A/M VAITHIYANATHA SWAMY TEMPLE,VAITHEESHWARAN KOVIL

FLOORING NEW STONE WORK & REFIXING,POINTING ESTIMATE


1 New Stone Flooring Work ; Swamy Maha Mandabam 840sqft
35.0 X 24.0
2 Swamy Sobana Mandapam
47.9 X 28.0 1337sqft
19.0 X 6.6 123.50 Sqft
3 Selva Muthukumara Swamy Sannathi
15.0 X 15.0 225sqft
33.0 X 56.0 1848sqft
4 Somaskandhar Mandapam
56.0 X 32.9 1834sqft
5 Ambal Maha Mandabam East Side, Center Stage
21.3 X 6.0 127.50sqft
7.0 X 7.0 49.0sqft
6 Ambal Sobanamandapam
63.0 X 38.0 2394sqft
7 Karthigai Mandabam Center
106.0 X 19.0 2014sqft
TOTAL 10792SQFT

1 Removing Old Stone


10792 Sqft X 25.0 2,69,800.00
Removing Deprices 75,000.00
2 Sand Filling 54unit
54 X 8500 4,59,000.00
3 New Cut Stone,Dressing,Sand Filling,Laying,Pointing Including
Cost And Convenience 10792 X 350.00 37,77,200.00
4 Transport,Loading & Unloading 1,95,000.00
47,76,000.00
GST 12% 5,73,120.00
TOTAL 53,49,120.00
SWAMY KODIMARA MANDAPAM SOUTH SIDE
OLD STONE REFIXING

1 Removing Old Kadappa Slab & Stone


3500 Sqft X 25 87,500.00
2 Old Depress Removing 35,000.00
3 Sand Filling Unit 17.50 X 8500 1,48,750.00
4 Refixing Old Stone Pointing 3500 X 150 5,25,000.00
Total 7,96,250.00

OLD STONE POINTING WORK


1 Swamy Inner Prahara Mandapam
2 Swamy Kodimara Mandapam
3 Karthigai Mandapam West,East Side
4 Pathrakaliyamman Mandapam
5 Guga Sandeshwarar Mandapam
1814 Sqft X 340 = 6,16,760.00
A/M VAITHIYANATHA SWAMY TEMPLE
VAITHEESHWARAN KOVIL

1 NEW STONE WORK 53,49,120.00

2 OLD STONE REFIXING 7,96,250.00

3 OLD STONE POINTING WORK 6,16,760.00


TOTAL 67,62,130.00