Kill Sheet For Vertical Wells

Drillstring Volume Annular Volume


Other Calculations
(BBLS) (BBLS)
LENGTH CAPACITY VOLUME LENGTH CAPACITY VOLUME
(FT) (BBLS/FT) (BBLS) (FT) (BBLS/FT) (BBLS) Previous Casing Depth 1610 ft
Drillpipe String & Casing
1000 × 0.07 = 70 × = 0 LOT Pressure (psi) 412 psi
LOT Original MW (ppg) 9.4 ppg
× = 0 1600 × 0.0773 = 123.68 LOT Equivalent (ppg) 14.32 ppg
String & Open Hole
3290 × 0.007421 = 24.41509 × = 0 MASCP 361.768 psi
BHA 2690 × 0.02454 = 66.0126
700 × 0.004387 = 3.07062 × = 0 Strokes to Bit 1,406 stks
185 × 0.00491 = 0.90835 885 × 0.01452 = 12.8502 Bitto Surface Strokes 2,893 stks
Total Circulation for Well 4,299 stks
Tot. String Len. 5175 Tot. String Vol. 98.39406 Tot. Ann. Len. 5175 Tot. Ann. Vol. 202.5428 Initial Circulating Pressure 286 psi
Final Circulating Pressure 107 psi

Well Information DP Pressure Time to Bit 28 min


and Kick Data Schedule Time from bit to Surface 58 min
Total Time to Circulate Kick Out 86 min
Circ.
Mud Weight (ppg) 10 Strokes Pressure 1.43 hrs
(Psi)
Total Vertical Depth (ft) 5,173
Total Measured Depth (ft) 5,175 0 286 ICP
141 268 Well Kill Chart
Slow Pump Pressure (psi) 100 281 250
350
Slow Pump Speed (spm) 50 422 232
Pump Output (bbls/stk) 0.07 562 214 300

Circulating Pressure
703 196 250
Shut-In Drillpipe Pressure (psi) 186 843 179
200
Shut-In Casing Pressure (psi) 100 984 161
Pit Gain (bbls) 20 1125 143 150
1265 125 100
Strokes to Bit 1406 107 FCP
50
Well Name BA 2535
Well Location 1405.629 0
Rig UMP-102 Strokes Increment (stks) 141 0 200 400 600 800 1000 1200 1400 1600
Drilling Contractor SDS Kill Weight Mud (ppg) 10.7 Strokes
Time of Event Reduction in Pump Pressure (psi) 17.9