor) 38.12

Sub - Total for B 38.12


Total (A + B) 419.30
Output per hour = 15.0000 m.
Direct Unit Cost (C ÷ D) 27.95
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Coco Fiber Roll (CGR 300) m 1.05 509.00 534.45


(Price includes nylon ropes and live stakes)

Sub - Total for F 534.45


Direct Unit Cost (E + F) 562.40
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 50.62
Contractor's Profit (CP) 8% of G 44.99
Value Added Tax (VAT) 5% of (G + H + I) 32.90
Total Unit Cost (G + H + I + J) 690.91
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(3)a Bio-Engineering Solutions (Vegetation)


Unit of Measurement : sq.m.
Output per hour : 62.50

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Hydroseeding Machine 1 1.00 952.00 952.00


b. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
(including maintenance time)

Sub - Total for B 3,402.00


Total (A + B) 3,549.36
Output per hour = 62.500 sq.m.
Direct Unit Cost (C ÷ D) 56.79
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Grass Cover sq.m. 1.05 45.00 47.25


(Price includes grass seeds, mulch, cocopeat
& binding agent for hydroseeding)

Sub - Total for F 47.25


Direct Unit Cost (E + F) 104.04
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 9.36
Contractor's Profit (CP) 8% of G 8.32
Value Added Tax (VAT) 5% of (G + H + I) 6.09
Total Unit Cost (G + H + I + J) 127.81
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(3)b Bio-Engineering Solutions (Vegetation)


Unit of Measurement : sq.m.
Output per hour : 35.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 381.18

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Water Truck/Pump (16000L) 1 0.50 2,450.00 1,225.00


Minor Tools (10% of Labor) 38.12

Sub - Total for B 1,263.12


Total (A + B) 1,644.30
Output per hour = 35.0000 sq.m.
Direct Unit Cost (C ÷ D) 46.98
Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Vetiver Grass System sq.m. 1.05 70.00 73.50


(Price includes cocopeat fertilizer)

Sub - Total for F 73.50


Direct Unit Cost (E + F) 120.48
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 10.84
Contractor's Profit (CP) 8% of G 9.64
Value Added Tax (VAT) 5% of (G + H + I) 7.05
Total Unit Cost (G + H + I + J) 148.01
ITEM NO. DESCRIPTION

PART C EARTHWORKS
100(1) Clearing and Grubbing (with Stripping)
100(2)a Individual Removal of Trees (small a,150-300mm Ø)
100(2)b Individual Removal of Trees (small b, 301-500mm Ø)
100(3)a Individual Removal of Trees (large a, 501-750mm Ø)
100(3)b Individual Removal of Trees (large b, 751-900mm Ø)
101(1) Removal of Structures and Obstruction (other than concrete)
101(2) Removal of Concrete Bridge Structures
101(2) Removal of Steel Bridge Structures
101(2) Removal of Stone Masonry Lined Drainage Structures
101(2) Removal of Concrete Drainage Structures
101(2)a Removal of RCPC (24" dia.) - 610mm
101(2)b Removal of RCPC (30" dia.) - 760mm
101(2)c Removal of RCPC (36" dia.) - 910mm
101(2)d Removal of RCPC (42" dia.) - 1070mm
101(2)e Removal of RCPC (48" dia.) - 1220mm
101(2)f Removal of RCPC (60" dia.) - 1520mm
101(2)g Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200mm Ø), L = 10 ft.
101(3)a.1 Removal of Existing Concrete Pavement (0.23m thk.)
101(3)a.2 Removal of Existing PCC Pavement, 0.23m thk. (for Reblocking at intermittent section))
101(3)b Removal of Existing Asphalt Pavement (100mm thk.)
101(3)c Removal of Sidewalk
101(4)a Removal of Curb
101(4)b Removal of Existing Curbs & Gutter
102(1) Roadway Excavation (Unsuitable)
102(2)a Roadway Excavation (Surplus Common)
102(2)b Roadway Excavation (Surplus Common) - w/ Backhoe
102(3)a Roadway Excavation (Surplus Soft Rock) - w/ Backhoe
102(3)b Roadway Excavation (Surplus Soft Rock)
102(3)c Roadway Excavation (Surplus Hard Rock) - Blasting
102(3)d Roadway Excavation (Surplus Hard Rock) - Blasting (Tunnel Excavation)
102(4) Roadway Excavation (Unclassified)
103(1)a Structure Excavation (Common Soil)
103(1)b Structure Excavation (Soft Rock)
103(1)c Structure Excavation (Solid Rock)
103(2)a Bridge Excavation (Common Soil)
103(2)b Bridge Excavation (Soft Rock)
103(2)c Bridge Excavation (Solid Rock)
103(3) Foundation Fill
103(4) Excavation ordered below Plan Elevation
103(5)a Shoring
103(5)b Cribbing/Cofferdamming
103(6) Pipe Culvert and Drain Excavation
ITEM NO. DESCRIPTION
104(1)a Embankment from Borrow
104(1)b Embankment from Roadway Excavation
ITEM NO. DESCRIPTION
104(2) Selected Borrow for topping, case 1
104(3) Selected Borrow for topping, case 2
104(4) Earth Berm
105(1) Subgrade Preparation (Common Material)
105(2) Subgrade Preparation (Existing Pavement)
105(3) Subgrade Preparation (Unsuitable Material)
PART D SUBBASE AND BASE COURSE
200 Aggregate Subbase Course
200(1) Aggregate Subbase Course (for intermittent Reblocking)
201 Aggregate Base Course
201(1) Aggregate Base Course (for Reblocking)
202 Crushed Aggregate Base Course
203 Lime Stabilized Road Mix Base Course
204 Portland Cement Stabilized Road Mix Base Course
205 Asphalt Stabilized Road Mix Base Course
206 Portland Cement Treated Plant Mix Base Course
PART E SURFACE COURSE
300(1) Gravel Surface Course (Uncrushed)
300(2) Crushed Aggregate Surface Course
301(1) Bituminous Prime Coat (MC Cut-back Asphalt)
301(2) Bituminous Prime Coat (RC Cut-back Asphalt)
302(1) Bituminous Tack Coat (RC Cut-back Asphalt)
302(2) Bituminous Tack Coat (Emulsified Asphalt)
303(1) Bituminous Seal Coat (Cover Aggregate)
303(2) Bituminous Seal Coat (MC Cut-back Asphalt)
303(3) Bituminous Seal Coat (RC Cut-back Asphalt)
303(4) Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150)
304(1) Bituminous Surface Treatment (Aggregate Grading)
304(2) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150)
304(3) Bituminous Surface Treatment (MC Cut-back Asphalt)
304(4) Bituminous Surface Treatment (RC Cut-back Asphalt)
304(5) Bituminous Surface Treatment (Emulsified Asphalt)
305(1) Bituminous Penetration Macadam Pavement (Aggregates)
305(2) Bituminous Penetration Macadam Pavement (Asphalt Cement)
305(3) Bituminous Penetration Macadam Pavement (RC Cut-back Asphalt)
305(4) Bituminous Penetration Macadam Pavement (Emulsified Asphalt)
306(a) Bituminous Road Mix Surface Course (MC Cut-back Asphalt)
306(b) Bituminous Road Mix Surface Course (Emulsified Asphalt)
306(1) Aggregate for Bituminous Road Mix Surface Course
306(2) Bituminous Material for Bituminous Road Mix Surface Course
307 Bituminous Plant Mix Surface Course-General - 50mm thk.
308(a) Cold Asphalt Plant Mix (Emulsified Asphalt) - 50mm thk.
308(b) Cold Asphalt Plant Mix (Cut-back Asphalt) - 50mm thk.
309 Bituminous Plant Mix (Stockpile Maintenance Mixture)
ITEM NO. DESCRIPTION
310(a.1) Bituminous Concrete Surface Course, Hot Laid - 30mm thk. (Delivered)
ITEM NO. DESCRIPTION
310(a.2) Bituminous Concrete Surface Course, Hot Laid - 40mm thk. (Delivered)
310(a.3) Bituminous Concrete Surface Course, Hot Laid - 50mm thk. (Delivered)
310(b.1) Bituminous Concrete Surface Course, Hot Laid - 30mm thk. (Batching Plant)
310(b.2) Bituminous Concrete Surface Course, Hot Laid - 40mm thk. (Batching Plant)
310(b.3) Bituminous Concrete Surface Course, Hot Laid - 50mm thk. (Batching Plant)
311(1)a.1 PCC Pavement (Plain) - Conventional Method, 150mm thk.
311(1)a.2 PCC Pavement (Plain) - Conventional Method, 200mm thk.
311(1)a.3 PCC Pavement (Plain) - Conventional Method, 230mm thk.
311(1)a.4 PCC Pavement (Plain) - Conventional Method, 250mm thk.
311(1)a.5 PCC Pavement (Plain) - Conventional Method, 280mm thk.
311(1)a.6 PCC Pavement (Plain) - Conventional Method, 300mm thk.
311(1)b.1 PCC Pavement (Plain) - Using Concrete Paver, 230mm thk.
311(1)b.2 PCC Pavement (Plain) - Using Concrete Paver, 250mm thk.
311(1)b.3 PCC Pavement (Plain) - Using Concrete Paver, 280mm thk.
311(1)b.4 PCC Pavement (Plain) - Using Concrete Paver, 300mm thk.
311(1)c PCC Pavement (Plain) - Conventional Method, 150mm thk. (Using One Bagger Mixer)
311(2) PCC Pavement (Reinforced), 230mm thk.
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
404 Reinforcing Steel Bar, Grade 40 (Minor Structures)
405 Structural Concrete Class A (Minor Structures)
500(1)a Pipe Culverts, 610mm dia. (24" Ø)
500(1)b Pipe Culverts, 760mm dia. (30" Ø)
500(1)c Pipe Culverts, 910mm dia. (36" Ø)
500(1)d Pipe Culverts, 1070mm dia. (42" Ø)
500(1)e Pipe Culverts, 1220mm dia. (48" Ø)
500(1)f Pipe Culverts, 1520mm dia. (60" Ø)
501(1) Underdrain
501(2) Blind drain
501(3) Granular Backfill filter material for Underdrains
502 Manhole/Catch Basin/Inlet
502(4) Concrete Covers
502(5) Metal Frames and Gratings
502(6) Metal Frames and Covers (Circular)
503(a) Drainage Steel Grating w/ Frame (675mm x 975mm Sump Grating)
503(b) Drainage Steel Grating w/ Frame (715mm x 2000mm Trench Grating)
504(1)a Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (24" dia.) - 610mm
504(1)b Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" dia.) - 760mm
504(1)c Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" dia.) - 910mm
504(1)d Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" dia.) - 1070mm
504(1)e Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" dia.) - 1220mm
504(2)a Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (24" dia.) - 610mm
504(2)b Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (30" dia.) - 760mm
504(2)c Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (36" dia.) - 910mm
504(2)d Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070mm
ITEM NO. DESCRIPTION
504(2)e Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220mm
504(3)a Cleaning Culvert Pipe in place (610mm dia.) - Half Silted
504(3)b Cleaning Culvert Pipe in place (760mm dia.) - Half Silted
504(3)c Cleaning Culvert Pipe in place (910mm dia.) - Half Silted
504(3)d Cleaning Culvert Pipe in place (1070mm dia.) - Half Silted
504(3)e Cleaning Culvert Pipe in place (1220mm dia.) - Half Silted
504(3)f Cleaning Culvert Pipe in place (1520mm dia.) - Half Silted
504(4) Reconditioning Drainage Structures
505(1) Riprap, Class A
505(2) Riprap, Class B
505(3) Riprap, Class C
505(4) Riprap, Class D
505(5) Grouted Riprap, Class A
505(6) Grouted Riprap, Class B
505(7) Grouted Riprap, Class C
505(8) Grouted Riprap, Class D
505(9) Filter Layer of Granular Material
506 Stone Masonry
507 Rubble Concrete
508 Hand-Laid Rock Embankment
509(a) Sheet Piles (Timber)
509(b.1) Sheet Piles (Steel) - Slope Protection
509(b.2) Sheet Piles (Steel) - Cofferdamming
509(c) Sheet Piles (Concrete), furnished and driven
510(1) Bed Course Granular Material
510(2) Concrete Slope Protection
511(1) Gabions
511(2) Mattresses
511(3) Filter Cloth
PART H MISCELLANEOUS STRUCTURES
600(1) Concrete Curb (Cast in place)
600(2) Concrete Gutter (Cast in place)
600(3) Concrete Curb and Gutter, Type A (Cast in place) - National Road
600(4) Concrete Curb (Precast)
600(5) Concrete Gutter (Precast)
600(6) Concrete Curb & Gutter (Precast)
601(a) Sidewalk (100mm thk.)
601(b) Sidewalk - Using One Bagger Mixer, (100mm thk.)
602(1)a Right-of-Way Monuments (Cast in place)
602(1)b Right-of-Way Monuments (Precast)
602(2)a Maintenance Marker Posts (Cast in place)
602(2)b Maintenance Marker Posts (Precast)
602(3)a Kilometer Post (Cast in Place)
602(3)b Kilometer Post (Precast)
ITEM NO. DESCRIPTION
602(4) Guide Post
603(1) Cable Wire Guardrail
603(3)a Metal Guardrail (Metal Beam) including Concrete Post
603(3)b Metal Beam End Piece
603(4) Guardrail (Timber)
604(1) Fencing (Barbed Wire)
604(2) Fencing (Chain Link Fence Fabric)
604(3) Fencing (Posts)
604(4) Fencing (Gates) - (Height = 3m & length = 4.24m)
605(1)a Danger/Warning Signs (60cm Triangle)
605(1)b Danger/Warning Signs (90cm Triangle)
605(2)a Regulatory Signs (60cm Triangle)
605(2)b Regulatory Signs (90cm Triangle)
605(2)c Regulatory Signs (60cm Octagon)
605(2)d Regulatory Signs (90cm Octagon)
605(3)a Informative Signs (12" x 24")
605(3)b Informative Signs (12" x 48")
605(3)c Informative Signs (18" x 24")
605(3)d Informative Signs (18" x 48")
606(1) Pavement Markings (Premix Reflectorized)
606(2)a Pavement Markings (Reflectorized Thermoplastic), White
606(2)b Pavement Markings (Reflectorized Thermoplastic), Yellow
607(1) Reflectorized Pavement Studs (Flush Type)
607(2) Reflectorized Pavement Studs (Raised Profile Type)
608(1) Furnishing and Placing Topsoil
608(2) Placing Topsoil
609 Sprigging
610 Sodding
611(1) Trees (Furnishing and Transplanting), 150mm dia. or less
611(2) Trees (Transplanting), 150mm dia. or less
612(1) Reflectorized Thermoplastic Pavement Markings (White)
612(2) Reflectorized Thermoplastic Pavement Markings (Yellow)
613 Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types)
620(a) Chevron Signs (450mmx600mm)
620(b) Chevron Signs (600mmx800mm)
622(1)a Bio-Engineering Solutions (Coco-net), CGN 400
622(1)b Bio-Engineering Solutions (Coco-net), CGN 700
622(2)a Bio-Engineering Solutions (Coco-logs/Fascine), CGR 200
622(2)b Bio-Engineering Solutions (Coco-logs/Fascine), CGR 300
622(3)a Bio-Engineering Solutions (Vegetation), Hydroseeding
622(3)b Bio-Engineering Solutions (Vegetation), Vetiver Grass System
PART J SPECIAL ITEMS
SPL 2(a) Crack and Seat - Using Backhoe
SPL 2(b) Crack and Seat - Using Arrow Master
ITEM NO. DESCRIPTION
SPL 3(a) Tree Planting - With Tree Guard
SPL 3(b) Tree Planting
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 2(a) Crack and Seat Item


Unit of Measurement : sq.m. Unit
Output per hour : 35.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77

Name and Capacity No of Units No. of Hours Rental Rate Amount

B. Equipment B.

a. Backhoe w/ Breaker (0.80 cu.m.) 1 1.00 2,074.95 2,074.95


b. Vibratory Roller (10 m.t.), SP56 1 0.75 1,507.00 1,130.25
c. Water Truck (1000 gal.) 1 0.10 1,065.00 106.50

Sub - Total for B 3,311.70


C. Total (A + B) 3,623.47 C.
D. Output per hour = 35.0000 sq.m. D.
E. Direct Unit Cost (C ÷ D) 103.53 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 103.53 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 9.32 H.
I. Contractor's Profit (CP) 8% of G 8.28 I.
J. Value Added Tax (VAT) 12% of (G + H + I) 14.54 J.
K. Total Unit Cost (G + H + I + J) 135.66 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 2(b) Crack and Seat Item


Unit of Measurement : sq.m. Unit
Output per hour : 30.00 Out

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor A.

a. Construction Foreman 1 1 109.19 109.19


b. Skilled Laborer 1 1 79.70 79.70
c. Laborer 2 1 61.44 122.88

Sub - Total for A 311.77

Name and Capacity No of Units No. of Hours Rental Rate Amount

B. Equipment B.

a. Arrow Master D 500 1 1.00 1,485.84 1,485.84


(Additional 35% for Oil and Lubricants)
b. Vibratory Roller (10 m.t.), SP56 1 0.75 1,507.00 1,130.25
c. Water Truck (1000 gal.) 1 0.10 1,065.00 106.50

Sub - Total for B 2,722.59


C. Total (A + B) 3,034.36 C.
D. Output per hour = 30.0000 sq.m. D.
E. Direct Unit Cost (C ÷ D) 101.15 E.

Name and Specification Unit Quantity Unit Cost Amount

F. Materials F.

Sub - Total for F 0.00


G. Direct Unit Cost (E + F) 101.15 G.
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 9.10 H.
I. Contractor's Profit (CP) 8% of G 8.09 I.
J. Value Added Tax (VAT) 12% of (G + H + I) 14.20 J.
K. Total Unit Cost (G + H + I + J) 132.54 K.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 3(a) Tree Planting


Unit of Measurement : pc.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 10 1 61.44 614.40

Sub - Total for A 723.59

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (5 T) 1 0.25 712.00 178.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 72.36

Sub - Total for B 516.61


Total (A + B) 1,240.20
Output per hour = 60.0000 pc.
Direct Unit Cost (C ÷ D) 20.67

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Saplings pc. 1 50.00 50.00


b. Coco Lumber bd.ft. 8 20.00 160.00
c. Assorted CWN (1 kg./100 bd.ft.) kg. 0.08 68.00 5.44
d. Fertilizers kg. 0.10 50.00 5.00

Sub - Total for F 220.44


Direct Unit Cost (E + F) 241.11
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 21.70
Contractor's Profit (CP) 8% of G 19.29
Value Added Tax (VAT) 12% of (G + H + I) 33.85
Total Unit Cost (G + H + I + J) 315.95
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 3(b) Tree Planting


Unit of Measurement : pc.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount

Labor

a. Construction Foreman 1 1 109.19 109.19


b. Laborer 10 1 61.44 614.40

Sub - Total for A 723.59

Name and Capacity No of Units No. of Hours Hourly Rate Amount

Equipment

a. Cargo Truck (5 T) 1 0.25 712.00 178.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 72.36

Sub - Total for B 516.61


Total (A + B) 1,240.20
Output per hour = 60.0000 pc.
Direct Unit Cost (C ÷ D) 20.67

Name and Specification Unit Quantity Unit Cost Amount

Materials

a. Saplings pc. 1 50.00 50.00


b. Fertilizers kg. 0.10 26.00 2.60

Sub - Total for F 52.60


Direct Unit Cost (E + F) 73.27
Overhead, Contingencies & Miscellaneous (OCM) 9% of G 6.59
Contractor's Profit (CP) 8% of G 5.86
Value Added Tax (VAT) 12% of (G + H + I) 10.29
Total Unit Cost (G + H + I + J) 96.01

You might also like