JOINT INSPECTION FOR COMPLETION

FOR RECTIFICATION WORK


Page 1/2
FINISHING CHECKLIST
ARCHITECTURAL (INTERIOR)
Contract Package 1 : Terminal
RFI No : PTRPW-PTBP1-RFI-BLDG-xxx
Construction
Date : xxxxx
PREPARED BY : PatimOne Consul
Time :
LOCATION RECLAMATION - ADMI BUILDING B
ITEM COMMENTS
Comments on Inspection on 23th March 2021 ACTION BY CONFIRMATION BY
PTRPW PATIMONE CONSUL
1. Lobby B
1.1 Floor :
Nat ceramic shall be regrouting
Border ceramic shall be remove and replace Not yet Not yet
Need cleanless
( Picture x.1a-1e)
1.2
Ceiling : Already Closed
S make good platnes and frame

Wall :
Plastered shall be smooting, painting shaal be repainting, No Activity No Activity
1.3 partition/interior wall shall be reparired
(picture x.1a-x.1e/x.1a-x.1d)

Window&doors :
Horizontality and verticality Frame door shall be repaired

2. Corridor 1 B

2.1 Floor :
Nat ceramic shall be repaired
Border ceramic shall be remove and replace
Need cleanless
( Picture x.1a-1e)

Ceiling :
Shall be repaired platnes and frame

Wall :
Plastered shall be smooting, painting shaal be repainting,
partition/interior wall shall be reparired
(picture x.1a-x.1e/x.1a-x.1d)

Window&doors :

-
-
This Site Inspection Sheet is correctly recorded.

Inspection by Checked by Approved by Inspection by


Inspector Engineer in Charge Chief Resident Engineer Contractor

Mr. Tatang Sutisna Mr. Khairil Mr. Horigome Mr. M Abel Firdaus
Building Inspector. Architect Building Engineer Archi/Building Engineer